SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Article Pause Article
judgment-img

2025 Supreme(Bom) 1653

IN THE HIGH COURT OF JUDICATURE AT BOMBAY
Somasekhar Sundaresan, J.
Rajasthan State Co-op Oil Seed Growers Federation Ltd. (Tilam Sangh) - Appellant
Versus
B.G. Shirke Construction Technology Pvt. Ltd. & Anr. - Respondents
Arbitration Appeal No. Of 47 Of 2013, Arbitration Appeal No. Of 48 Of 2013, Arbitration Appeal No. Of 49 Of 2013
Decided On : 03-11-2025

Advocates Appeared:
For the Appellant : Mr. Rajiv Narula a/w Tarang Jagtiani, i/b Thangiani, Narula & Associates
For the Respondent: Mr. Sukand Kulkarni, Ms. Archita Gharat a/w Prabhakar M. Jadhav, Mr. Prabhakar M. Jadhav

The court determined that non-signatories may be bound by arbitration agreements through their actions and involvement in the contractual relationship, allowing enforcement of arbitral awards.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 37 - The appeals challenge orders by the District Court regarding arbitral awards related to construction projects. The court found that the appellant was a veritable party to the arbitration agreement, affirming jurisdiction over arbitral decisions. (Paras 1, 17, 28)

(B) Privity of Contract - The court ruled that non-signatory parties may be bound by arbitration agreements if they demonstrate intent through actions. The appellant's involvement in the project indicated implied consent to arbitrate. (Paras 21, 24)

(C) Grounds for Appeal - Courts must defer to arbitral awards unless there is a clear absence of jurisdiction or other grievous errors. Here, the findings of the arbitral tribunal were maintained without sufficient grounds for interference. (Paras 15, 28)

Facts of the case:
The appellant engaged a project consultant for construction. Disputes led to arbitration, with awards issued. Challenges were filed based on jurisdictional claims by the appellant, arguing non-privity of contract. (Paras 2-4)

Findings of Court:
The court upheld the arbitral award and found the appellant had a legitimate connection to the contract. Joint liability to a third party (the contractor) was deemed unsupported. (Paras 26-28)

Issues: The court addressed whether the appellant was a party to the arbitration agreement and whether the awards were enforceable against them. (Paras 15, 17)

Ratio Decidendi: The court emphasized that implied consent to an arbitration agreement may arise from conduct establishing a significant connection, thus validating the arbitral tribunal's jurisdiction over disputes involving non-signatories. (Paras 17-20, 28)

Result: Appeal dismissed.

Table of Content
1. context of arbitration appeals and related agreements. (Para 1 , 2 , 3 , 4 , 5)
2. contentions from both parties regarding contractual obligations. (Para 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13)
3. analysis of jurisdiction and privity of contract. (Para 14 , 15 , 16 , 17 , 18 , 19 , 20 , 21 , 22 , 23)
4. implications of the court's findings and conclusions. (Para 24 , 25 , 26 , 27)
5. final judgment on the appeals brought forth. (Para 28 , 29 , 30)

JUDGMENT :

Somasekhar Sundaresan, J.

Context and Factual Background:

1. The captioned appeals are filed under Section 37 of the Arbitration and Conciliation Act, 1996 (“the Act”) challenging orders passed by the Learned District Court Pune, disposing of challenges to arbitral awards passed by a three-member arbitral tribunal in three separate arbitral awards, in all of which the issues are just the same.

2. In a nutshell, the Appellant, Rajasthan State Co-op Oil Seed Growers Federation Ltd. (“Tilam Sangh”) was desirous of setting up silos for storage and process of mustard seeds in three different locations – a 100-tonnes per day facility at Merta City (Nagaur District); a 50-tonnes per day facility at Gangapur City (Sawaimadhopur District); and a 100-tonnes per day facility at Sri Ganganagar (Ganganagar District) – in the State of Rajasthan. Towards this end, Tilam Sangh engaged National Heavy Engineering Co-operative Ltd. (“NHEC”) as the Project Management Consultant (“PMC”), which in turn engaged Shirke Structurals Pvt. Ltd. (“Shirke”) to carry out the works involved in each of the aforesaid projects. Shirke underwent a name change later.

3. Work was completed, and payment claims were made by Shirke, which filed civil suits. NHEC filed applications under Section 8  of the Act indicating that the disputes are subject matter of an arbitration agreement. These were allowed and an arbitral tribunal was constituted in each matter, and arbitral awards came to be passed.

4. The Learned Advocates for the parties have consented to take up Appeal No. 47 of 2013 as the representative lead matter, indicating that adjudication of issues in that Appeal would be dispositive of all Appeals. By consent of the parties, all references to facts, dates and the record are made to those contained in Appeal No. 47 of 2013, on the understanding that this judgement would cover all the captioned proceedings.

5. A brief overview of relevant facts is set out below:-

a) On November 6, 1987, Tilam Sangh executed an agreement with NHEC as the PMC (“PMC Contract”);

b) PMC executed an agreement dated September 28, 1989 (“Agreement”) appointing Shirke as the contractor to carry out the work. The work was to be commenced by October 5, 1989 and completed by January 20, 1990;

c) Work was completed and a certificate of completion was issued on October 31, 1993;

d) On April 4, 1994, Shirke made a claim for a sum of Rs. ~4.83 lakh;

e) Shirke filed a Special Civil Suit 1734 of 1995 (“Civil Suit”) against Tilam Sangh and NHEC, but it was on an application filed by NHEC, the Civil Suit was rejected, referring the parties to arbitration;

f) On May 20, 2002, Tilam Sangh filed a Written Statement in response to the Statement of Claim and also filed a Counter-claim;

g) On April 4, 2003, Tilam Sangh claimed to have made a mistake, withdrew the Counter-Claim, and claimed that the Learned Arbitral Tribunal had no jurisdiction since there was no privity of contract between Tilam Sangh and Shirke under the Agreement, and the arbitration clause could not bind Tilam Sangh;

h) On June 2, 2003, an arbitral award was passed awarding Rs. ~4.83 lakh coupled with interest at 15% per annum from September 4, 1993 and at 12%  per annum from May 1, 2002 until realisation (“Arbitral Award”). Both Tilam Sangh and NHEC were made jointly liable to pay the amount to Shirke under the Arbitral Award;

i) Special Leave Petition filed in the Supreme Court was disposed of giving leave to Tilam Sangh to raise jurisdictional grounds when pursuing a challenge under

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
whatsapp-icon Back to top