2016 Supreme(Bom) 31
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
R.D. DHANUKA, J.
M/s. Oil and Natural Gas Corporation Ltd. - Petitioner
Versus
Essar Oil Limited - Respondent
Arbitration Petition No. 267 and 630 of 2011
Decided on : 14.1.2016
Act Referred
ARBITRATION AND CONCILIATION ACT : S.34, S.34(2)(a)(i), S.34(2)(a)(ii), S.34(2)(a)(iii), S.34(2)(a)(iv), S.34(2)(a)(v), S.34(2)(b)
BOMBAY HIGH COURT ORIGINAL SIDE RULES : R.803(c)(a)
CIVIL PROCEDURE CODE : O.7 R.11
Advocate Appeared:
Mr. Pradeep Sancheti, Mr.Rohan Cama, Mr.Virendra Perira, Mr.Aziz Khan, Jahan Chokshi, Ms.Gautami Manjrekar, Mr.Pulkit Sharma, i/b. Divya Shah Associates for the Petitioner in Arbitration Petition No. 267 of 2011 and for the Respondent in Arbitration Petition No. 630 of 2011.
Mr.Rahul Narichania, Mr.Vishal Muglikar, Mr.Gandhar Raikar for the Respondent in Arbitration Petition No. 267 of 2011 and for the Petitioner in Arbitration Petition No. 630 of 2011.
By these two petitions filed under section 34 of the Arbitration and Conciliation Act, 1996, (for short the said Arbitration Act), both the parties have impugned the arbitral award dated 30th September, 2010. M/s.Oil and Natural Gas Corporation Ltd. the petitioner in the Arbitration Petition NO.267 of 2011 was the original respondent in the arbitral proceedings and have impugned the arbitral award dated 30th September, 2010 in toto. M/s.Essar Oil Limited the petitioner in the Arbitration Petition No.630 of 2011 was the original claimant in the arbitral proceedings and have challenged the arbitral award dated 30th September, 2010 to the extent that the claims of the claimant having been rejected viz. Claim nos. 1(a), 2(2), 2(4), 2(5), 2(6), 2(7), 2(9), 2(10), claim no.5 and also thereby allowing part of the counter claims for liquidated damages in favour of M/s. Oil and Natural Gas Corporation Ltd. The parties to the present proceedings are referred in the later part of the judgment as they were referred in the arbitral proceedings as claimant and respondent for the sake of convenience. By consent of parties, both the petitions were heard together and are disposed of by a common judgment. Some of the relevant facts for the purpose of deciding these two petitions are as under :-
2. Sometime in the month of December 1991 the respondent invited tenders for the Bombay High Modification Project. Pursuant to the said invitation of bids, the claimant submitted their bid. The respondent vide Letter of Intent dated 16th November, 1992 considered the bid submitted by the claimant. On 27th November, 1992, the claimant and the respondent entered into a contract.
3. On 15th May, 1994, the claimant completed the work on 14 platforms and 5 pipelines by the scheduled completion date. On 8th February, 1995, the claimant completed 5 platforms and 6 pipelines. According to the respondent, on 9th April, 1996, the warranty period in view of condition 2.2.6 of the General Condition of Contract expired.
4. On 17th December, 1999, the dispute arose between the parties. The claimant invoked the arbitration agreement and nominated a former Chief Justice of India as their nominee arbitrator. The respondent also nominated a former Chief Justice of India as their arbitrator on 11th February, 2000. The arbitrator nominated by the parties thereafter nominated a former judge of this court as a presiding arbitrator.
5. Pursuant to the directions issued by the arbitral tribunal, on 27th October, 2000, the claimant filed their statement of claim containing about five claims and several sub-claims aggregating to approximately Rs.35,00,27,929.76 along with interest and cost. The respondent filed their written statement and statement of counter claims before the arbitral tribunal. The said claim was however subsequently revised to Rs.29,92,64,507.43 along with interest and cost.
6. Claim no.1 was divided in five sub-claims. Claim no.2 was divided in 10 sub-claims. The respondent had filed counter claim inter alia praying for (1) reimbursement of payment in foreign exchange variation and (2) liquidated damages for delayed completion of work in respect of 4 platforms and 6 pipelines in the sum of Rs.24,46,37,396.75 i.e. at the rate of 3% of the contract value. Both the parties had also filed their written submissions before the arbitral tribunal. During the pendency of the arbitral proceedings, two of the arbitrators expired and the parties accordingly nominated two new arbitrators in place of those arbitrators. The claimant had examined a witness who was cross-examined by the learned counsel for the respondent.
7. The arbitral tribunal thereafter rendered an award on 30th September, 2010 allowing claim nos. 1, 2 and 5 partly. The arbitral tribunal rejected claim no.1(a) and allowed claim nos. 3 and 4 as claimed. The arbitral proceedings were concluded in approximately 9 years and 8 months. By the said impugned award, the arbitral tribunal allowed part of the