SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Bom) 1476

IN THE HIGH COURT OF JUDICATURE AT BOMBAY
Sandeep V. Marne, J.
Central Railway-Mumbai Division - Petitioner
Versus
A-1 Laundry Services (JV) - Respondent
Comm. Arbitration Petition No.454 of 2024, Interim Application No.4173 of 2025, Interim Application (L) No.18932 of 2024
Decided On : 21-11-2025

Advocates Appeared:
For the Petitioner: Mr. Narayan Bubna
For the Respondent:Mr. Arshad Shaikh, Senior Advocate with Mr. Ranjit Agashe, Mr. Rajendra Jain, Ms. Namrata Agashe, Mr. Pranil Lahigade, Mr. Aniket Pardeshi i/b Ms. Vinsha S. Acharya

An Arbitral Tribunal must adhere to explicit contractual terms without imposing external fairness standards, as such actions may result in rewriting the contract, which is impermissible under arbitration law.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - Challenge to arbitral award concerning recovery of lost linen, delay penalty, and fixed cost compensation - Tribunal awarded Rs.4,89,49,985/- - Petitioner contended award ignored contract provisions and improperly relied on external circulars. (Paras 1-48)

(B) Legal principles - Arbitral Tribunal must strictly adhere to the contract's terms without rewriting them; reliance on external guidelines must be justified.

(C)

Facts of the case:
Disputes arose from a contract for laundry services between petitioner and respondent; the award was contested on grounds of improper application of contract clauses.

Findings of Court:
Tribunal's reliance on circulars over defined contract terms deemed improper. (E)

Issues: Whether the Tribunal correctly interpreted the contract in awarding claims against external circulars. (F)

Ratio Decidendi: The Tribunal exceeded its jurisdiction by applying external fairness standards contrary to explicit contract terms. (G)

Result: Petition partly allowed; certain claims set aside, resulting in a revised award of Rs.1,73,20,991/-.

Table of Content
1. arbitration petition challenging the tribunal's award (Para 1 , 2 , 3 , 4)
2. petitioner's objections to the tribunal's award (Para 5 , 6)
3. respondent's defense against the petitioner's claims (Para 7 , 8 , 9 , 10 , 11)
4. court's analysis on claims and award confirmations (Para 12 , 14 , 15 , 16 , 17 , 18)
5. judicial reasoning regarding tribunal exceeding contractual terms (Para 19 , 24 , 27 , 39 , 45)
6. court's examination of delay penalties and contract terms (Para 30 , 31 , 33 , 38 , 46)
7. final order on claims and petition resolution (Para 48 , 49 , 50)
JUDGMENT :

Sandeep V. Marne, J.

1) Petitioner-Central Railway has filed the present Petition under the provisions of Section 34 of the Arbitration and Conciliation Act, 1996 (Arbitration Act) challenging the Award dated 7 March 2024 passed by the Arbitral Tribunal awarding sum of Rs.4,89,49,985/- in favour of the Respondent alongwith GST. The disputes between parties have arisen during performance of contract by the Respondent for collection of soiled linen from AC coaches, washing in mechanized laundry, supply and loading of washed linen into AC coaches. Out of various claims raised by the Respondent, the Arbitral Tribunal has awarded claims towards loss of linen, delay penalty, penalty over ceiling of 10%, fixed cost compensation and electricity charges totally amounting Rs.4,89,49,985/-.

2) A brief factual background in which the Arbitration Petition arises is stated thus:

Petitioner-Central Railway invited open tender dated 11 January 2010 for setting up and operating dedicated mechanized laundry in railway premises in Mumbai at Wadibundar Depot on Build-Own-Operate- Transfer model (BOOT) for initial period of 15 years including supply and installation of plant, equipment and related infrastructure (works) alongwith collection and transportation of soiled linen from coaches/trains and transportation/loading of washed and packed linen in the coaches/trains at Chhatrapati Shivaji Maharaj Terminus (CSMT), Lokmanya Tilak Terminus (LTT) and Dadar Terminus (DT). Respondent participated in the tender process and emerged as a successful bidder. Respondent was awarded contract by the Petitioner at the cost of Rs.79,94,45,813/- for a period of 15 years from the date of commissioning of the plant. Contract Agreement dated 17 March 2012 was executed between the parties. The contract commenced from 16 April 2013.

3) During execution of the contract, disputes and differences arose between the parties and as per Clause-64(1) contained in the Regulation of Tenders and Contracts and General Conditions Of Contract dated 16 July 2020, the Respondent invoked arbitration clause and sought resolution of the disputes. The General Manager of Central Railways constituted Arbitral Tribunal comprising of three retired railway officials, Shri. Prashant K. Ranade, IRTS. Retd. CAO, System, CR as presiding Arbitrator, Shri. Chandra Mohan Jindal, Retd, DG. IRIFM and Shri. Alok Kumar Tewari, Retd. AM (EnHM), Railways Board as Co-Arbitrators.

4) The Respondent filed Statement of Claim claiming an amount of Rs.18,01,83,764/- from the Petitioner. The claim was resisted by the Petitioner-Railways by filing Statement of Defense. Both the sides filed various documents in support of their respective claims. It appears that oral evidence was not led by either of the parties. Based on documentary evidence and written arguments, the Arbitral Tribunal has allowed most of the claims sought for by the Respondent by its Award dated 7 March 2024. Petitioner-Railways are directed to pay to the Respondents aggregate claim amount of Rs.4,89,49,985/-. Aggrieved by the Award dated 7 March 2024, the Petitioner has filed the present Petition under Section 34 of the Arbitration Act.

5) Mr. Bubna, the learned counsel appearing for the Petitioner- Central Railway has submitted that the Arbitral Tribunal has erred in awarding claims to the Respondent relating to recovery of loss of linen covered by Issue Nos.1 and 2.

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top