SANJAY KAROL, MANMOHAN
Pushpa Jagannath Shetty – Appellant
Versus
Sahaj Ankur Realtors – Respondent
Question 1? Question 2? Question 3?
Key Points: - Limitation is not to defeat a substantive right; earnest efforts to secure possession of flats are relevant to limitation computation. (!) - The NCDRC erred by holding the complaint time-barred; the case involves a continuing cause of action due to ongoing efforts and escrow arrangements. (!) (!) - The Court held that the complaint was within time and restored it to its status, directing expeditious adjudication by NCDRC. (!)
ORDER :
1. This appeal is under Section 67 of the Consumer Protection Act, 2019 and is directed against the judgment dated 14th March 2023 passed in Consumer Case No.238 of 2019 by the National Consumer Disputes Redressal Commission, New Delhi1[hereinafter NCDRC].
2. The short facts giving rise to the present appeal are that the respondents are a partnership firm that owned the building named "Madhav Baug" in the village of Andheri, Mumbai. The complainants were tenants in two flats on the ground floor in Building-A. The former decided to demolish this building and construct a new one and, in furtherance thereof, executed, a Permanent Alternate Accommodation Agreement dated 20th September 2013, allotting Flat No. 801, carpet area 700 sq. ft. on the 8th floor of the B-Wing of the new building. The agreement provided 24 months from the date of the issue of the commencement certificate, along with a grace period of 6 months to complete such construction. The proposed redevelopment however could not be completed in the stipulated time, as such, on 10th January 2015, the respondents executed an “Indemnity- cum-Undertaking” to allot two flats numbered 301 and 302 having carpet area of 650
Limitation, while important as a feature of law, is not meant to defeat a substantive right – Efforts, in earnestness, to secure possession of flats cannot be discounted in order to compute applicabl....
Breach of contractual obligations in housing redevelopment led to consumer compensation under the Consumer Protection Act.
Flat Buyers have right to receive fair delay compensation when developers unduly and unreasonably delayed possession as per Agreement.
(1) Contract - A term of a contract, will not be final and binding if it is shown that the consent to the said term was not really voluntary, if the person giving consent had no other choice. (2) Nom....
(1) Earing profits - The onus of establishing that the Complainant was dealing in real estate i.e. in the purchase and sale of plots/ flats in his normal course of business to earn profits, shifts to....
(1) Negligence on Part of Builder – If the builder, whose services are engaged by a buyer for construction of a residential house for him fails to complete the construction and deliver its possession....
Mandatory Condonation of Delay – Section 24A is a legislative mandate. If a complaint is filed after the expiry of two years, the Complainant must satisfy the Forum that there was “sufficient cause” ....
(1) Apartment Buyer’s Agreement – Possession offered without requisite completion certificate is illegal and purchaser cannot be compelled to take possession in such circumstances.(2) Pecuniary juris....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.