SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2024 Supreme(Pat) 624

IN THE HIGH COURT OF JUDICATURE AT PATNA
K. VINOD CHANDRAN, CJ., PARTHA SARTHY, J.
M/s Astitva Advertisement Private Limited, through its Director Om Prakash Tiwari, S/o. Muneshwar Tiwari - Petitioner
Versus
The Bihar Urban Infrastructure Development Corporation Ltd., through its Managing Director and Ors. - Respondents
Civil Writ Jurisdiction Case No.404 of 2024
Decided On : 10-07-2024

Advocates Appeared:
For the Petitioner: Mr. Ashhar Mustafa, Adv., Mr. Ranjan Kumar Srivastava, Adv.
For the Respondents: Mr. Lalit Kishore, Sr. Adv., Mr. Rabindra Kumar Priyadarshi, Adv., Mr. Kanishka Shankar, Adv.

The court ruled that a contractor cannot claim an extension of a contract as a matter of right after its expiration, and disputes must be resolved through arbitration.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Clause-1.2 and Clause-12.3 - Contract extension - The petitioner challenged the issuance of a fresh Notice Inviting Tender (NIT) after the expiration of the contract period, claiming entitlement to an extension due to pandemic-related delays. The court found no obligation for the respondent to extend the contract and stated that any claims regarding the contract's operation during the pandemic must be pursued in arbitration. (Paras 6, 8, 11)

(B) Contractual Obligations - The court emphasized that the parties must continue to perform their obligations under the agreement only during its validity, and the petitioner could not claim an extension as a matter of right. (Paras 10, 12)

Facts of the case:
The petitioner, a contractor, challenged the NIT issued by BUIDCO after the expiration of their contract, which was initially set for 2017-2022 but extended until 31.12.2023 due to pandemic-related issues. (Paras 1-2)

Findings of Court:
The court found no grounds to interfere with the fresh NIT and stated that the petitioner’s claims regarding contract extension must be resolved in arbitration. (Paras 11-12)

Issues: The main issues were whether the petitioner was entitled to an extension of the contract and the applicability of the arbitration clause regarding claims for non-operation during the pandemic. (Paras 6, 8)

Ratio Decidendi: The court ruled that the petitioner could not claim an extension as a matter of right and that any claims regarding the contract's operation during the pandemic must be pursued in arbitration. (Paras 10-12)

Result: Writ petition dismissed.

JUDGMENT :

(K. Vinod Chandran, CJ.)

The petitioner, a contractor who had been entrusted with a work, challenge the Notice Inviting Tender (NIT) issued by the respondent authority, the Bihar Urban Infrastructure Development Corporation Ltd., (‘BUIDCO’ for short) to award the same work but for a different period.

2. The period of contract of the petitioner is over, however, the petitioner’s challenge is based on the recommendation granted by the Bid Evaluation Committee to allow extension of the petitioner’s contract for two years since its operation remained suspended during the pandemic period. It is also an admitted position that the petitioner has invoked the arbitration clause in the agreement.

3. We have heard Mr. Ashar Mustafa learned Counsel appearing on behalf of the petitioner and Mr. Lalit Kishore, learned Senior Counsel appearing on behalf of the respondent- BUIDCO.

4. The petitioner was granted the contract as per Annexure-P/2 for the period 2017-22. The petitioner, according to the submission made, has also paid the entire premium amounts due as per the contract; despite the petitioner having not been able to operate it during the pandemic period. The work awarded to the petitioner for the five-year period was the operation and maintenance of bus queue shelters and displaying advertisements on such shelters within Patna. It is pointed out from the agreement that the authorization period can be extended as per Clause-1.2 for Force Majeure situations and the dispute resolution procedure as delineated in Clause-12.3 requires that the performance of the contract not be hampered when the dispute resolution process is pending. The learned Counsel for the petitioner has also produced a translation of the documents produced along with the counter affidavit, across the bar.

5. Annexure-R/1 indicates that the contract was awarded to the petitioner and one another agency and an agreement was signed on 14.02.2017. The period of the contract expired on 14.02.2022 and the Executive Engineer, Bus Queue Shelter, Patna based on Clause-1.2(b) of the agreement recommended extension of agreement for five years till 14.02.2027 on the condition of 5% increase in the amount of the present premium. There were complaints received by the BUIDCO from Patna Municipal Corporation regarding the advertisements displayed having not complied with the stipulations in the tender and also having been carried out in flagrant violation of the terms and conditions, resulting in huge loss of revenue.

6. Be that as it may, the Technical Bid Evaluation Committee had recommended the award of work from 15.02.2022 to 14.02.2024. The final decision however was to extend the period from 15.02.2022 to 31.12.2023 at a penalty of 2% on the amount of premium. The extended period also has expired and we are of the opinion that there is no cause to challenge the issuance of fresh NIT; which is the prerogative of the respondent-BUIDCO and the Patna Municipal Corporation. Whatever claim the petitioner has on the ground of the petitioner having been prevented from running the contract during the period of pandemic has to be urged in the arbitration proceeding; which, in the circumstance of the newly floated NIT cannot be for extension of the period of contract.

7. We have looked at the specific provisions regarding the extension as provided in Clause-1.2 of the agreement. Clause-1.2 has the nominal heading of authorization period and sub-clause (b) speaks of extension on mutual agreement at such terms and conditions as may be mutually agreed. It is also stipulated by Clause-1.2(c) that authorization period could be extended due to Force Majeure conditions. The words employed does not impose an obligation on the Awarder to extend the period and admittedly there is neither mutual agreement nor did the Awarder deem it appropriate to extend the period beyond that extended already on the condition of 2% penalty on premium.

8. The petitioner cannot as a matter of right claim extensio

    Click Here to Read the rest of this document
    1
    2
    3
    4
    5
    6
    7
    8
    9
    10
    11
    SupremeToday Portrait Ad
    supreme today icon
    logo-black

    An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

    Please visit our Training & Support
    Center or Contact Us for assistance

    qr

    Scan Me!

    India’s Legal research and Law Firm App, Download now!

    For Daily Legal Updates, Join us on :

    whatsapp-icon Back to top