RAJEEV RANJAN PRASAD, J.
Misc. Appeal No.651 of 2021
(5.4.2023)
National Highway Authority
of India ... Appellant
vs.
Sri Vijay Kumar Singh & Ors. ... Respondents
Arbitration and Conciliation Act 1996 – Sections 34 and 37 – National Highways Act, 1956 – Section 3G(5) – Appeal against arbitral award – Dispute over quantum of compensation for land acquired – Under sub-section (3) of Section 34 limitation starts running from date of delivery of Award – It does not require filing of a certified copy of Arbitral Award with application under Section 34 of Act of 1996 – When application under Section 34 was presented, it was well within limitation – It was same and one court which had permitted applicant/appellant to withdraw first case and to refile the same as Civil Miscellaneous Case – It was only a case of change of title /nomenclature on the petition – In facts of present case principles of Section 14 of Limitation Act would come to rescue of appellant – Arbitrator has simply recorded his finding that land is in nature of a commercial land – Thereafter, he has remitted record to competent authority to proceed further – This is not in consonance with scheme of Arbitration under Section 3G of Act of 1956 – Such order cannot be conferred with statutory flavour of an Award – Award is liable to be set-aside – Matter remitted to Arbitrator to conduct Arbitration in accordance with procedures provided under Act of 1996 and pass an award in accordance with law – Appeal allowed. (Paras 30, 40, 45, 48 and 49)
Rajeev Ranjan Prasad, J. – The present Miscellaneous Appeal has been filed under Section 37 of the Arbitration and Conciliation Act 1996 (hereinafter referred to as the ‘Act of 1996’) for the following reliefs: –
“1. That the present Misc. Appeal is being filed for setting aside the judgment dated 02.07.2021 passed by the learned Additional District Judge VIII, Aurangabad in Civil Misc. Application Case No. 79 of 2018 / 02 of 2021, whereby and where under the order dated 14.02.2017 in L.A Case No. 102/2016-17 passed by the Respondent No. 2 (Arbitrator-cum-Additional Collector, Aurangabad) (Annexure-4) has been up-held and the original award dt-30.11.2015 in L.A Case No. 58 (IX) of 2012-13 passed by the Respondent No.-3 (Competent Authority – Cum-CDLR, Aurangabad) (Annexue 3) has been set aside.
(ii) For setting aside the order dated 14.02.2017 in L.A Case No. 102/2016-17 passed by the Respondent no.-2 (Arbitrator-Cum-Additional Collector, Aurangabad) (Annexure-4) by which the original award dt-20-11- 2015 has been directed to be modified in terms of the observations made therein.
(iii) For setting aside the Revised award dt-22.07.2021 passed by the Respondent no.-3 in pursuance of the order dt-02-07-2021 (Annexure-7) . As a result the amount of compensation has been increased from Rs. 88,77,420/- in terms of original award to Rs. 13,88,57,762/- according to the revised award for the same plot of land. This increase is more than 1500% only due to change in classification of land from agricultural to commercial.”
Brief Facts of the Case
2. The National Highways Authority of India (hereinafter referred to as the ‘NHAI’) was entrusted with the work of widening/six laning work of NH-2 (Aurangabad-Chordaha Section) in the district of Aurangabad. In connection with this work, an acquisition proceeding in respect of a piece of plot bearing no. 1461 khata No. 171 measuring area 0.3887 hectare in Village Madanpur Anchal-Madanpur, District- Aurangabad (Bihar) owned and possessed by the respondent no. 1 was initiated in accordance with the provisions of National Highways Act, 1956 (hereinafter referred to as the ‘Act of 1956’). A Gazette notification dated 14.01.2013 under Section 3A of the Act of 1956 followed by a notification dated 06.01.2004 under Section 3D of the same Act was issued in which the land in question was classified as agricultural land on the basis of actual land usage as on 14.01.2013.
3. The District Level Committee entrusted with the work of classification of the nature of the land conducted site verification of the land and recommended the nature of land as agricultural land. Based on the said recommendation, the respondent no. 3 who is the Competent Authority-cum-DCLR, Aurangabad determined the compensation and communicated the amount payable to the Project Director, NHAI, Dhanbad vide his letter No. 647 dated 30.11.2015 (Annexure-3 to the Memo of Appeal). In respect of the land in question, in L.A. Case No. 58(IX)/2012-13 the competent authority found the respondent no. 1 entitled for Rs.88,77,420/-.
Challenge to the compensation determined by the competent authoirty.
4. Aggrieved by and dissatisfied with the compensation determined by the respondent no. 3, the land owner-respondent no. 1 filed an application under Section 3G(5) of the Act of 1956 before the Arbitrator (respondent no. 2). On behalf of the land owner, it was contended that on the land in question weekly cattle fair is being held for last 70 years. The land is registered in the name of the mother of respondent no. 1 and she had been paying tax to the Market Committee. It was contended that the land under acquisition is totally commercial and compensation should be determined accordingly. The land owner assailed the compensation determined by the competent authority. From the arbitration award dated 14.02.2017 as contained in Annexure ‘4’ to the memo of appeal, it appears that the Additional Collector, Aurangabad who was acting as the Arbitrator went for ins
Consolidated Engineering Enterprises vs. Principal Secretary, Irrigation Department
Associate Builders vs. Delhi Development Authority
M.P. Steel Corporation vs. Commissioner of Central Excise
Simplex Infrastructure Ltd. vs. Union of India
Oriental Insurance Company Ltd. vs. Tejparas Associates and Exports Pvt. Ltd.
Union of India vs. West Coast Paper Mills Ltd.
Project Director NHAI vs. M. Hakeem
State of Karnataka vs. Shankar Textile Mills
Point of Law : Once the time-limit or extended time-limit for challenging the arbitral award expires, the period for enforcing the award under Section 36 of the Arbitration Act commences.
The court established that an arbitral award can be set aside if it contravenes the principles of natural justice and public policy, particularly when crucial evidence is introduced after the conclus....
The nature and status of the land on the date of notification must be considered in determining compensation for land acquired under the NHAI Act, 1956, and settled legal principles must be applied i....
The court affirmed that judicial intervention in arbitral awards is limited to grounds of public policy or patent illegality, emphasizing respect for the Arbitrator's findings.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.