SUPREME COURT OF INDIA
PAMIDIGHANTAM SRI NARASIMHA, MANOJ MISRA, JJ.
BGM And M-RPL-JMCT (JV) – Appellant
Versus
Eastern Coalfields Limited – Respondent
Civil Appeal No. of 2025 (Arising out of SLP (C) Diary No. 21451 of 2024)
Decided on : 18-07-2025
(A) Arbitration and Conciliation Act, 1996 – Sections 11 and 7 – Appointment of Arbitrator – Arbitration agreement is foundation of arbitration – Referral Court before appointing Arbitral Tribunal will have to be prima facie satisfied that arbitration agreement as contemplated in Section 7 of 1996 Act exists – For this limited purpose it can scrutinize documents relied upon by parties in proof of its existence – Though burden of proving existence of arbitration agreement lies on party seeking to rely on such agreement, only prima facie proof of its existence must be adduced before Referral Court because Referral Court is not the appropriate forum to conduct a mini-trial by allowing parties to adduce evidence in regard to its existence – However, where professed arbitration agreement is found in an undisputed document, no trial or inquiry is required as to its existence. (Paras 16, 17 and 20)
(B) Arbitration and Conciliation Act, 1996 – Section 7 – Arbitration agreement – Mere use of word “arbitration” or “arbitrator” in a clause will not make it an arbitration agreement, if it requires or contemplates a further or fresh consent of the parties for reference to arbitration – Any agreement, or clause in an agreement, requiring or contemplating a further consent or consensus before a reference to arbitration, is not an arbitration agreement. (Para 26)
Facts of the case:
This appeal impugns an order of High Court1 dated 19.01.2024 whereby the application of appellant, under Section 11 of Arbitration and Conciliation Act, 19963, was dismissed on the ground that there exists no arbitration agreement between the parties.
Findings of Court:
As it is not the case of appellant that parties at any later stage have agreed to refer disputes to arbitration, High Court was justified in rejecting application seeking appointment of Arbitrator.
Result : Appeal dismissed.
| Table of Content |
|---|
| 1. existence of contract and arbitration agreement interpretation (Para 2 , 3 , 4 , 5 , 6) |
| 2. arguments on interpretation of the arbitration clause (Para 8 , 9 , 10 , 11) |
| 3. judicial review parameters under section 11 (Para 13 , 14 , 15 , 16 , 17 , 18) |
| 4. scope of referral court under section 11 defined. (Para 19) |
| 5. legal principles defining arbitration agreement (Para 20 , 21 , 22 , 24) |
| 6. analysis of clause 13 as an arbitration agreement (Para 27 , 30 , 31) |
| 7. appeal dismissed as no binding arbitration agreement exists. (Para 28) |
| 8. conclusion of the appeal (Para 33 , 34 , 35 , 36) |
JUDGMENT :
MANOJ MISRA, J.
1. Leave granted.
2. This appeal impugns an order of the High Court1[The High Court at Calcutta] dated 19.01.2024 whereby the application2[A.P. No. 745 of 2023] of the appellant, under Section 11 of the Arbitration and Conciliation Act, 19963[1996 Act], was dismissed on the ground that there exists no arbitration agreement between the parties.
FACTS
3. The appellant and the respondent entered into a contract relating to transportation/handling of goods. Disputes arose between the parties during the subsistence of the contract. Clause 13 of the General Terms and Conditions, appended to the e-tender notice, which forms part of the contract and relied upon by the appellant as an arbitration agreement, is the subject matter of interpretation. The same is extracted below:
It is incumbent upon the contractor to avoid litigation and disputes during the course of execution. However, if such disputes take place between the contractor and the department, effort shall be made first to settle the disputes at the company level.
The contractor should make request in writing to the Engineer-in-charge for settlement of such disputes/claims within 30 (thirty) days of arising of the cause of dispute/claim failing which no disputes/claims of the contractor shall be entertained by the company.
Effort shall be made to resolve the dispute in two stages.
In first stage dispute shall be referred to Area CGM, GM. If difference still persist the dispute shall be referred to a committee constituted by the owner. The Committee shall have one member of the rank of Director of the company who shall be chairman of the company.
If differences still persist, the settlement of the dispute shall be resolved in the following manner:
In the event of any dispute or difference relating to the interpretation and application of the provisions of commercial contract(s) between Central Public Sector Enterprises (CPSEs)/Port Trusts inter se and also between CPSEs and Government Departments/Organizations (excluding disputes concerning railways, Income Tax, Customs & Excise Departments), such dispute or difference shall be taken up by either party for resolution through AMRCD as mentioned in DPE OM No. 4(1)/2013-DPE (GM)/FTS-1835 dated 22-05-2018.
In case of parties other than Govt. Agencies, the redressal of the dispute may be sought through ARBITRATION AND CONCILIATION ACT , 1996 as amended by AMENDMENT ACT OF 2015” (Emphasis supplied)
4. Treating the underscored portion of clause 13 as an arbitration agreement, the appellant filed an application under Section 11 (6) of the 1996 Act for appointment of an Arbitrator for settlement of the disputes inter se the parties.
5. The respondent objected to the prayer for appointment of an Arbitrator, inter-alia, on the ground that clause 13 is bereft of the essential ingredients to constitute an arbitration agreement and therefore the application seeking appointment of an Arbitrator deserves rejection.
6. The High Court accepted the objection and dismissed the application. While rejecting the prayer, the High Court laid emphasis on use of the word “may” before “be sought” in the underscored portion of clause 13 and, inter alia, relied on two decisions of this Court, namely, Jagdish Chander vs. Ramesh Chander and Others , (2007) 5 SCC 719 and Mahanadi Coalfields Ltd. vs. IVRCL AMR Joint Venture , (
Jagdish Chander vs. Ramesh Chander and Others
Mahanadi Coalfields Ltd. vs. IVRCL AMR Joint Venture
Interplay Between Arbitration Agreements under Arbitration, 1996 & Stamp Act, 1899, In re
Bihar State Mineral Development Corporation vs. Encon Builders
Cox and Kings Limited vs. SAP India Private Limited and another
Appointment of Arbitrator – Arbitration agreement is foundation of arbitration – Referral Court before appointing Arbitral Tribunal will have to be prima facie satisfied that arbitration agreement as....
Arbitration agreement – Mere mentioning of terms ‘arbitration’ or ‘arbitrator’ in heading or existence of these terms in scattered manner in clauses of agreements between parties do not aggregate to ....
(1) Invocation of arbitration – Execution of discharge voucher – There is no rule of absolute kind which precludes arbitration in cases where a full and final settlement has been arrived at.(2) Invoc....
The existence of an arbitrable dispute, the validity of the arbitration agreement, and the existence of an arbitrable dispute are to be determined by the arbitral tribunal.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.