IN THE HIGH COURT OF JUDICATURE AT BOMBAY AURANGABAD BENCH
RAVINDRA V. GHUGE, S.G. DIGE, JJ.
Shashikant S/o Bhanudas Shelke – Petitioner
Versus
The State of Maharashtra – Respondent
Writ Petition No. 2152 of 2017
Decided On : 01-07-2022
Land Acquisition - Bramhagavhan Lift Irrigation Scheme - Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 - Maharashtra Underground Pipelines and Underground Ducts (Acquisition of Right of User in Land) Act, 2018 - Section 9(1) and (2)
Fact of the Case:
The petitioners, farmers, sought mandamus to complete land acquisition proceedings for the Bramhagavhan Lift Irrigation Scheme's second phase and pay compensation as per the Act of 2013. They also challenged a notification under the Act of 2018 for land acquisition.
Finding of the Court:
The court found that the petitioners' lands were taken for the irrigation scheme, and possession was already acquired. The court held that the Act of 2018 did not apply, and the petitioners were entitled to compensation under the Act of 2013.
Issues: The main issue was whether the petitioners' lands could be acquired under Section 9(1) and (2) of the Act of 2018.
Ratio Decidendi: The court determined that the Act of 2018 did not apply to the case, as the lands were already in possession of the respondents and the petitioners were entitled to compensation under the Act of 2013.
Final Decision: The writ petition was allowed, the notification under the Act of 2018 was quashed, and the respondents were directed to complete the land acquisition proceedings as per the Act of 2013.
JUDGMENT :
S.G. DIGE, J.
1. By this petition, the petitioners are praying for issuance of writ of mandamus against the respondents directing them to complete the land acquisition proceedings in respect of the lands needed for the second phase of Bramhagavhan Lift Irrigation Scheme and pay compensation on declaring the award to the petitioners as per the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (hereinafter referred to as “Act of 2013”).
2. The petitioners also prays to quash and set aside the impugned notification/notice dated 31st August, 2019 issued by the Executive Engineer, Irrigation Department, Aurangabad whereby the respondents have taken a decision to acquire the lands as per section 9(1) and (2) of the Maharashtra Underground Pipelines and Underground Ducts (Acquisition of Right of User in Land) Act, 2018 (hereinafter referred to as “the Act of 2018”).
3. Respondent no. 1 is the State of Maharashtra. Respondent No. 2 is the Chief Engineer of Water Resources Division, Aurangabad. Respondent no. 3 is the Corporation established by the State Government to develop irrigation facilities in the Marathwada region. Respondent nos. 4 to 6 are the authorities of the State.
4. The brief facts of the case are as under:
(b) Respondent nos. 1 to 4 decided to undertake the work of the second phase of the project. For the second phase of the project, the lands situated at village Pimpalwadi and Isarwadi are affected. The advance possession of the lands were taken by private negotiations. It was agreed to make the payment of rental compensation till the acquisition is finalized by declaration of award. Accordingly, the petitioners have handed over the possession of the lands to respondent nos. 1 to 4, so also respondents started paying annual rental compensation to the petitioners since the year 2010 onwards.
(c) Respondent nos. 1 to 3 caused the joint measurement of the lands belonging to the petitioners through respondent no. 4 sometime in November, 2010. It is a matter of record that the respondents changed it’s earlier decision to lay down the pipeline of 35 meters to 13 meters and for that purposes again joint measurement was carried out in the year 2011. On both occasions, after receipt of the joint measurement reports, respondent no. 3 invited the claims and objections from the concerned land owners and thereafter further steps of acquisition have been taken.
(d) Respondent Nos. 3 and 4-acquiring body have determined the rates at which the compensation is to be paid to the petitioners for the acquired lands and submitted a report to the office of respondent no. 2 on 2nd May, 2014.
(e) Respondent nos. 1 to 4 made certain changes in the proposal of the size of the pipeline and a revised administrative sanction was accorded to lay down the pipeline by digging a channel in the width of 13 meters. The petitioners consented to the acquisition of their lands for the area which the respondents needed for laying down the pipelines as per revised proposal. On 15th March, 2016, respondent no. 1 declared the revised proposal of the State Go
The court established that the Act of 2018 did not apply to the case, and the petitioners were entitled to compensation under the Act of 2013 for the acquisition of their lands.
Land of a farmer cannot be acquired with taking recourse to provisions of Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013.
Point of law: The provisions of Section 5 and 6 of PMP Act would categorically show that the legislature attached much importance to the objections of the owner of the land in respect of acquisition ....
Point of law: Thus, we have a scenario where, on the one hand, invocation of urgency provisions under Section 17 of the Act and dispensing with the right to file objection under Section 5A of the Act....
Subsequent purchasers of land can only claim compensation based on their vendors' titles and cannot challenge acquisition proceedings initiated under different statutes.
Acquisition proceedings initiated under the Land Acquisition Act, 1894, where an award has been made five years or more prior to the commencement of the Right to Fair Compensation and Transparency in....
The acquisition proceedings under Award No.12/83 were held not to lapse in terms of Sec. 24(2) of the RFCTLARR Act and they will continue.
The main legal point established in the judgment is that for the acquisition proceedings to lapse under Section 24(2) of the 2013 Act, the landowner must prove that possession was not taken and compe....
Section 24 of the Right to Compensation Act does not apply to acquisitions initiated under the West Bengal Requisition and Acquisition Act; subsequent purchasers can only claim compensation based on ....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.