IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NEELA GOKHALE, J.
Hyundai Construction Equipment India Pvt Ltd., Through its Authorized Signatory Mr. Abhishek Shukla - Petitioner
Versus
M/s. Saumya Mining Limited and Anr. - Respondents
Arbitration Petition No.32 Of 2022
Decided On : 11-01-2024
Arbitration - Appointment of Arbitrator - Arbitration & Conciliation Act, 1996 - Section 11 - Agreements dated 1st October 2011 and 26th September 2013 - Clause 25 and Clause 31 - Kolkata High Court's jurisdiction - Supreme Court's interpretation of Section 42 and Section 11(6)
Fact of the Case:
The petition seeks appointment of an arbitrator under Section 11 of the Arbitration & Conciliation Act, 1996 to decide the dispute arising from agreements dated 1st October 2011 and 26th September 2013 between Hyundai and Saumya. Disputes arose, and Hyundai invoked the arbitration clause, leading to the present petition.
Finding of the Court:
The Court found that the Kolkata High Court had jurisdiction to entertain the application under Section 11 of the Act, as the cause of action and the earlier application arose within Kolkata. The Court relied on the Supreme Court's interpretation of Section 42 and Section 11(6) to dismiss the petition for appointment of an arbitrator in this Court.
Issues: Jurisdiction of the Court to entertain the application under Section 11 of the Act, interpretation of arbitration clauses in the agreements, and the applicability of Section 42 and Section 11(6) as per the Supreme Court's decisions.
Ratio Decidendi: The Court held that the Kolkata High Court had jurisdiction to entertain the application under Section 11 of the Act, as the cause of action and the earlier application arose within Kolkata. The Court relied on the Supreme Court's interpretation of Section 42 and Section 11(6) to dismiss the petition for appointment of an arbitrator in this Court.
Final Decision: The Court dismissed the Arbitration Petition for appointment of an arbitrator in this Court, citing lack of jurisdiction. No order as to costs was made.
JUDGMENT :
1. The petition seeks appointment of an arbitrator under Section 11 of the Arbitration & Conciliation Act, 1996 (“Act”) to decide the dispute that has arisen between the parties out of agreements dated 1st October 2011 and 26th September 2013. Both the agreements are executed at Kolkata, West Bengal. The Petitioner (“Hyundai”) is a company engaged in the manufacture and supply of heavy construction equipment having all India operations. The Respondents (“Saumya”) is also a company engaged in the business of mining and undertaking infrastructure projects. Saumya has their registered offices in Kolkata.
2. By agreement dated 1st October 2011, Hyundai agreed to deliver to Saumya specified equipment for a purchase consideration. The agreement contains schedule pertaining to installments in which the purchase price would be paid by Saumya to Hyundai. Clause 25 of the agreement pertains to reference to arbitration in case of any dispute. It reads as thus;
3. The 2nd Agreement dated 26th September 2013 is titled ‘Agreement of Sale in Installment’. By way of this agreement, Hyundai agreed to give a hydraulic excavator and other equipment on hire to Saumya. Saumya intended to use the said equipment for excavation. The hire charges have been mentioned in the agreement. Clause 31 of the agreement is the arbitration clause. It reads as thus;
4. There arose some disputes between the parties out of the 2 agreements leading to Hyundai issuing a demand notice dated 16th October 2015 to Saumya. Saumya failed to reply. The Petitioner thus filed Arbitration Petition No.265 of 2016 in the Kolkata High Court. The Kolkata High Court appointed a Court Receiver to take possession of machinery and other equipment. However, since the Respondent had shifted the machinery to areas unknown to the Petitioner, time was extended for the Court Receiver to take possession of the remaining machinery. Thereafter, by notice dated 16th April 2019, Hyundai invoked the arbitration clause and conveyed to the Saumya that Hyundai had nominated its arbitrators but requested Saumya to nominate its arbitrator if they did not agree to the arbitrator appointed by the Petitioner. Saumya issued reply dated 27th May 2019 to the lawyers of Hyundai through their own counsel. While denying the claim of the Petitioner, Saumya also denied any existing juridical relations between the parties and also raised the issue of limitation in its notice-reply. The Petitioner has thus filed the present petition seeking appointment of an arbitrator.
5. Mr. Wable, learned counsel appearing for the Petitioner contends that since arbitration clause in agreement dated 26th September 2013 specifies that the arbitration proceedings shall be conducted at Pune in India, it is this Court that is vested with jurisdiction to entertain an application under Section 11 of the Act. Conceding that while both agreements being execut
The main legal point established in the judgment is the interpretation and application of Section 42 and Section 11(6) of the Arbitration & Conciliation Act, 1996, as per the Supreme Court's decision....
The main legal point established in the judgment is that the Court with jurisdiction to entertain an application under Section 11 of the Act is the one where the cause of action and the application w....
The court upheld party autonomy, determining that the High Court has jurisdiction to appoint a Sole Arbitrator even with an exclusive jurisdiction clause designating Gurugram as the venue.
Jurisdiction for arbitration petitions must align with the exclusive contractually specified jurisdiction, confirming that the High Court lacked authority to entertain the application under Section 1....
It is a settled position of law that Section 42 of the Act would not apply to an application that has been filed under Section 11 of the Act.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.