SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(SC) 249

SUPREME COURT OF INDIA
J.K. MAHESHWARI, ATUL S. CHANDURKAR, JJ.
Municipal Corporation of Greater Mumbai – Appellant
Versus
M/s R.V. Anderson Associates Limited – Respondent
Civil Appeal Nos. 3277-3278 of 2026 [Arising Out of SLP (C) Nos. 23846-23847 of 2025]
Decided On : 11-03-2026

Advocates appeared:
For the Appellant(s) : Ms. Asha Gopalan Nair, AOR
For the Respondent(s): Ms. Riddhi Sancheti, AOR Mr. Mukul Kulhari, Adv. Ms. Tanjul Sharma, Adv.

The court affirmed the validity of the arbitral tribunal's constitution and concluded that the party's failure to act within the stipulated timeframe amounted to a waiver of jurisdictional objections.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 and Section 37 - Jurisdiction challenge to the arbitral tribunal due to improper constitution under Clause 8.3(b) of the arbitration agreement following the expiration of 30 days without further action from either party regarding arbitrator appointment. (Paras 3, 4, 21, 24)

(B) The arbitral tribunal’s decision that the agreement's language permitted continued action past the 30-day period, thus affirming its validity and waiver of jurisdictional challenges by the Municipal Corporation of Greater Mumbai due to inaction. (Paras 21-68)

Facts of the case:
The case involved disputes arising from a consultancy agreement related to sewerage operations, with arbitration invoked after payment disputes. The Respondent triggered the arbitration clause on 09.08.2005.

Findings of Court:
The courts affirmed the tribunal's ruling and found no jurisdictional defects nor grounds for setting aside the arbitral award, emphasizing party conduct and agreement interpretation.

Issues: The main issues included the validity of the arbitral tribunal's constitution and the waiver of jurisdictional objections due to MCGM's conduct.

Ratio Decidendi: The apex court held that the tribunal was validly constituted, and that party conduct showed acquiescence, effectively waiving the right to challenge the tribunal’s composition after engaging in arbitration.

Result: Appeals dismissed.

Table of Content
1. background facts of the arbitration process. (Para 5 , 6 , 7 , 8 , 9 , 10)
2. the jurisdictional challenge's basis explored. (Para 21 , 22 , 23)
3. mcgm's arguments on tribunal constitution. (Para 25 , 26)
4. interpretation of clause 8.3(b) discussed. (Para 27 , 28 , 29 , 30 , 31 , 32)
5. understanding arbitrators’ powers and limits. (Para 33 , 34 , 35 , 36)
6. waiver and acquiescence principles examined. (Para 38 , 39 , 40 , 41)
7. mcgm's actions interpreted in context. (Para 42 , 43 , 44 , 45 , 46)
8. conduct in arbitration affects rights. (Para 54 , 55 , 56 , 57 , 58)
9. legal precedents on waiver in arbitration. (Para 59 , 60 , 61 , 62 , 63)
10. final findings justifying the court's decisions. (Para 64 , 65 , 66 , 67)
11. conclusion of the appeals decisions. (Para 68)

JUDGMENT :

J.K. MAHESHWARI, J.

1. Leave granted.

2. The instant appeals are directed against the judgment dated 04.07.2025 of the High Court of Bombay (hereinafter referred to as “High Court”) in Arbitration Appeal (L) No. 4339 of 2024 with Interim Application (L) No. 7312 of 2024.

3. By the impugned judgment, the High Court dismissed the appeal of the Appellant-Municipal Corporation of Greater Mumbai (hereinafter referred to as “MCGM”) under Section 37 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as “1996 Act”) and confirmed the judgment and order dated 19th and 20th of October, 2022 of the learned Single Judge in Arbitration Petition No. 84 of 2012 dismissing the application filed under Section 34 of the 1996 Act by MCGM for setting aside the award dated 05.06.2010 of a three-member Arbitral Tribunal.

4. The challenge made in the proceedings of Section 34 was threefold - improper constitution of the tribunal, limitation and interest. However, before us, the Appellant has confined their arguments only to the question of lack of jurisdiction due to improper constitution of the tribunal. As such, our examination of the facts of the case is confined to the question of validity of constitution of the tribunal.

FACTS

5. The facts shorn of unnecessary details are that the MCGM had floated a tender and invited proposals for ‘Consultancy Services to Upgrade Sewerage Operations & Maintenance Services’. The scope of work of the contract was for providing consultancy in upgrading the sewage and sewerage handling facilities, operations and routine maintenance protocols. This was a World Bank funded project and the Respondent turned out to be the successful bidder in association with PHE Consultants, Mumbai. Pursuant thereto, an agreement dated 18.09.1995 (hereinafter referred to as the “Agreement”) was entered into between the MCGM and M/s R.V. Anderson Associates Ltd. which is an engineering firm based out of Canada.

6. The stipulated duration for completion of the work under the Agreement was 72 months and the contract was designed to be implemented in stages. The work under the contract was completed on 20.06.2001 and a final report was submitted by the Respondent to the MCGM. At that stage, a dispute arose in respect of payment of outstanding dues. A meeting was held on 24.10.2002 where the Respondent’s claims were discussed and rejected by MCGM except to make partial payments on 17.02.2004.

7. When things stood as thus, on 09.08.2005, the Respondent invoked the arbitration clause as contained in the Agreement. Vide communication dated 09.08.2005, received by the MCGM on 14.09.2005, the Respondent invoked the arbitration clause, particularly clause 8.3(b) of the Agreement and appointed Hon’ble Mr. Justice S.M. Jhunjhunwala (Retd.) as their nominee arbitrator. On 07.10.2005, the MCGM appointed Mr. Sharad Upasani, former IAS officer as their nominee arbitrator.

8. On 04.11.2005, a meeting was held between the Appellant and the Respondent, where the parties discussed about exploring a possibility of conciliation or mediation. In reference to the said meeting, another letter dated 08.11.2005 was sent by the Respondent to MCGM, seeking to ex

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top