SUPREME COURT OF INDIA
ABHAY S. OKA, PANKAJ MITHAL, JJ.
National Highways Authority of India – Appellant
Versus
M/s Hindustan Construction Company Ltd. – Respondent
Civil Appeal No. 4702 of 2023 with Civil Appeal No. 4703 of 2023, Civil Appeal No. 4704 of 2023, Civil Appeal No. 4705 of 2023, Civil Appeal No. 4706 of 2023, Civil Appeal No. 4707 of 2023, Civil Appeal No. 4708 of 2023 and Civil Appeal No. 4709 of 2023
Decided On : 07-05-2024
Arbitration and Conciliation Act, 1996 – Sections 34 and 37 – Appeal against arbitral award – Jurisdiction of Court under Section 34 is relatively narrow and jurisdiction of Appellate Court under Section 37 of Arbitration Act is all the more circumscribed – As far as construction of terms of a contract is concerned, it is for Arbitral Tribunal to adjudicate upon – If, after considering material on record, Arbitral Tribunal takes a particular view on interpretation of contract, Court under Section 34 does not sit in appeal over findings of Arbitrator – Single Judge and Division Bench of High Court have examined challenge to award within four corners of limitation imposed by Sections 34 and 37 of Arbitration Act – View taken by Arbitral Tribunal, Single Judge and Division Bench cannot be found fault with – Appeals dismissed. (Paras 9, 13, 14 and 15)
Facts of the case:
Being aggrieved by award, appellant filed a petition under Section 34 of Arbitration and Conciliation Act, 1996. By impugned judgment and order dated 30th November 2011, Single Judge confirmed the award in respect of Claim no.1 and Claim no.3.
Findings of Court:
Division Bench was right in holding that majority opinion of technical persons need not be subjected to a relook, especially when Single Judge had also agreed with view taken by Arbitral Tribunal. We have also perused findings of majority in Award. We find nothing perverse or illegal about it.
Result : Appeals dismissed.
FACTUAL ASPECTS IN CIVIL APPEAL NO. 4702 OF 2023
1. The appellant- National Highways Authority of India Ltd. has been constituted under Section 3 of the National Highways Authority of India Act, 1988. On 2nd June 2004, the appellant awarded a contract to the respondent for the work of the Allahabad Bypass Project, which involved the construction of a road from km 158 to km 198 (except a bridge on the river). The total cost of the project was Rs.4,46,99,12,839/-. A dispute between the parties was referred to the Dispute Resolution Board. The Board gave its recommendations. Ultimately, the dispute was referred to an Arbitral Tribunal of three arbitrators. There were three claims referred to arbitration, which are as follows:
- Claim no.2 - Non-payment for executed work of embankment with soil/pond ash for the initial 150 mm depth stripped in accordance with the requirements of the contract and
- Claim no.3 - Reimbursement of additional costs incurred due to an increase in the forest transit fee rates.
2. The Arbitral Tribunal made an award on 30th March 2010. The summary of the award is as follows:
- Claim no. 2 - Two members of the Arbitral Tribunal consisting of three members held that the respondent was entitled to Rs.3,47,35,522/- towards the formation of the embankment for an initial 150 mm, along with a price adjustment on the said amount in accordance with clause 70.3 of the contract, with interest and future interest at 12% per annum. The third member of the Arbitral Tribunal dissented and held that the respondent was not entitled to any amount under the said claim.
- Claim no.3 - The respondent was granted Rs.3,77,74,427.39/- along with interest and future interest at 12% per annum.
3. Being aggrieved by the award, the appellant filed a petition under section 34 of the Arbitration and Conciliation Act, 1996 (for short ‘the Arbitration Act’). By the impugned judgment and order dated 30th November 2011, the learned Single Judge confirmed the award in respect of Claim no.1 and Claim no.3, relying upon the decision of the High Court in the case of National Highways Authority of India v. M/s. ITD Cementation India Limited, 2008 (100) DRJ 431. Regarding Claim no.2, the learned Single Judge held that the award was a majority decision of the Arbitral Tribunal based on an analysis of the material placed before the Arbitral Tribunal. Therefore, the award for Claim no.2 was upheld. Being aggrieved by the said judgment and order, the appellant preferred an appeal under Section 37 of the Arbitration Act before a Division Bench of the Delhi High Court. By the impugned judgment, the said appeal has been dismissed. From the impugned judgment, it appears that the submissions made before the Division Bench of Delhi High Court were confined to Claim nos. 1 and 2. By the impugned judgment, the appeal preferred by the appellant was dismissed. Being aggrieved by the Arbitral Tribunal’s award and the judgments of the High Court, the appellant has preferred the present appeal. At the outset, we may note here that one of the grounds of challenge in the present appeal was that the decision of the High Court in the case of National Highways Authority of India v. M/s. ITD Cementation India Limited, 2008 (100) DRJ 431 was the subject matter of challenge before this Court. We may state that by judgment and order dated 24th April 20152[(2015) 14 SCC 21], the said appeal has been partly allowed by setting aside t
Parsa Kente Collieries Ltd. v. Rajasthan Rajya Vidyut Utpadan Nigam Ltd.
McDermott International Inc. v. Burn Standard Co. Ltd.
Rashtriya Ispat Nigam Ltd. v. Dewan Chand Ram Saran
NHAI v. ITD Cementation (India) Ltd.
Appeal against arbitral award – It is for Arbitral Tribunal to adjudicate upon terms of a contract.
In international commercial arbitration, challenges to awards are limited to specific legal grounds, and mere dissatisfaction with arbitral decisions does not constitute public policy violations.
Appeal against arbitral award – Scope of jurisdiction under Section 34 and Section 37 of Act is not akin to normal appellate jurisdiction – Mere possibility of an alternative view on facts or interpr....
Under Section 34, courts cannot act as appellate bodies. Judicial interference is restricted to cases of patent illegality or policy violation. If a tribunal adopts a plausible interpretation of cont....
Setting aside arbitral award – Dissenting opinion would not receive level and standard of scrutiny which majority award which is under challenge is subjected to – A dissenting opinion cannot be treat....
The main legal point established in the judgment is the interpretation and application of Section 34 of the arbitration and Conciliation act, 1996 to an international commercial arbitration, and the ....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.