IN THE HIGH COURT OF JUDICATURE AT BOMBAY
B.P. COLABAWALLA, M.M. SATHAYE, JJ.
Sandesh Vitthal Thakur & Ors. – Appellants
Versus
The Deputy Collector (Land Acquisition) Raigad & Ors. - Respondents
Interim Application No.1515 of 2023 In Writ Petition No.1712 of 2018, Writ Petition No.2046 of 2023, Writ Petition No.2047 of 2023, Writ Petition No.10428 of 2018
Decided on : 16-01-2024
Land Acquisition - Lapse of Acquisition Proceedings - Land Acquisition Act, 1894 - Sections 11A, 17 - Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 - Sections 24(1)(a), 25 - Urgency Clause - Compensation Calculation - Delay in Passing Award
Fact of the Case:
The Writ Petitions sought to challenge the Award dated 22nd April 2015 passed by Respondent No.1 under which the lands of the Petitioners were acquired for the MTHL Sea Link Project. The Petitioners' lands were to be acquired for the Mumbai Trans Harbour Link Project at Jasai Village, Tal-Panvel, Dist- Raigad. Acquisition proceedings under the Land Acquisition Act, 1894 were initiated, and a Section 4 notification was published in the Government Gazette on 2nd July 2009. The urgency clause under Section 17 of the 1894 Act was applied, and no enquiry under Section 5A of the Act was conducted. The Award, impugned in the Writ Petitions, was passed on 22nd April 2015, much after the statutory time frame.
Finding of the Court:
The Court found that the acquisition proceedings lapsed for non-passing of the Award within the statutory period. The urgency clause invoked by the State under Section 17 of the 1894 Act failed as no compensation was paid to the Petitioners, and possession of the lands was not taken. The Court held that there was no inordinate delay in approaching the Court, and the argument of delay was of desperation. The Court directed the State to determine compensation for the Petitioners' lands by passing a fresh Award under the provisions of the 2013 Act.
Issues: The main issues were the lapse of acquisition proceedings due to the delay in passing the Award, the applicability of the urgency clause under Section 17 of the 1894 Act, and the argument of delay in approaching the Court.
Ratio Decidendi: The Court held that the acquisition proceedings lapsed for non-passing of the Award within the statutory period. The urgency clause invoked by the State under Section 17 of the 1894 Act failed as no compensation was paid to the Petitioners, and possession of the lands was not taken. The Court found no inordinate delay in approaching the Court and directed the State to determine compensation for the Petitioners' lands by passing a fresh Award under the provisions of the 2013 Act.
Final Decision: The Writ Petition succeeded, and the Court made the Rule absolute, directing the State to determine compensation for the Petitioners' lands by passing a fresh Award under the provisions of the 2013 Act. The Court held that possession of the acquired lands shall not revert to the Petitioners, and they will only be entitled to compensation for their lands.
JUDGMENT :
B.P. COLABAWALLA J.
1. All the above Writ Petitions inter alia seek to challenge the Award dated 22nd April 2015 passed by Respondent No.1 under which the lands of the Petitioners were acquired. We must mention that the prayers sought in all the Writ Petitions are identical and for the sake of easy reference the prayers in Writ Petition No.1712 of 2018 are reproduced hereunder:-
(b) That his hon. court may be pleased to hold that the impugned award dated 22/4/2015 bearing no.4 of 2006 for acquiring the suit land has lapsed according to provisions of Section 11A of The Land Acquisition Act."
2. The facts in all the above Writ Petitions are really undisputed. The Petitioners lands were to be acquired for the MTHL Sea Link Project, at Jasai Village, Tal-Panvel, Dist-Raigad. This was because CIDCO had envisioned an ambitious project of the "Sewri-Nhava Road" under the New Bombay Project. The execution of this project was entrusted to the MMRDA. CIDCO had made an intention for acquisition of lands admeasuring about 15.79.10 Hectares required for the said project situated at village Jasai, Tal-Uran, Dist-Raigad, out of which CIDCO has claimed to have acquired about only 8.66.00 Hectares of land from the concerned land owners without taking recourse to the provisions of the statute by obtaining some agreements etc. For the balance area of 7.13 Hectares, acquisition proceedings under the Land Acquisition Act, 1894 (for short "the 1894 Act") came to be initiated which includes the Petitioners lands. Accordingly, and to take these acquisition proceedings forward, a Section 4 notification came to be published in the Government Gazette on 2nd July 2009. Further, individual notice under Section 4(1) of the 1894 Act were also issued to the concerned landowners whose lands were proposed to be acquired for the said "Sewri-Nhava Road Project". It is not in dispute that the Petitioners were also served with the notice under Section 4(1) of the 1894 Act. It appears that in the present case the urgency clause [under Section 17 of the 1894 Act], was applied to this acquisition and hence no enquiry under Section 5A of the said Act was conducted. Thereafter, a declaration under Section 6 of the 1894 Act came to be published in the Government Gazette on 19th June 2012 and published in the local newspaper on 18th July 2012. The final date of publication of the Section 6 declaration was 22nd December 2012. However, despite this, the Award, which is impugned in the present Writ Petition, came to be passed only on 22nd July 2015.
3. In this factual backdrop, Mr. Thakur, the learned advocate appearing on behalf of the Petitioners, submitted that though in the Petition it is averred that because of the provisions of Section 11A of the 1894 Act, the above acquisition has lapsed because no Award is passed within 2 years from the final date of publication of the Section 6 declaration (i.e. within 2 years from 22nd December 2012), he is not pressing this argument in light of the law laid down by the Hon'ble Supreme Court in the case of The Executive Engineer, Goshikhurd Project Ambadi, Bhandara, Maharashtra Vidharbha Irrigation Development Corporation V/S Mahesh & Ors [(2022) 2 SCC 772]. He fairly submitted that this decision clearly stipulates that if acquisition proceedin
Compliance with Section 17(3-A) of the Land Acquisition Act, 1894 is mandatory for absolute vesting of the notified land, and the requirement to pass the award within the time frame contemplated unde....
The provisions of Section 11-B of the 1990 Act shall not be applicable to the cases where the Government has invoked Section 17 and the Collector has scrupulously complied with the requirements of Se....
The court established that the failure to comply with the procedural requirements of the J&K Land Acquisition Act, particularly regarding the timely passing of awards and the payment of compensation,....
The revised award passed after the expiry of two years from the date of Declaration was deemed to be a fresh award, and the acquisition proceedings stood lapsed under Section 11-A of Act, 1894. The c....
The main legal point established in the judgment is that the acquisition proceedings lapsed as no award was made within 2 years of the declaration under Section 6 of the 1894 Act, and the State was d....
Award validity under the Land Acquisition Act hinges on strict adherence to prescribed timelines, with stays influencing but not absolving time limits for passing awards.
Section 25 of LARR Act reads as Period within which an award shall be made –The Collector shall make an award within a period of twelve months from the date of publication of the declaration under se....
Compensation in land acquisition must adhere to statutory requirements, including formal awards under section 11 of the Land Acquisition Act, or provisions of the updated Act of 2013 apply.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.