HIGH COURT OF JUDICATURE AT ALLAHABAD LUCKNOW
Prashant Kumar, J.
Lko. Development Authority Thru. Secy. - Appellant
Versus
Shakuntala Devi (Dead) Thru. Sudhir Kumar Rastogi And Others - Respondents
First Appeal Defective No. - 129 of 2025, First Appeal Defective No. 130 of 2025
Decided On : 07-01-2026
| Table of Content |
|---|
| 1. delay and its implications on appeals. (Para 3 , 4 , 5) |
| 2. arguments for condoning delay based on procedural inefficiencies. (Para 6 , 7 , 12) |
| 3. court’s reasoning on the necessity of sufficient cause for delay. (Para 8 , 9 , 10 , 14) |
| 4. supreme court's stance on bureaucratic inefficiencies. (Para 11 , 18 , 21 , 24) |
| 5. guidelines on interpreting 'sufficient cause' in delay petitions. (Para 15 , 16 , 17) |
| 6. evolving jurisprudence of condonation of delay in government matters. (Para 22 , 23 , 25 , 26 , 27) |
| 7. rejection of plea for condonation based on lack of due diligence. (Para 28 , 29) |
| 8. final decision on delay applications and merits. (Para 30) |
JUDGMENT :
PRASHANT KUMAR, J.
Order on Applications for Condonation of Delay
1. Vakalatnama filed by Shri Paavan Awasthi on behalf of respondent No.1/2/1 in First Appeal Defective No.129/2025 is taken on record.
2. Heard Shri Mukund Tewari, learned Senior Advocate assisted by Shri Bhanu Bajpai, learned counsel for the appellant, Shri Paaavan Awasthi, learned counsel for respondents and perused the record.
3. As per office report, First Appeal Defective No.129 of 2025 has been filed with delay of 173 days and First Appeal Defective No.130 of 2025 has been filed with delay of 182 days.
4. These first appeals have been filed by the appellant-Lko. Development Authority against the judgment and order dated 09.08.2024 passed by Presiding Officer, Land Acquisition, Rehabilitation and Resettlement Tribunal, Kapoorthala, Lucknow Division, Lucknow in Misc. Case No.16/1990 (Smt. Shakuntala Devi (dead) and others vs. U.P. State through Collector, Lucknow and others) and Misc. Case No.14/1990, Chandra Kishore Rastogi (dead) and another vs. U.P. State through Collector, Lucknow and others under Section 18 of the Land Acquisition Act, 1894 respectively.
5. The reasons stated in the delay condonation applications are that the impugned orders were passed on 09.08.2024 and the counsel appearing on behalf of the appellant before the Tribunal only came to know about the judgment on 08.09.2024 however, no reasons had been given as to who informed him and what was the reason for not knowing. Even after knowing about the judgment on 08.09.2024, the certified copies were applied on 25.09.2024 which were made available on 03.10.2024. The reasons stated in the application filed along with delay condonation applications are nothing but an excuse and an effort has been made to explain the delay.
6. Learned Senior Advocate appearing on behalf of appellant submits that in these cases the delay is not an inordinate delay as the delay is only 173 & 182 days respectively.
7. It is further submitted that the certified copies were misplaced and later on recovered and it is only after getting certified copies, an opinion was given by him to contest the matter on 21.12.2024. Thereafter, the matter was put up before the Department who examined the matter on 08.01.2025 and 21.01.2025 and thereafter, the matter was referred to the lawyer and the appeal was filed on 08.05.2025.
8. To buttress his argument he has placed reliance on the judgment passed by the Hon'ble Supreme Court in the matter of Inder Singh vs. State of Madhya Pradesh reported in [2025 SCC OnLine SC 600]. He submits that this judgment considers the previous judgments and held as under:-
"13. In the present case, the contentions of the appellant, on first blush appears to be attractive, inasmuch as the State cannot be given any undue indulgence as compared to an ordinary litigant, especially in matters of limitation. There is no doubt that all parties, whether or not State under Article 123 of the Constitution, are required to act with due diligence and promptitude.
14. There can be no quarrel on the settled principle of law that delay cannot be condoned without sufficient cause, but a major aspect which has to be kept in mind is that, if in a particular case, the merits have to be examined, it should not be scuttled merely on the basis of limitation.
15. In
Ramchandra Shankar Deodhar v State of Maharashtra
Postmaster General and others vs. Living Media India Limited and another
State of Madhya Pradesh and others vs. Bherulal
State of Odisha and ors. vs. Sunanda Mahakuda
The court held that bureaucratic inefficiencies do not constitute sufficient cause for condoning delays in appeals, emphasizing accountability in litigation processes.
The law of limitation applies equally to the State and private parties, with bureaucratic inefficiency not sufficient for condoning delay.
Condonation of delay under the Limitation Act requires substantial justification, and the State is treated no differently than private litigants in these matters.
(1) Limitation – Condonation of delay – Phrase “within such period” signifies that period covered therein extends to not only original period within which, appeal or application, should have been fil....
A liberal approach is essential in condoning delays, particularly for government bodies, ensuring that procedural delays do not hinder substantial justice.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.