SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Kar) 2727

IN THE HIGH COURT OF KARNATAKA AT BENGALURU
K.S. HEMALEKHA, J.
M/s. Hassan Thermal Power Private Limited - Appellant
Vs.
The Power Company Of Karnataka Ltd. (PCKL) - Respondent
Writ Petition No.19513 of 2025 (GM-KEB)
Decided On : 06-11-2025

Advocates:
Advocate Appeared:
For the Appellant :Sri Ramesh Kumar Naroola, Advocate For Smt. Deepa V., Advocate
For the Respondent:Sri Sriranga S., Senior Counsel For Smt. Sumana Naganand, Advocate Sri Raj Kumar M., AGA

EMD is independent of the PPA and must be refunded following governmental withdrawal of approval; its retention constitutes unjust enrichment under Article 300A.

Headnote:(A) Constitution of India - Article 300A - Electricity Act, 2003 - Section 86(1)(f) - Claim for refund of Earnest Money Deposit (EMD) of Rs. 1,00,00,000/- made upon governmental directive, acknowledged by KEB - Petitioner contends that the EMD is independent of the Power Purchase Agreement (PPA) and should be refunded following the withdrawal of the governmental approval. Respondents maintain the retention is lawful due to delay, laches, and because the EMD is a performance security linked to the PPA. (Paras 19, 20, 21)

(B) The court finds that the PPA does not contain terms for forfeiture or adjustment of EMD, and judicial review under Article 226 may occur despite alternative remedies available. The claim is not barred by limitation as the retention constitutes a continuing wrong. (Paras 18, 22)

Facts of the case:
The petitioner deposited Rs. 1,00,00,000/- as EMD on November 28, 1998, for a power project, which was acknowledged by KEB. Following the government withdrawal of approval to the PPA in April 2016, the petitioner sought its refund. The respondents have not presented a lawful basis for retaining the EMD.

Findings of Court:
The petitioner is entitled to a refund of the sum with interest.

Issues: 1) Is the writ petition maintainable given the alternative remedy? 2) Has the petitioner established entitlement to EMD refund? 3) Is the claim barred by delay and laches?

Ratio Decidendi: The absence of terms regarding EMD in the PPA indicates it is independent of that contract. Retaining the EMD after withdrawal of approval infringes the rights of the petitioner under Article 300A.

Result: Writ petition is allowed, directing refund of EMD with interest.

ORDER :

K.S. HEMALEKHA, J.

The petitioner- M/s. Hassan Thermal Power Private Limited has approached this Court seeking a writ of mandamus directing respondent No.1-Power Company of Karnataka Ltd. (PCKL) to refund a sum of Rs. 1,00,00,000/- (Rupees One Crore) deposited by it as Earnest Money Deposit (EMD) on 28.11.1998, together with interest at 12% per annum from 12.04.2016, the date on which the Government of Karnataka withdrew its approval to the proposed Power Purchase Agreement (PPA).

Brief Facts:

2. The petitioner is a company duly incorporated under the provisions of the Companies Act, 1956. It was originally incorporated under the name M/s. Euro India Power Canara Private Ltd. and had its registered office at Bengaluru, with its administrative office situated at New Delhi.

3. The Government of Karnataka, represented by respondent No.2, by its order dated 05.03.1996, acting through the then Karnataka Electricity Board (KEB), the predecessor in contract to the present Karnataka Power Transmission Corporation Ltd., (KPTCL) granted permission to M/S. Euro Kapital A.G. (‘M/s. AG’ for short) to establish a Low Sulphur Heavy Stock (LSHS)-based barge-mounted-power plant of 1x150 MW capacity on the Mulki River near Mangaluru in Udupi District.

4. However, M/s. AG was subsequently declared bankrupt and became subject to legal proceedings, thereby jeopardizing the execution of the project. In the wake of these developments, respondent No.2 noted that two entities M/s. Euro India Power Canara Private Ltd. (the petitioner herein) and M/s. Euro India Energy Ltd. had raised rival claims to succeed to the rights conferred on M/s. A.G. in relation to the said project.

5. To ensure fairness and transparency, the Karnataka Electricity Board (KEB), in consultation with the Government, decided to afford both companies an equal opportunity to establish their respective entitlements. Consequently, by Government letter dated 31.10.1998, both companies were directed to deposit a sum of Rs. 10,00,00,000/- (Rupees Ten Crores) each by way of a demand draft drawn in favour of the Chairman, Karnataka Electricity Board (KEB) within 30 days from the date of said communication. It was categorically stated that the failure to comply with the said condition would render the concerned entity ineligible for further consideration of its claim.

6. In response, M/s. Euro India Energy Ltd., by its letter dated 21.09.1998, expressed its inability to furnish the required deposit within the stipulated period. In contrast, the petitioner-M/s. Euro India Power Canara Pvt. Ltd. by its letter dated 26.09.1998, submitted a bank guarantee for USD 2.38 million (approximately Rs. 10.11 crores), which was duly acknowledged by the Chairman of the Karnataka Electricity Board (KEB).

7. However, since the Government's directive dated 31.10.1998 specially required the deposit to be made by demand draft, the petitioner's compliance by furnishing a bank guarantee was taken up for further consideration. Subsequently, by letter dated 23.10.1998, the petitioner conveyed his willingness to deposit an additional amount of Rs. 1,00,00,000/- in cash, in line with the mode adopted for similarly power projects.

8. Pursuant to the petitioner's communication dated 23.10.1998, the Government of Karnataka, after considering the rival submissions, decided to recognize the petitioner's initiative and financial readiness to undertake the project, the petitioner thereafter deposited Rs. 1,00,00,000/- by demand draft dated 28.11.1998, which was accepted and acknowledged by the Karnataka Electricity Board (KEB).

9. Thereafter, by the Government Order dated 05.03.1999, the petitioner was formally permitted to proceed with the project, and concerned authorities were directed to take further steps to facilitate its implementation. Following the reorganization of the power sector, the Karnataka Power Transmission Corporation Ltd. (KPTCL), and subsequently, the Power Company of Karnataka Ltd. (PCKL), became the s

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top