SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(SC) 218

SUPREME COURT OF INDIA
SANJAY KAROL, VIPUL M. PANCHOLI, JJ.
Union of India & Ors. – Appellants
Versus
Larsen & Tubro Limited (L&T) – Respondent
Civil Appeal No. of 2026 (@ Special Leave Petition (Civil) No. 14989 of 2023)
Decided On : 27-02-2026

Advocates appeared:
For the Petitioner(s): Mrs. Aishwarya Bhati, A.S.G. Mr. Annirudh Sharma Ii, Adv. Mr. Digvijay Dam, Adv. Mrs. Ruchi Kohli, Adv. Mr. Raman Yadav, Adv. Mr. Sachin Sharma, Adv. Mr. Amrish Kumar, AOR
For the Respondent(s): M/S. Acm Legal, AOR

IMPORTANT POINTS
(1) Appeal against Arbitral Award – Grant of post-award interest is conditional in nature and operates as a deterrent against delayed payment, rather than as an automatic or punitive imposition of post-award interest.
(2) Interpretation of Statute – Rule of ejusdem generis is a tool of interpretation and is applicable only where general words follow a specific class forming a genus.

Headnote:

(A) Arbitration and Conciliation Act, 1996 – Sections 28(3) and 31(7)(a) – Appeal against Arbitral Award – In present case, a distinct legal regime governs post-award interest, which operates independent of principles applicable to pre-award or pendente lite interest – Grant of post-award interest is conditional in nature and operates as a deterrent against delayed payment, rather than as an automatic or punitive imposition of post-award interest – Arbitral Tribunal is not justified in awarding pre-award/pendente lite interest, by way of compensation, while passing award in favour of respondent-claimant – Conditional grant of post-award interest in present case is consistent with statutory framework and serves purpose of ensuring timely satisfaction of award – However, rate of post- award interest at 12% per annum, as awarded by Arbitral Tribunal, is on higher side – Rate of post-award interest modified from 12% per annum to 8% per annum from date of award till realization. (Paras 45, 50, 54, 58, 60, 61 and 62)

(B) Interpretation of Statute – Rule of ejusdem generis is a tool of interpretation and is applicable only where general words follow a specific class forming a genus. (Para 39)

Facts of the case:

This is an appeal challenging the final judgment and order dated 25.05.2023 passed by High Court of Judicature at Allahabad in Appeal No. 433 of 2023 under Section 37 of Arbitration and Conciliation Act, 1996. Vide impugned judgment, High Court dismissed appeal filed by appellants herein and upheld Order dated 15.09.2022 passed by Commercial Court, Jhansi, and thereby upheld Arbitral Award dated 25.12.2018 passed by Arbitral Tribunal.

Findings of Court:

Impugned judgment dated 25.05.2023 passed by High Court of Judicature at Allahabad, order dated 15.09.2022 passed by Commercial Court, Jhansi, and Arbitral Award dated 25.12.2018, are set aside, to the extent of grant of pre-award/pendente lite interest or amounts in nature of interest, qua Claim No. 1, 3 and 6. Arbitral Award dated 25.12.2018 is further modified to the extent of rate of post-award interest from 12% per annum to 8% per annum from date of award till realization.

Result : Appeal partly allowed.

Judgement Key Points

Key Points: - An appeal against an arbitral award regarding post-award interest is conditional and acts as a deterrent for delayed payment rather than an automatic punitive measure (!) . - The grant of post-award interest is a distinct legal regime operating independently from pre-award or pendente lite interest (!) . - Arbitral Tribunals are not justified in awarding pre-award or pendente lite interest by way of compensation if the contract explicitly prohibits it (!) . - The Supreme Court modified the post-award interest rate from 12% per annum to 8% per annum from the date of the award till realization (!) . - The rule of ejusdem generis is a tool of interpretation applicable only when general words follow a specific class forming a genus (!) . - Clause 16(3) of the General Conditions of Contract (GCC) was interpreted to bar interest on all amounts payable to the contractor, not just deposits (!) . - Section 31(7)(a) of the Act mandates that pre-award interest awards must respect the terms agreed upon in the contract (!) . - Section 31(7)(b) of the Act allows for post-award interest unless the award specifically directs otherwise, and this provision is not subject to the contract's bar on pre-award interest (!) . - Courts retain the power to modify the rate of post-award interest under Section 31(7)(b) where facts justify such modification to ensure just compensation (!) . - The impugned judgment and Arbitral Award were set aside to the extent of the grant of pre-award/pendente lite interest for specific claims (!) .


JUDGMENT :

VIPUL M. PANCHOLI, J.

1. Leave granted.

2. This is an appeal challenging the final judgment and order dated 25.05.2023 passed by the High Court of Judicature at Allahabad in Appeal No. 433 of 2023 under Section 37 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as “the Act”) titled as “Union of India and 2 others v. Larsen & Tubro Limited (L and T)”.

3. Vide the impugned judgment, the High Court dismissed the appeal filed by the appellants herein and upheld the Order dated 15.09.2022 passed by the Commercial Court, Jhansi, and thereby upheld the Arbitral Award dated 25.12.2018 passed by the learned Arbitral Tribunal.

FACTUAL MATRIX

4. The brief facts of the case are that the underlying dispute originates from the Agreement dated 27.01.2011, bearing No. CME/NCR/JHSW/MOD/2010 (Turnkey), executed between the appellants (Union of India & North Central Railway Administration) and the respondent (Larsen & Tubro Limited [L&T]).

5. The contract stipulated the execution of work related to the modernization of Jhansi Workshop of North Central Railways, valued at a negotiated rate of Rs. 93,08,07,696/-. The original date for the completion of the work was 18.07.2012 (a period of 18 months). However, the same was extended by the appellants 10 times until 30.11.2015. This resulted in a total delay of 40 months beyond the original deadline.

6. During this course, disputes concerning the execution of the work and outstanding payments arose between the parties. The General Conditions of Contract (hereinafter referred to as “the GCC”) provided for the arbitration agreement, being Clause 64. The respondent submitted an application on 04.09.2017 for the appointment of an Arbitral Tribunal. As per Clause 64(3) of the GCC, the three-member Arbitral Tribunal was formally constituted. The learned Arbitral Tribunal (hereinafter referred to as “the AT”) entered into reference on 10.01.2018, with L&T as claimant (respondent herein) and North Central Railway as respondent (appellants herein).

7. L&T submitted a statement of claim, subsequently revised, raising claims, inter alia, for Financing Charges towards Inordinate Delay in release of payments against running account bills (Claim No. 1), Cost incurred due to Variations in Foreign Exchange Currency Component beyond original contract period (Claim No. 2), Non-payment of Price Variation Component (PVC) (Claim No. 3), Indirect Costs incurred during extended stay in the project (Claim No. 4), Refund of the amount recovered as token liquidated damages (Claim No. 5), Payment due against the final bill / variation for the additional works as per the contract (Claim No. 6), Interest on the claim amount (Claim No. 7), and Costs of Arbitration (Claim No. 8). North Central Railway made a counter claim for Losses to Railway due to late commissioning of CNC Portal Wheel Lathe, MOD.

8. After perusing the material available on record, the AT passed the Arbitral Award on 25.12.2018. The operative part of the Arbitral Award is reproduced as under:-

    “5.0 Summary of the Claims / Counter-claim and award declared:

    Claims:

Sr.

Particulars

Claim Amount in Rs.

Award sum in Rs.

Claim No.1

Financing charges towards inordinate delay

2,26,25,891

1,77,78,727/-

Claim No.2

Claim for Variations in Foreign Exchange Currency

2,21,00,586

Nil

Claim No.3

Claim for non payment of PVC & INTEREST

98,44.886/-

1,70,18,577/-

Claim No.4

Claim for indirect costs during extended stay in the project

5,70,04,383

Nil

Claim No.5

Refund of the amount recovered as token liquidated damages

2,00,000

Nil

Claim No.6

Payment due against the final bill & interest

1,67,51,576

2,28,70,261/-

Claim No.7

Interest on the claim amount @ 18%

10,27,41,682

NIL

Claim No.8

Costs of arbitratio

              Click Here to Read the rest of this document
              1
              2
              3
              4
              5
              6
              7
              8
              9
              10
              11
              SupremeToday Portrait Ad
              supreme today icon
              logo-black

              An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

              Please visit our Training & Support
              Center or Contact Us for assistance

              qr

              Scan Me!

              India’s Legal research and Law Firm App, Download now!

              For Daily Legal Updates, Join us on :

              whatsapp-icon Back to top