IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI
D.V.S.S. SOMAYAJULU, V. SRINIVAS, JJ.
M/s. Sri. SCL Infratech Ltd. – Petitioner
Versus
M/s V.R. Constructions – Respondent
Commercial Court Appeal.No.7 of 2018
Decided On : 05-05-2023
This case involves a dispute over escalation charges and interest in a contract between the appellant and the 1st respondent. The appellant argued that the lower Court's judgment was against settled principles of law, specifically pointing out the lack of a condition for payment of escalation charges in the contract and the absence of pleading about escalation in the suit. The appellant also contested the lack of discussion on various issues and the award of interest without proper evidence and pleading. The respondent, on the other hand, argued that all issues were considered, and the judgment cannot be criticized for not separately answering each issue. The respondent also justified the award of interest as a discretionary remedy due to delay. The Court found that the trial Court failed to properly pronounce judgment on all issues and answer them in seriatim, and proceeded to decide the case based on the available evidence instead of remanding the matter. The Court also highlighted the absence of a clause for payment of escalation charges in the agreements between the parties and the lack of pleading and proof for the claim of interest. Ultimately, the Court concluded that the trial Court committed a gross error in awarding interest without proper discussion, considering the pleadings, evidence, and applicable law, and reversed all findings of the trial Court, setting aside the judgment and decree.
JUDGMENT :
(D.V.S.S. Somayajulu, J.)
1. This appeal is filed questioning the judgment and decree dated 08.12.2017 passed in O.S.No.83 of 2017 by the Commercial Court-cum-Principal District Judge, Kurnool.
2. Sri B.Adinarayana Rao, learned senior counsel appeared for the appellant, whereas Sri N.Subba Rao, learned senior counsel appeared for the respondents.
3. Learned senior counsel for the appellant essentially argued that the judgment of the lower Court is against the settled principles of law. He points out that in the contract between the appellant and the 1st respondent, there is no condition for payment of escalation charges. In the parent contract between the appellant and the State, there is an escalation clause which is not, however, included in the agreement between the plaintiff and defendant No.1. It is also pointed out that the pleading about the escalation in the suit is absolutely lacking and that the trial Judge committed an error in awarding escalation. It is, according to him, a matter of contract and the Court cannot award escalation on the grounds of equity or otherwise. He also points out that the claim made is essentially for alleged balance due, whereas escalation was awarded. He also argues that the documents filed do not amount to evidence in the eye of law and merely on the basis of some consolidated and typed statements, huge sums of money were awarded without considering the fact whether these documents actually constitute evidence or not. He also points out that in the ultimate conclusion, learned Judge did not discuss the quantum of the claim or about the manner in which it was proved. Merely on the ground that the main parent agreement contained an escalation clause and the appellant received the escalation from the State Government, the trial Judge awarded the amounts. He submits that this is totally contrary to law.
4. He also points out that the conclusions are at page 51 and 52 of the impugned judgment are clearly erroneous. Prior to that he states there is a discussion on the various issues without leading to a legal conclusion. He also points out that although the issues were framed, the same are not answered. He points out that initially clear and cogent issues were framed and thereafter additional issues were also framed. Learned counsel points out that as per law, each of these issues must be answered properly and clearly, since they have a bearing on the final decision. In the end, these issues were not answered. This is a fatal flaw as per him. As far as interest is concerned, he contends that the issue No.5 is with regard to interest, but there is no discussion whatsoever about the “delay” or the quantum of interest. He submits that the pleading and proof about interest is not there. Merely on the basis of a tabular statement interest was awarded.
5. Learned counsel therefore submits that the impugned judgment is not in accordance with law and should be set aside. He also files a compendium of case law, which is referred to later in the judgment.
6. In reply to this, Sri N.Subba Rao, learned senior counsel argues that the issues were all considered and thereafter only the order was passed. He points out that the learned Judge discussed the oral and documentary evidence before coming to the conclusions. He draws the attention of this Court to the various pages in the judgment where evidence of the witnesses and documents were also discussed and therefore, he submits that the impugned judgment cannot be commented upon only because all the issues were not separately answered. He submits that since issues 1 to 5 are interlinked, they were rightly clubbed together and a final order was passed. He also points out that admittedly from a reading of the evidence, there is a delay and therefore, he submits that it is within the competence of the Court to award interest. Learned counsel points out that almost five (5) witnesses were examined and 32 documents were marked for the plaintiff and anoth
Bank of India and another v. K.Mohandas and others
M.R. Engineers and Contractors Private Limited v. Som Datt Builders Limited
Sharma and Associates Contractors Private Limited v. Progressive Constructions Limited
Central Coop. Bank Ltd. V. Kamalaveni Sundaram
Secretary, Irrigation Department, Govt. of Orissa vs. G.C. Roy
The main legal point established in this judgment is the requirement for proper pleading and proof of claims, including escalation charges and interest, in a contract dispute. The Court emphasized th....
The main legal point established in this judgment is that the award of escalation charges and interest in a commercial contract dispute should be based on proper pleading, proof, and consideration of....
The suit was within limitation as the cause of action accrued upon the non-payment of the final bill, and not completing the price escalation calculations per the contract terms invalidated the defen....
The main legal point established in the judgment is the entitlement of the petitioner to escalation cost under the contractual provision of Clause-32(a)(b)(c) despite the submission of a 'no claim ce....
Failure to raise claims for escalation in a timely manner and acceptance of payments in full and final settlement preclude further claims.
Escalation of contract rates is permissible when delays are not due to the contractor's fault, allowing for additional payment for work done after significant delays.
The appellate jurisdiction under section 37 is limited to the grounds prescribed under section 34. Courts cannot re-appreciate evidence or substitute their views for that of the arbitrator, provided ....
Point of Law : None of the objections as raised, fell within the purview of Section 34 of the Act and therefore, the award impugned did not deserve any interference.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.