SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Article Pause Article
judgment-img

2025 Supreme(Bom) 1117

IN THE HIGH COURT OF JUDICATURE AT BOMBAY 
Somasekhar Sundaresan, J.
Larsen And Toubro Limited - Petitioner
Versus
High Parra Construction Pvt Ltd - Respondent
Notice Of Motion No. 1717 Of 2018, Notice Of Motion (L) No. 1912 Of 2018, Arbitration Petition (L) No. 899 Of 2018
Decided On : 11-07-2025

Advocates:
Advocate Appeared:
For the Petitioner: Mr. Nimay Dave, a/w Faisal Sayyed & Padmesh Joshi, i/b Manilal Kher Ambalal & Co.
For the Respondent: Mr. Siddharth Chhabria, a/w Khushnuma Khan & Inayat Ali Qureshi, i/b K K Associates

A party challenging an arbitral award under the MSMED Act must deposit 75% of the awarded amount, and courts will not condone delay unless sufficient cause is established.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - Micro, Small and Medium Enterprises Development Act, 2006 - Section 19 - Application to challenge arbitral award - Delay in filing challenge and lack of deposit of 75% of awarded amount as per statutory requirements; Court cannot condone delay without sufficient cause. (Paras 2, 4, 29)

(B) Condonation of Delay - The court must objectively assess claims of sufficient cause for delay; the reasons stated must be sound and logical. Notably, large corporates may not receive leeway typically afforded to smaller enterprises. (Paras 15, 20)

(C) Judicial Policy - The MSMED Act imposes a statutory framework designed to ensure expeditious resolution of disputes involving small enterprises, seeking to deter unnecessary challenges by imposing pre-conditions on such challenges. (Paras 26, 27)

Facts of the case:
The petitioner sought to challenge an arbitral award for Rs.44,513 awarded to the respondent but failed to deposit the required amount and claimed a delay in filing the challenge.

Findings of Court:
The delay in filing the challenge was not condoned due to insufficient evidence of the receipt of the award, and the reasons for the delay were deemed unacceptable.

Issues: Whether the delay in filing the challenge should be condoned and if the petitioner’s reasons sufficiently justify the lack of deposit.

Ratio Decidendi: The court ruled that the petitioner did not demonstrate sufficient cause for delay and that the MSMED Act's requirements must be adhered to for a challenge to be entertained.

Result: Request for condonation of delay rejected; application dismissed.

Table of Content
1. challenge to arbitral award under msmed act (Para 1 , 2)
2. arguments regarding delay and deposit requirements (Para 3 , 4 , 5 , 6)
3. court's verification of delay claims and receipt date (Para 7 , 8 , 9 , 10 , 11)
4. assessment of reasons for condonation of delay (Para 12 , 13 , 14 , 15 , 16 , 17 , 18)
5. judicial discretion and context in condonation of delay (Para 19 , 20 , 21 , 22 , 23)
6. public policy and legislative intent of msmed act (Para 25 , 26)
7. conclusion on condonation of delay denied (Para 27 , 28 , 29 , 30 , 31)

JUDGMENT :

Somasekhar Sundaresan, J.

Context and Background:

1. The captioned primary proceedings are essentially an application seeking to challenge an arbitral award dated March 3, 2018 (“Impugned Award”) passed by the MSME Facilitation Council, Mumbai (“MSME Council”) under Section 34 of the Arbitration and Conciliation Act, 1996 (“Arbitration Act”).

2. The Petitioner, Larsen & Toubro Ltd. (“L&T”) seeks to challenge payment of a princely sum of Rs.44,513/- awarded to the Respondent, High Parra Construction Pvt. Ltd. (“High Parra”) with interest thereon to be computed in terms of the Micro, Small and Medium Enterprises Development Act, 2006 (the “MSMED Act”). Till date, L&T has deposited nothing despite a deposit being a statutory per- condition for any court to entertain a challenge to an arbitral award passed under the MSMED Act.

Hurdles to the Challenge:

3. That apart, the main hurdle to L&T’s challenge is the admitted delay in filing the application under Section 34 of the Arbitration Act. It is L&T’s case that the delay is within the 30-day window after the expiry of three months from the receipt of the Impugned Award. This is the time window within which it is permissible for this Court to condone delay under Section 34 (3) of the Arbitration Act, provided sufficient cause is shown.

4. As noticed above, under Section 19 of the MSMED Act, no Court shall entertain any challenge to an arbitral award passed by the MSME Council unless a deposit of 75% of the amount awarded is made. Section 19 of the MSMED Act contains a statutory embargo on entertainment of the challenge. Admittedly, L&T has not deposited a single rupee since 2018.

5. Mr. Nimay Dave, Learned Counsel representing L&T would submit that L&T is willing to make such a deposit now along with interest computed until today, within a few weeks as permitted by this Court. According to him, L&T has a strong case on merits and the delay ought to be condoned and the deposit ought to be permitted to ensure that a meritorious challenge is not shut out on these two preliminary objections.

6. Mr. Siddharth Chhabria, Learned Counsel representing High Parra would counter these submissions by indicating that there is simply no semblance of a reason in the application for condonation of delay, and that sufficient cause has not been made out.

Factual Matrix:

7. The following facts would be relevant to consider whether a delay in filing this challenge under Section 34 deserves to be condoned:-

a) The Impugned Award is dated March 3, 2018 and is passed by the MSME Council based in Mumbai;

b) The Impugned Award is for a sum of Rs. 44,513 being declared as payable by L&T to High Parra, along with interest in terms of the MSMED Act;

c) L&T, which is also headquartered in Mumbai claims to have received the Impugned Award only on April 12, 2018, nearly 40 days after the Impugned Award was passed. However, there is nothing to show the actual date of receipt of the Impugned Award;

d) Even if one were to accept L&T’s stated date of receipt, the three-month period within which a challenge is permitted under Section 36(3) of the Arbitration Act, would have expired on July 12, 2018;

e) The period of thirty days after the aforesaid three-month window, would end on August 11, 2018; and

f) This challenge under Section 34 of the Arbitration Act is said to have been filed on August 10, 2018, purporting to be just one day before the last date on which this Court wou

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
whatsapp-icon Back to top