SUPREME COURT OF INDIA
J.B. PARDIWALA, K. V. VISWANATHAN, JJ.
Tamil Nadu Generation And Distribution Corporation Ltd. – Appellant
Versus
M/s Penna Electricity Limited – Respondent
Civil Appeal No. 5700 of 2014
Decided On : 16-12-2025
| Table of Content |
|---|
| 1. overview of the case and findings by aptel. (Para 1 , 2) |
| 2. appellant's arguments regarding cod and infirm power. (Para 3 , 9) |
| 3. findings of tnerc on ppa alignment with regulations. (Para 4 , 5) |
| 4. aptel's findings on the legal status of ppa. (Para 7 , 8) |
| 5. discussion on legal principles governing the tariff regulations. (Para 11 , 12 , 29) |
| 6. analysis of power categorization as firm/infirm. (Para 30 , 34) |
| 7. conclusion of the court on the appeal. (Para 37 , 38) |
JUDGMENT :
K.V. Viswanathan, J.
1. The present appeal calls in question the correctness of the judgment and order dated 10.07.2013 passed by the Appellate Tribunal for Electricity (for short ‘APTEL’) in Appeal No.112 of 2012.
2. The Tamil Nadu Electricity Regulatory Commission (for short ‘TNERC’) and the APTEL have concurrently found in favour of the respondent. It has been held that the power generated by the respondent by the open cycle gas turbine for the period from 29.10.2005 to 30.06.2006 (hereinafter called as ‘Relevant Period’) and supplied to the appellant could not be termed as “infirm power” and that it could only be treated as “firm power”. The consequence of the said finding was that the Commercial Operation Date (for short the ‘COD’) for the Gas Turbine in Open Cyc006Ce was held to be 29.10.2005 (i.e. the synchronization date) and since power was delivered on a continuous basis, the appellant was ordered to pay fixed charges for the relevant period.
3. Aggrieved, the appellant is in appeal. The principal argument is that any sale of electricity prior to “COD” would be infirm power and would entail the supplier only to variable charges i.e., the cost of the fuel. To support this, the appellant relies on the clause in the Power Purchase Agreement (for short ‘PPA’) originally entered on 29.04.1998 and undisputedly amended on 25.08.2004. According to the appellant, under the PPA, as amended, date of commercial operation was the day on which the project achieved entry into commercial operation i.e., 01.07.2006.
4. The relevant clauses under the PPA dealing with Date of Commercial Operation are as under: -
(a) The Project shall be deemed to have achieved Entry into Commercial Operation on the date of issue by the Company to the Board of the Certificate of Project Completion, provided that the Company shall not be entitled to issue such a certificate unless during the Capacity Test to establish Entry into Commercial Operation conducted pursuant to the provisions of Section 4.1, the Project achieves a Tested Capacity of at least 47.52 MW.
(b) If the Tested Capacity at the time of Entry into Commercial Operation is more than 55.44 MW then any revision in the Contracted Capacity, and the adjustment in the Fixed Charges shall be mutually decided between the Parties.”
Attention is also drawn to the definition of “infirm power” under the PPA which reads as follows: -
FINDINGS OF THE TNERC:-
5. The TNERC recorded the following findings: -
a) Any PPA executed after the enactment of the ELECTRICITY ACT , 2003, (for short ‘2003 Act’) should have been placed before the TNERC for approval under Section 86(1)(b) of the 2003 Act, but both the parties in this case have failed to do so.
b) That the original PPA dated 29.04.1998 and the amended PPA dated 25.08.2004 which incorporated the requirements of combined cycle power project were not placed before the TNERC especially when the amended PPA was executed after the enactment of the 2003 Act.
c) Though the original PPA was dated 29.04.1998 and was based on
State of Himachal Pradesh vs. JSW Hydro Energy Ltd.
Tata Power Company Limited vs. Reliance Energy Limited and Others
KKK Hydro Power Limited vs. Himachal Pradesh State Electricity Board Limited and Others
PTC India Limited vs. Central Electricity Regulatory Commission, through Secretary
Power purchase agreements must be aligned with regulatory frameworks and cannot be enforced if unapproved, particularly regarding classifications impacting fixed charges.
Tariff determination for hydro projects with enhanced capacity, binding nature of prior PPAs on successors, and writ jurisdiction limited; exclusive domain of regulatory commission, not courts, to fi....
Tariff modifications in power purchase agreements must comply with regulatory approvals as per Section 86(1)(b) of the Act, ensuring valid determination of electricity purchase prices.
Claim relating to unpaid fixed charges and underpaid variable charges – If there is any risk in supply, same has to be shared between generator and fuel supplier.
The main legal point established in the judgment is that the capacity declaration based on RLNG could be done unilaterally, unencumbered by the requirement of the appellant’s consent in the latter ha....
Point of law: since Merit Order Despatch does not apply to renewable energy, which runs on Must Run Basis, the learned single Judge has not committed any illegality in directing that the respondents ....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.