SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(All) 200

HIGH COURT OF JUDICATURE AT ALLAHABAD LUCKNOW
Prashant Kumar, J.
Lko. Development Authority Thru. Secy. - Appellant
Versus
Shakuntala Devi (Dead) Thru. Sudhir Kumar Rastogi And Others - Respondents
First Appeal Defective No. - 129 of 2025, First Appeal Defective No. 130 of 2025
Decided On : 07-01-2026

Advocates Appeared:
For the Appellant : Mukund Tewari, Dhawal Bir Prasad

The court held that bureaucratic inefficiencies do not constitute sufficient cause for condoning delays in appeals, emphasizing accountability in litigation processes.

Headnote:(A) Land Acquisition Act, 1894 - Section 18 - Delays in filing appeals - Applications for condonation of delay in filing appeals were rejected by the court due to inability of the appellant to provide sufficient reasons explaining the delays of 173 and 182 days respectively, and reliance was placed upon the Supreme Court's holding that sufficient cause must evidence diligence. (Paras 4, 30)

(B) Limitation Act, 1963 - Section 5 - The court emphasized that liberality in condoning delay for state entities has evolved to require accountability and responsibility, and delays should not be condoned as a matter of course but must be justified with genuine explanations. (Paras 20, 26, 30)

(C) Judicial efficiency - The judgment stresses the importance of adhering to statutory timeframes to uphold the rule of law and prevent unnecessary litigations. (Paras 240, 262)

Facts of the case:
The appellant, Lko. Development Authority, sought to condone delays in filing two appeals against judgments dated 09.08.2024 from the Land Acquisition Tribunal, but provided insufficient justification for the delays.

Findings of Court:
The court found no satisfactory reasons for the delays and criticized the procedural inefficiency often attributed to state departments.

Issues: Whether the delay of 173 and 182 days was justified, and if the explanations provided constituted sufficient cause as per relevant legislation.

Ratio Decidendi: The court ruled that a genuine and sufficient cause should be shown to condone any delay, emphasizing that mere bureaucratic inefficiencies do not qualify as valid excuses, thereby aligning with recent jurisprudence on limitations regarding state appeals.

Result: Delay condonation applications rejected; appeals dismissed.

Table of Content
1. delay and its implications on appeals. (Para 3 , 4 , 5)
2. arguments for condoning delay based on procedural inefficiencies. (Para 6 , 7 , 12)
3. court’s reasoning on the necessity of sufficient cause for delay. (Para 8 , 9 , 10 , 14)
4. supreme court's stance on bureaucratic inefficiencies. (Para 11 , 18 , 21 , 24)
5. guidelines on interpreting 'sufficient cause' in delay petitions. (Para 15 , 16 , 17)
6. evolving jurisprudence of condonation of delay in government matters. (Para 22 , 23 , 25 , 26 , 27)
7. rejection of plea for condonation based on lack of due diligence. (Para 28 , 29)
8. final decision on delay applications and merits. (Para 30)

JUDGMENT :

PRASHANT KUMAR, J.

Order on Applications for Condonation of Delay

1. Vakalatnama filed by Shri Paavan Awasthi on behalf of respondent No.1/2/1 in First Appeal Defective No.129/2025 is taken on record.

2. Heard Shri Mukund Tewari, learned Senior Advocate assisted by Shri Bhanu Bajpai, learned counsel for the appellant, Shri Paaavan Awasthi, learned counsel for respondents and perused the record.

3. As per office report, First Appeal Defective No.129 of 2025 has been filed with delay of 173 days and First Appeal Defective No.130 of 2025 has been filed with delay of 182 days.

4. These first appeals have been filed by the appellant-Lko. Development Authority against the judgment and order dated 09.08.2024 passed by Presiding Officer, Land Acquisition, Rehabilitation and Resettlement Tribunal, Kapoorthala, Lucknow Division, Lucknow in Misc. Case No.16/1990 (Smt. Shakuntala Devi (dead) and others vs. U.P. State through Collector, Lucknow and others) and Misc. Case No.14/1990, Chandra Kishore Rastogi (dead) and another vs. U.P. State through Collector, Lucknow and others under Section 18 of the Land Acquisition Act, 1894 respectively.

5. The reasons stated in the delay condonation applications are that the impugned orders were passed on 09.08.2024 and the counsel appearing on behalf of the appellant before the Tribunal only came to know about the judgment on 08.09.2024 however, no reasons had been given as to who informed him and what was the reason for not knowing. Even after knowing about the judgment on 08.09.2024, the certified copies were applied on 25.09.2024 which were made available on 03.10.2024. The reasons stated in the application filed along with delay condonation applications are nothing but an excuse and an effort has been made to explain the delay.

6. Learned Senior Advocate appearing on behalf of appellant submits that in these cases the delay is not an inordinate delay as the delay is only 173 & 182 days respectively.

7. It is further submitted that the certified copies were misplaced and later on recovered and it is only after getting certified copies, an opinion was given by him to contest the matter on 21.12.2024. Thereafter, the matter was put up before the Department who examined the matter on 08.01.2025 and 21.01.2025 and thereafter, the matter was referred to the lawyer and the appeal was filed on 08.05.2025.

8. To buttress his argument he has placed reliance on the judgment passed by the Hon'ble Supreme Court in the matter of Inder Singh vs. State of Madhya Pradesh reported in [2025 SCC OnLine SC 600]. He submits that this judgment considers the previous judgments and held as under:-

"13. In the present case, the contentions of the appellant, on first blush appears to be attractive, inasmuch as the State cannot be given any undue indulgence as compared to an ordinary litigant, especially in matters of limitation. There is no doubt that all parties, whether or not State under Article 123 of the Constitution, are required to act with due diligence and promptitude.

14. There can be no quarrel on the settled principle of law that delay cannot be condoned without sufficient cause, but a major aspect which has to be kept in mind is that, if in a particular case, the merits have to be examined, it should not be scuttled merely on the basis of limitation.

15. In

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top