IN THE HIGH COURT OF KARNATAKA, AT DHARWAD
S.G.PANDIT, GEETHA K.B., JJ.
The Government Of Karnataka, R/By Its Chief Secretary – Appellant
Versus
M/s. B.V. Reddy & Company, R/By Its Managing Partner, B. Venkata Reddy, S/o. Late Rami Reddy – Respondent
Comap No.100018 Of 2021 C/W, Comap No.100019 Of 2021
Decided On : 19-12-2025
| Table of Content |
|---|
| 1. overview of appeals and procedural context (Para 1 , 2 , 3) |
| 2. claims made by the plaintiff and contract details (Para 4 , 5 , 6 , 8) |
| 3. plaintiff's submission of work execution under supervision (Para 10 , 11 , 12 , 41) |
| 4. defendants’ counter-claims and allegations of negligence (Para 14 , 15 , 17 , 19 , 20) |
| 5. trial court's issues and framing of relevant legal questions (Para 24 , 33 , 43 , 45) |
| 6. court's reasoning on procedural missteps and legal standards (Para 49 , 52 , 56 , 60 , 66) |
| 7. foundation for establishing breach of contract and damages (Para 105 , 110 , 120 , 130) |
| 8. conclusion regarding claims and counterclaims (Para 176 , 178 , 180 , 182) |
JUDGMENT :
GEETHA K. B., J.
1. These appeals are filed by the defendants/appellants challenging the judgment and decree passed in Commercial O.S.No.2/2020 on the file of Principal District Judge, Koppal dated 20.02.2021 and order passed in Civil Review Petition No.1/2021 dated 08.07.2021 and also dismissal of Counter-Claim filed by defendants respectively.
2. As both appeals arise out of the same case, both appeals are clubbed together, arguments heard and common judgment is being delivered.
3. Parties would be referred with their ranks, as they were before the Trial Court for the sake of convenience and clarity.
4. Plaintiff has filed the suit before Trial Court praying for damages on several claims i.e., claim Nos.(A) to (M) totally amounting to Rs.7,00,05,930/- with interest at 18% per annum from the date of suit till date of payment; for Court costs and for such other reliefs.
5. The case of plaintiff in nutshell is that plaintiff is a Partnership Firm registered under the provisions of the Indian Partnership Act, 1932, represented by its Managing Partner, Mr.B.Venkata Reddy. The plaintiff was Class-I Contractor registered with Government of Karnataka. Defendant No.4 has called for tender for construction of Cable Stayed Bridge (balance portion) across the Tungabhadra River from Anegundi Village, Gangavathi taluk to Hampi, vide Tender Notification No.1431 dated 20.08.2007. In pursuance to which, the plaintiff has submitted his tender which was accepted, work order was issued and parties entered into Agreement No.167/12/2008 dated 15.12.2008 for a contract value of Rs.662.4 lakhs with stipulation to complete the work within 6 months from the date of agreement.
6. The nature of work involved is highly technical and requires expertise consultancy and the same is quite different from general engineering skills required for ordinary bridge work. There was no sufficient time for plaintiff to acquire technical expertise and information with regard to the condition and strength of the existing cables prior to submission of bids. Since the plaintiff had only 18 days time to submit the tender documents, plaintiff had no time to get the expert advice to investigate and to know the condition of the existing cables of the existing bridge. It is surprising to note that defendants had no clue and methodology as to how to go with the execution of the work. It was a dis-jointed effort on the part of defendants without any proper planning to execute such a mind boggling work. Defendants did not furnish any methodology along with the bid documents to acquaint with the nature of the work to be done and also to proceed with the work.
7. Defendants have not investigated the condition and strength of the existing cables which were perhaps executed some years back, either prior to calling for bids or during finalisation of bids, though they took more than one year to finalise the bids.
8. However, the time stipulated for work was only six months which is impossible to complete because of the highly skilled and risky nature of work involved in the present case. Plaintiff had his own reservations but he had no other alternatives except to submit to the dictates of the defendants being a weaker party.
9. Plaintiff further contended that, defendant No. 4 directed the plaintiff to get the drawings a
Smt.Nalini Sunder vs. G.V.Sunder
Kaushik Narsinhbhai Patel and Others vs. S.J.R. Prime Corporation Private Limited and Others
Malleeswari vs. K.Suguna and Another
Batliboi Environmental Engineers Limited vs. Hindustan Petroleum Corporation Limited and Another
AI
In a Turn-Key contract, the contractor bears full responsibility for execution; failure to meet contractual obligations excludes claims for damages arising from project failure.
Arbitral awards under Section 34 set aside in part for patent illegality where claims lack evidence of loss; sustained for plausible delay findings, scope changes; severability applies to separable p....
Civil Courts have jurisdiction to hear claims under construction contracts barred from arbitration, provided they arise within the limitation period set by specific contract conditions.
The court emphasized the requirement for the arbitrator to assign reasons in support of the award and the limited scope of interference by the court in arbitration awards.
The court affirmed that judicial review of arbitration awards is limited, allowing intervention only for evident legal errors, not for reevaluation of evidence or correctness.
An arbitrator's award can be set aside if it is based on a fundamental breach of contract that ignores material clauses of the agreement, leading to a finding that is perverse and constitutes a paten....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.