IN THE HIGH COURT OF BOMBAY
Mangesh S. Patil, S.G. Chapalgaonkar, JJ.
State of Maharashtra - Appellant
Versus
Morya Infrastructure Pvt. Ltd - Respondent
Commercial Arbitration Appeal (St.) No. 1440 of 2023
Decided On : 01-02-2023
CONDONATION OF DELAY - ARBITRATION AND COMMERCIAL COURTS - Arbitration and Conciliation Act, 1996 - Sec. 34, Sec. 37; Commercial Courts Act, 2015 - Sec. 13 - The court discussed the provisions of the Arbitration and Conciliation Act and the Commercial Courts Act, particularly focusing on the timelines for filing appeals and the conditions under which delays may be condoned. The court emphasized the need for a bona fide explanation for the delay and referenced the Supreme Court's decision in Government of Maharashtra v. Borse Brothers, which allows for discretion in condoning delays under certain circumstances. The court ultimately found that the department's delay was not intentional and warranted condonation.
Fact of the Case:
The Public Works Department of Maharashtra filed a civil application seeking condonation of a 187-day delay in appealing against a judgment that dismissed its application under Sec. 34 of the Arbitration Act. The delay was attributed to administrative formalities and issues with e-filing.
Finding of the Court:
The court found that the delay was not deliberate or intentional, and the department had provided sufficient reasons for the delay. It also noted that the claimant did not demonstrate any mala fides or deliberate inaction on the part of the department.
Issues: Whether the delay in filing the appeal should be condoned and if the reasons provided by the department were sufficient to warrant such condonation.
Ratio Decidendi: The court held that while the law of limitation applies equally to the State, the peculiar circumstances surrounding the department's delay, including administrative processes and e-filing issues, justified the exercise of discretion in condoning the delay.
Final Decision: The court allowed the civil application, condoned the delay subject to the department depositing costs of Rs. 10,000 within four weeks, and stayed the execution of the award for the same period.
JUDGMENT/ORDER
MANGESH S.PATIL, J. - Civil application no. 651 of 2023 is filed by the Public Works Department of the State of Maharashtra (hereinafter referred to as "Department") seeking condonation of delay calculated as 187 days in filing appeal under Sec. 37 of the Arbitration and Conciliation Act, 1996 ("Arbitration Act") read with Sec. 13 of the Commercial Courts Act, 2015 ("Commercial Courts Act"), against the judgment and order passed by the learned District Judge-2 & Commercial Court, Beed in a proceeding bearing Civil Miscellaneous Application no. 87 of 2018 dtd. 6/5/2022 dismissing the department's application preferred under Sec. 34 of the Arbitration Act.
2. The learned Additional Government Pleader by referring to the application and the additional affidavit filed by the department submitted that the facts and circumstances leading to the filing of the appeal are peculiar. The department manned by the personnel has been made to suffer the award because of the misdeeds of its officers and apart from the cause which the department is required to satisfy for condonation of delay, all the happenings throughout this proceeding right from the appointment of the arbitrator, are relevant factors for this Court to exercise its discretion.
3. As regards the cause for the delay, Mr. P.K. Lakhotiya, learned AGP would submit that though the department is not entitled to claim any exception and the law of limitation has to be applied equally even against it, there are sufficient circumstances which prevented it from preferring the appeal in time. He would submit that some time was lost to complete the administrative formalities and in seeking instructions and documents. The delay is neither deliberate nor is it intentional. The department was not to gain anything by causing the delay particularly when it is intending to challenge the award which is passed by the sole arbitrator in spite of a stipulation in the clause 3/4/17(iii)(a) that the arbitral tribunal would comprise of three arbitrators; one to be appointed by each of the sides and the third by the two such arbitrators of the parties.
4. The learned AGP would submit that according to the Bombay High Court Rules, this being an arbitration cum commercial appeal, it is supposed to be filed online. An attempt was made to submit it on 14/12/2022 but for want of bill of costs, the system was not accepting the registration and some time was lost therein till it was finally registered on 11/1/2023. The application under Sec. 34 of the Arbitration Act was decided on 6/5/2022 and the appeal under sec. 37 has been filed on 19/11/2022. The limitation for filing appeal is 60 days. Five (5) days were required for obtaining certified copies from the date of application till its receipt and there is 132 days delay.
5. Mr. Lakhotiya, the learned AGP would then refer to the decision of the Supreme Court in the matter of Government of Maharashtrta (Water Resources Department) represented by Executive Engineer Vs. Borse Brothers Engineers and Contractors Pvt. Limited; (2021) 6 SCC 460. He would submit that the department is entitled to take benefit of this decision since the delay has occurred bona fide and not in a negligent manner.
6. The learned advocate Mr. Singh for the claimant would strongly oppose the application by referring to the affidavit in reply. He would submit that there is no sufficient cause demonstrated by the department for this Court to exercise the discretion. Even the application for certified copy was not filed soon after pronouncement of the judgment and order by the learned District Judge on 6/5/2022. The calculation of delay is also incorrect. There is delay of 253 days. He would submit that the department is under an obligation to demonstrate sufficient cause and any reference to the merits of the appeal is irrelevant. He would also place reliance in the judgment of Borse Brothers (supra). The delay is enormous and the right which by lapse of time has vested in the c
The court established that delays in filing appeals can be condoned if sufficient cause is shown, particularly when the delay is not due to negligence or mala fides, and emphasized the importance of ....
The law of limitation applies equally to all parties, including the Government, and a lack of diligence in filing appeals can result in rejection of delay condonation applications.
The court adopted a liberal and justice-oriented approach in the matter of condonation of delay, allowing the delay of 23 days to be condoned as sufficient cause was explained by the DDA.
The court emphasized that delay in filing appeals under the Arbitration Act must be justified by sufficient cause, with negligence being insufficient for condonation.
The court emphasized a pragmatic approach in determining 'sufficient cause' for delays attributed to government entities, asserting equal application of limitation laws for all parties involved.
Point of Law : Merely because the appellant is Government organization, lenience cannot be shown to condone such a long delay.
The court may condone delays in filing appeals where sufficient cause is shown, including circumstances beyond a party's control, advocated particularly in light of unprecedented events like a pandem....
Timely filing of appeals under the Arbitration and Conciliation Act is crucial; bureaucratic delays are inadequate reasons for condoning significant delays.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.