SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(SC) 1291

SUPREME COURT OF INDIA
Pamidighantam Sri Narasimha, Manoj Misra, JJ.
Oil And Natural Gas Corporation Ltd. – Appellant
Versus
M/S G & T Beckfield Drilling Services Pvt. Ltd. – Respondent
Civil Appeal No. 11324 of 2025 Arising out SLP (C) No. 18331 of 2019
Decided On : 02-09-2025

Advocates appeared:
For the Petitioner(s): Mr. Tushar Mehta, Solicitor General (NP) Mr. Akshay Amritanshu, AOR Ms. Drishti Saraf, Adv. Ms. Pragya Upadhyay, Adv. Ms. Swati Mishra, Adv.
For the Respondent(s): Ms. Bhargavi Kannan, Adv. Ms. Shivani Karmakar, Adv. Ms. Kavya Sarin, Adv. Ms. S. Ambica, Adv. Mr. Hardeep Singh Anand, AOR

IMPORTANT POINTS
(1) Post-award interest – If agreement stipulates that no interest is payable, Arbitral Tribunal cannot award interest for the period and an award contrary to terms of contract would be vulnerable to a challenge under Section 34 of Arbitration and Conciliation Act, 1996.
(2) Award of interest pendente lite on sum awarded – Sustainability – Arbitral Tribunal can be denuded of its power to award pendente lite interest only if agreement/ contract between parties is so worded that award of pendente lite interest is either explicitly or by necessary implication barred.

Headnote:

(A) Arbitration and Conciliation Act, 1996 – Section 31(7)(b) – Contract Act, 1872 – Section 28 – Post-award interest – Sustainability – If agreement stipulates that no interest is payable, Arbitral Tribunal cannot award interest for the period and an award contrary to terms of contract would be vulnerable to a challenge under Section 34 of 1996 Act – An agreement to waive interest is not ultra vires in terms of Section 28 of Contract Act, 1872 – However, if agreement is silent on award of interest, Arbitral Tribunal can award interest in terms of clause (a) of sub section (7) of Section 31 – Arbitral Tribunal has jurisdiction to award interest for three distinct periods, namely, pre-reference, pendente lite, and future i.e., post-award – Award of pre-reference and pendente-lite interest is subject to agreement between parties whereas post award interest is statutorily governed and is not subject to agreement between parties – In instant case, rate of interest awarded is 12% per annum – This appears reasonable being lower than statutorily prescribed rate then prevalent under clause (b) of sub-section (7) of Section 31. (Paras 12 and 13)

(B) Arbitration and Conciliation Act, 1996 – Section 31(7)(b) – Award of interest pendente lite on sum awarded – Sustainability – Arbitral Tribunal can be denuded of its power to award pendente lite interest only if agreement/ contract between parties is so worded that award of pendente lite interest is either explicitly or by necessary implication barred – A clause merely barring award of interest on delayed payment by itself will not be readily inferred as a bar to award pendente-lite interest by Arbitral Tribunal – No such error in award of pendente lite interest as may warrant interference with award. (Paras 25 and 26)

Facts of the case:

Present appeal arises from a judgment and order of Gauhati High Court1 dated 08.03.2019, whereby the appeal of the respondent, under Section 37 of the Arbitration and Conciliation Act, 1996, was allowed, judgment and order of the District Judge, Sivasagar, dated 15.11.2007, in Misc. Arb Case No.26 of 2005, under Section 34 of 1996 Act, was set aside and arbitral award dated 21.11.2004 was affirmed.

Findings of Court:

Since post-award interest is in line with statutory provision of clause (b) of sub section (7) of Section 31 as was in vogue then, we find merit in appeal, and same is, accordingly, dismissed.

Result : Appeal dismissed.

JUDGMENT :

MANOJ MISRA, J.

1. Leave granted. This appeal arises from a judgment and order of the Gauhati High Court1[The High Court] dated 08.03.2019, whereby the appeal (i.e., Arb. A 3/2007) of the respondent, under Section 37 of the Arbitration and Conciliation Act, 19962[1996 Act], was allowed, the judgment and order of the District Judge, Sivasagar, dated 15.11.2007, in Misc. Arb Case No.26 of 2005, under Section 34 of 1996 Act, was set aside and the arbitral award dated 21.11.2004 was affirmed.

FACTS

2. Facts relevant for deciding this appeal are that the appellant suffered an arbitral award, dated 21.11.2004, passed by a three member arbitral tribunal, which directed as follows:

    “1. Preliminary objection as to maintainability of the present arbitration proceeding raised on behalf of the respondent ONGC, is rejected.

    2(i) Claim No.2 relating to the 2nd invoice for dollar 20,729.17 being the outstanding balance is allowed rejecting the claim for interest thereon.

    2(ii) Claim No.3 in respect of invoice No.3 for dollar 1,26,536.44 being unpaid balance is allowed without interest.

    2(iii) Claim No.4 in respect of invoice No.4 for dollar 30,1401.05 being outstanding balance is allowed. Claim for interest is, however, rejected.

    2(iv) Claim No.5 in respect of invoice No.5 for dollar 14,321.68 being the outstanding balance is allowed without interest.

    2(v) Claim No.6 in respect of invoice No.6 of dollar 1,67,960.43 being outstanding balance is allowed but no interest is allowed.

    2(vi) Claim No.7 in relation to invoice No.7 for dollar 87,523.37 being the unpaid balance is allowed and the claim for interest on the said amount is disallowed.

    2(vii) Claim No.8 refers to invoice No.8 for dollar 60,000 is allowed without interest.

    2(viii) Claim No.9 in respect of invoice No.9 for dollar 78,750 being 75% of the tools lost in hole is allowed without any interest.

    2(ix) Claim No.10 vide invoice No.10 for dollar 15,000 in respect of charges for demobilization is allowed without any interest.

    2(x) Claim for performance-bond amount of dollar 55,050 is allowed as the said sum was deducted improperly without any justification.

    3. Accordingly, an award for the total amount of dollar 6,56,272.34 is passed in favour of the Claimant G & T BecField Drilling Services (P) Ltd against the Respondent, Oil & Natural Gas Corporation Ltd..

    4. The said sum will carry interest at the rate of 12% per annum on and from 12/12/1998, the date when the statement of claim was affirmed, till recovery of the said amount and an Award for interest on the said amount is made accordingly.

    5. The claimant will be entitled to Costs of the Proceeding assessed at Rs.5 (five) lakhs only from the Respondent, ONGC, and an Award for Rs.5 (five) lakhs for Costs is accordingly passed. Counter-Claims are dismissed.

    Sd/- 1. …. ; 2. ….; 3. …. Dt/- 21.11.2004”

3. Aggrieved by the award, the appellant filed an application (i.e., Misc. (Arbitration) Case no.26 of 2005), under Section 34 of 1996 Act, for setting aside the award by taking various pleas including the one that clause 18.1 of the agreement does not allow payment of interest on the claim.

4. The District Judge allowed the application and set aside the award, vide order dated 15.11.2007, inter alia, on two grounds: (a) the award is non-reasoned, therefore, violates the mandate of Section 31(3) of 1996 Act; and (b) objection under Section 16(2) was neither rejected prior to proceeding further, nor considered by the arbitral tribunal at the time of making final award.

5. Aggrieved therewith, respondent filed an appeal before the High Court under Section 37(1)(c) of 1996 Act, which was allowed by the impugned judgment and order thereby affirming the arbitral award in toto.

6. When notices were issued on the Special Leave Petition, seeking leave to appeal against the impugned order, it was limited to the extent as to whether interest on the total amount at the rate of 12 per cent could be awarded or not. The order dated 25.11.2019, issuing notice, is r

      Click Here to Read the rest of this document
      1
      2
      3
      4
      5
      6
      7
      8
      9
      10
      11
      SupremeToday Portrait Ad
      supreme today icon
      logo-black

      An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

      Please visit our Training & Support
      Center or Contact Us for assistance

      qr

      Scan Me!

      India’s Legal research and Law Firm App, Download now!

      For Daily Legal Updates, Join us on :

      whatsapp-icon telegram-icon
      whatsapp-icon Back to top