IN THE HIGH COURT OF KARNATAKA AT DHARWAD
S.G.PANDIT, GEETHA K.B., JJ.
The National Highways Authority of India, through its Project Director, M. Shivakumar S/o B. Madaiah – Appellant
Versus
Chandrashekharappa Basappa Mattur – Respondent
MFA Nos. 104750, 104751, 104752 of 2024
Decided On : 19-11-2025
JUDGMENT :
S.G. PANDIT, J.
1. The above batch of appeals are filed under Section 37 (1) of the Arbitration and Conciliation Act, 1996, For short ‘Act, 1996’ by the National Highway Authority of India, For short ‘NHAI’, questioning the common judgment dated 2.3.2023 passed in Arbitration Petition Nos.72, 73 & 74 of 2022, on the file of learned Prl. District and Sessions Judge, Haveri, whereunder the appellants’ challenge to the awards dated 12.01.2022 passed by the learned Arbitrator/Deputy Commissioner, Haveri in LAQ/ARBT/NH/CR/No.185/2004-05, LAQ/ARBT/NH/CR/No.77/2004-05, LAQ/ARBT/NH/CR/No.79/2004-05 and LAQ/ARBT/NH/CR/No.186/2004-05, is rejected by confirming the said awards.
2. Along with the above appeals, IA No.1/2025 is filed under Section 5 of the Limitation Act, 1963 praying to condone the delay of 441 days in preferring the appeals.
3. Heard the learned counsel Sri. Sagar Ladda for the appellants in all the above appeals, learned counsel Sri. S.N. Banakar for respondent No.1 as well as Smt. Kirti Lata Patil, learned HCGP for respondent No.2/State on IA No.1/2025.
4. Learned counsel Sri. Sagar Ladda for the appellants/NHAI would submit that impugned common judgment was passed on 2.3.2023 and the present appeals were filed before this Court on 14.08.2024. He submits that there is delay of 441 days, which is not deliberate and as the delay is bonafide, he prays for condoning the delay in preferring the appeals. Learned counsel would submit that there are number of connected/identical matters, which made it difficult for the appellants to keep a track at all times. Further, learned counsel would submit that the appellants are the government public exchequer authorities, who are dealing with hundreds of such matters on a daily basis. As such, he submits that the delay in approaching this Court is the result of handling such excessive matters among other reasons. However, he submits that mere reason of delay cannot be a ground to reject the appeals, since the impugned judgments would have far reaching implications on the public exchequer.
5. Per contra, learned counsel Sri. S.N. Banakar for respondent No.1 would submit that there is inordinate delay of 441 days in approaching this Court by NHAI and in the affidavit accompanying the application for condonation of delay, no acceptable reasons are forthcoming to condone the delay. He submits that there is no bonafide and as there is no acceptable cause is shown, IA No.1/2025 requires to be rejected, consequently appeals also.
6. Learned counsel Sri. S.N. Banakar would further submit that the acquisition proceedings under NHAI were commenced by issuing preliminary notification dated 19.3.2001 and final notification dated 3.1.2002, until this date, the claimant has not received entire compensation. Learned counsel referring to the objections filed to IA No.1/2025, prays for dismissal of IA No.1/2025 for condonation of delay.
7. Having heard the learned counsel for the parties and on perusal of the affidavit accompanying the application (IA No.1/2025) for condonation of delay as well as objections filed opposing the said IA, the only question, which falls for consideration is, whether the appellants have shown sufficient cause for condoning the inordinate delay of 441 days in preferring the appeals filed under Section 37 (1) of the Act, 1996.
8. Answer to the above point would be in the “negative” for the following reasons:
9. The first respondent’s lands were acquired for formation of national highway by issuing preliminary notification under Section 3 (A) of the National Highways Act, 1956, For short, ‘NH Act’, dated 19.3.2001 and final notification under (D) of the NH Act, dated 3.1.2002. The award determining the compensation in respect of acquired lands was passed on 28.8.2004, fixing the market value for non-agricultural land at Rs.47.33/- per sq.mtr. Not being satisfied with the market value determined in the award, the 1st respondent-land loser preferred reference before the
State of Maharashtra Vs. Borse Bros. Engineers & Contractors (P) Ltd.
A party seeking to condone delay in appeals must demonstrate sufficient cause, which cannot rely on bureaucratic inefficiency or negligence.
The court held that bureaucratic inefficiencies do not constitute sufficient cause for condoning delays in appeals, emphasizing accountability in litigation processes.
Appeal – Statutory time limit to file Appeal – Claim on account of impersonal machinery and inherited bureaucratic methodology of making several notes cannot be accepted in view of the modern technol....
Condonation of delay under the Limitation Act requires substantial justification, and the State is treated no differently than private litigants in these matters.
The Court must balance the need for substantial justice against the necessity of adhering to procedural timelines, requiring satisfactory explanations for delays.
The court adopted a liberal and justice-oriented approach in the matter of condonation of delay, allowing the delay of 23 days to be condoned as sufficient cause was explained by the DDA.
The court reinforced that strict compliance with limitation periods under the Arbitration and Conciliation Act is mandatory, and delays beyond the prescribed time cannot be condoned without adequate ....
Delay beyond 120 days (90+30) in Section 34 petitions or corresponding appeals under Section 37 of Arbitration Act not condonable via Limitation Act Section 5; negligence, inaction, lack of bonafides....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.