Andhra Pradesh High Court
Judges : P.B.MISHRA, R.BAYAPU REDDY
Deepak Galvanising and Engineering Industries Pvt.Ltd. - Appellant
Versus
Government of India and Anr. - Respondent
Decided On : 09-10-97
Arbitration and Conciliation Act, 1996 - Sections 11, 14, 15, 20 and 8 - Bid Documents - Section 3 - Tenders for Manufacture of SS Towers - Separate Contract Works - These two arbitration applications are filed by same petitioner against same respondents seeking appointment of an Arbitrator to adjudicate disputes that have arisen between petitioner and respondents in connection with two separate contract works entered into between them - Petitioner in both applications is Galvanizing and Engineering Industries Private Limited and respondents relate to Department of Telecommunications 1st respondent being Government of India represented by Secretary Department of Telecommunications and 2nd respondent being Director General Department of Telecommunications Government of India - Petitioner company undertook work of fabrication and structuring of Micro Wave Towers as required by Telecommunications Department - Telecommunications Department issued Notification inviting tenders for manufacture of self-supporting towers of height - Tenders submitted by petitioner for both said works were accepted by respondent which issued an advance purchase order and placed provisional order with petitioner Company for supply SS towers – Held, Therefore amounts to forfeiture of their right to appoint an Arbitrator named in arbitration as opined by Apex Court in cited decisions and that Court is therefore competent to appoint an independent Arbitrator of its own choice in view of facts and circumstances of present case - Learned Counsel for respondents has tried to rely upon Full Bench decision of this Court reported and decision of Supreme Court referred which is also referred in support of his contention that Court has to appoint only named Arbitrator in arbitration inspite of fact that respondent-Department had not chosen to respond to request of petitioner for appointment of an Arbitrator before present applications are filed in this Court - In view of facts and circumstances of that particular case concerned in decision of this particular case concerned in decision of this Court referred to it was observed by their Lordships that while effecting appointment of an Arbitrator Court will have to see whether it is desirable or feasible to appoint an Arbitrator in accordance with or as nearly as possible to intention of parties - If it is not possible it is open to Court to appoint an Arbitrator of its own choice - Applications are allowed.
( 2 ) THE petitioner in both the applications is M/s. Deepak Galvanising and Engineering Industries Private Limited, Secunderabad and the respondents relate to the Department of Telecommunications, the 1st respondent being the Government of India, represented by Secretary, Department of Telecommunications, New Delhi and the 2nd respondent being the Director General, Department of Telecommunications, Government of India, New Delhi. The petitioner company undertook the work of fabrication and structuring of Micro Wave Towers as required by the Telecommunications Department. The Telecommunications Department issued Notification dated 27-7-1992 inviting tenders for the manufacture of self supporting towers of the height of 60 mts. and 80 mts. The tenders submitted by the petitioner for both the said works were accepted by the respondent, which issued an advance purchase order dated 24-3-1993 and placed provisional order with the petitioner Company for the supply of 26 Nos. of 60 mts. SS towers and 22 Nos. of 80 mts. SS towers. As per the advance purchase order, the petitioner Company had to furnish a performance security bond in the form of bank guarantee for Rs. 17,00,000. 00 for both the works. The petitioner accordingly furnished the bank guarantee for Rs. 17,00,000. 00 on 18-8-1993, which was valid upto 18-8-1996 and it was extended till 18-2-1997. The respondents thereupon placed a firm order on 27-8-1993 with the petitioner-Company for the supply of 26 Nos. of 60 mts. SS towers for a value of Rs. 1,38,84,000. 00 and the said work had to be completed within six months from the date of purchase order. But on account of the delay occurred on the part of the respondent-Department at every stage namely, supply of drawings, inspecting the towers, giving consignee details etc. , the petitioner had to seek extension of time for delivering the towers as agreed upon. Having noticed some defects in the structural stability of the towers constructed by the petitioner, the respondent-Department instructed the petitioner to stop production during the contract period. The respondent-Department took considerable time for the petitioner to complete the work undertaken by him. Inspite of several requests by the petitioner, there was delay on the part of the Department in sending the list of consignees by various State Units and in sending the required forms. There was also diversions of the items from one State to another on the last minute. On account of such lapses on the part of the respondent-Department and also on account of the Department in not discharging the bank guarantee in favour of the petitioner, the petitioner was put to heavy loss under various heads. The disputes thus arose between the petitioner and the respondent-Department relating to the contract for supply of 26 Nos. of 60 mts. SS towers, which were in fact supplied, though with some delay, to the respondent.
( 3 ) REGARDING the second contract for the supply of 22 Nos. of 80 mts. SS towers, the respondent-Department issued purchase order on 25-11-1994, thereby placing firm order on the petitioner-Company for the supply of 22 Nos. of 80 mts. SS towers, for a value of Rs. 1,99,76,572. 00 within a period of six months from the date of the purchase order. But on account of the delay, on the part of the respondent-Department involved at every stage, namely, supply of drawings, according approval, inspecting the towers, etc. , the petitioner had to seek extension of time for delivering the towers as agreed upon. Having noticed some defects in the structural stability of the towers the respondent-Department instructed the petitioner-Company to stop production of the towers duri
SupremeToday
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.