IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BHARATI DANGRE, J.
K.I.P.L. Vistacore Infra Projects J.V. – Appellant
Versus
Municipal Corporation of the city of Ichalkarnji - Respondent
Commercial Arbitration Petition No.181 of 2023
Decided on : 22-01-2024
Arbitration - Extension of Time - Arbitration and Conciliation Act, 1996, Section 29-A
Fact of the Case:
The petitioner sought an extension of time for completion of pending arbitration proceedings under Section 29-A of the Arbitration and Conciliation Act, 1996. The dispute arose from the construction of sewage treatment plants under the Urban Infrastructure Development Scheme for Small and Medium Towns Scheme (UIDSSMT) Mission.
Finding of the Court:
The court analyzed the interpretation of the term 'Court' in Section 29-A and its applicability to the appointment and extension of the mandate of the Arbitrator. The court considered conflicting views on whether the Principal Civil Court of Original Jurisdiction or the High Court had the authority to extend the mandate of the Arbitrator.
Issues: The main issue was the interpretation of the term 'Court' in Section 29-A and its application to the appointment and extension of the mandate of the Arbitrator.
Ratio Decidendi: The court held that the term 'Court' in Section 29-A should be interpreted in the context of the power to appoint an Arbitrator under Section 11 of the Act. The court concluded that the power to extend the mandate of the Arbitrator should be exercised by the Court that appointed the Arbitrator.
Final Decision: The Arbitration Petition was allowed, and the mandate of the Arbitral Tribunal was extended by a further period of six months.
JUDGMENT :
1. The Arbitration Petition fled by the Petitioner under Section 29-A of the Arbitration and Conciliation Act, 1996 (for short, “The Act”), seeks extension of time for completion of the pending arbitration proceedings, by a period of six months.
The brief background facts reveal that the Urban Infrastructure Development Scheme for Small and Medium Towns Scheme (UIDSSMT) Mission was launched by the Government of India in the year 2012. Under the said scheme, the Municipal Corporation of city of Ichalkarnji, proposed construction of two decentralized Sewage Treatment Plants (STP) of 10+8 MLD capacity alongwith ancillary infrastructure such as pumping stations etc. The funding was sanctioned by the Government of India and the State of Maharashtra on the basis of the Detailed Project Report (DPR) submitted by the Respondents. Pursuant to the tender foated by the Respondent on 01/03/2021, the Petitioner’s bid, being the lowest one, was accepted and the Work Order was issued in it’s favour. By the year 2019, the Petitioner claimed to have completed 55% of work and the delay is attributed to the Respondent, as the possession of the land was handed over belatedly alongwith the drawings for STP.
2. The Petitioner was blacklisted by the Respondent and, hence, it approached this Court in a Writ Petition, which was withdrawn, as Respondent No.1 by its resolution extended the time for completion of the work, by a further period of six months. However, this resolution was stayed by the Collector and by the subsequent resolution passed by the Respondent, the contract of the Petitioner was terminated.
The Petitioner once again fled Writ Petition (St) No.4077 of 2020, challenging the said termination and it was disposed off with a liberty to make representation. Another Writ Petition was fled vide Writ Petition (L) No. 98777 of 2020, challenging the resolution passed by the Municipal Corporation in its general body meeting on being listed before the Division Bench on 22/01/2021, the Municipal Council Ichalkaranji informed the Court that it had passed a resolution dated 19/01/2021, to resolve the disputes between the parties by arbitration to be conducted through a retired District Judge. Upon such offer coming from the Municipal Council, the Petitioner agreed to withdraw it’s proceedings pending before the Urban Development Minister as well as the Petition. The Division Bench of this Court, therefore, appointed Shri Amol V. Deshpande, retired District Judge as an Arbitrator to decide the disputes between the parties by directing that arbitration shall be conducted at Kolhapur. The Arbitrator was also directed to make an endeavour to declare the Award within a period of six months from the date of the order.
3. The Arbitrator conducted a preliminary meeting on 08/02/2021 and the proceedings commenced before the Arbitrator. But, its progress was marred in the wake of the Covid pandemic. By consent of the parties, the mandate of the Tribunal was extended by six months and when it expired on 31/08/2023, an application is fled under Section 29-A of the Act, seeking extension of time to conclude the proceedings.
4. Mr. Godbole, the learned senior counsel has raised a preliminary objection about maintainability of the Petition before this Court, as according to him, Section 2 of the Act has defined the term “Court” under Section (2)(1)(e) of the Act. It is the contention of Mr. Godbole that Section 29-A, which was introduced by Act No.3 of 2016 w.e.f. 23/10/2015, has set out the time limit for passing of the Arbitral Award and by inviting my attention to sub-sections (4) to (6) of the said Section, his specific submission is, the word “Court” used in this context must be read as “Court”, as defined under Section 2(1)(e) and there is no justification in the Petition approaching this Court, seeking extension of time and in this case, since the appointment of the Arbitrator is not under Section 11 of the Act.
The learned senior counsel placed relian
The main legal point established in the judgment is that the term 'Court' in Section 29-A of the Arbitration and Conciliation Act, 1996 should be interpreted in the context of the power to appoint an....
The High Court has exclusive authority to extend the mandate of an arbitrator appointed under Section 11 of the Arbitration & Conciliation Act, 1996, regardless of the pecuniary value of the claim.
The High Court has jurisdiction to extend time for arbitration proceedings, provided the arbitrator was appointed by it, reflecting legislative intent requiring contextual interpretation of 'Court' i....
The term 'Court' in Section 29A of the Arbitration Act must be interpreted contextually, allowing only the appointing court (High Court/Supreme Court) to exercise powers under this section, including....
The court clarified that applications for extending the mandate of an arbitral tribunal under Section 29A must be filed before the Principal Civil Court of original jurisdiction, not the High Court.
The main legal point established in the judgment is that the application for extension of time under Section 29A(4) of the Arbitration Act is to be heard by the Court having jurisdiction to hear Arbi....
The Supreme Court clarified jurisdictional complexities regarding applications for extension of time for arbitral awards under Section 29A, emphasizing specific court roles based on how arbitrators a....
Jurisdiction for extending arbitration periods falls to District Courts under Section 29A(4) of the Arbitration Act, distinct from High Court powers under Section 11(6).
The main legal point established is that the jurisdiction and applicability of Section 29A of the Arbitration and Conciliation Act, 1996 should be considered in the context of the appointing authorit....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.