IN THE HIGH COURT AT CALCUTTA
SHEKHAR B. SARAF, J.
State of West Bengal and Others – Petitioners
Versus
Rajpath Contractors and Engineers Limited – Respondent
A.P. No. 737 of 2022
Decided On : 04-05-2023
Constitution of India,1950 - Article 133(1) read with Article 134A(a) - Arbitration and Conciliation Act - Section 34 and 37 - General Clauses Act, 1897 - Sections 3(35) and 9 - Limitation Act, 1963 0- Sections 12, 34(3), 33, 2(j) , and 4 - Award debtor raising several claims - Award debtor to pay a sum - Letter to the award debtor raising several claims award holder invoked arbitration clause - Extended to the award debtor - Three months period expired that is day this Court reopened - Learned Advocate General contended that as instant application – Held, Court beyond what has been prescribed in Act - Construction Company (supra) was the entire extendable period not available to the party who failed to file Section 34 application within prescribed period. case is unique in the sense that the entire thirty days, inclusive of the first day and thirtieth day - AP 737/2022 is dismissed
JUDGMENT :
SHEKHAR B. SARAF, J.
1. The instant application under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as ‘the Act’) by the petitioners, State of West Bengal through the Secretary, Public Works Department, Kolkata (hereinafter referred to as the ‘award debtor’) arises out of an arbitral award dated June 30, 2022 passed by Shri Bibek Raha, Sole Arbitrator. The respondent in the instant application is Rajpath Contractors and Engineers Ltd. (hereinafter referred to as the ‘award holder’).
2. The award holder has raised a challenge on the grounds of maintainability wherein it has argued that the instant application has been filed beyond the period of limitation as provided under the Act. The said challenge was vehemently opposed by the petitioners, and hence, in this judgment, I have only dealt with the point of maintainability of the Section 34 application.
Facts
3. I have mapped out the factual matrix of the instant lis below:
(b) On September 11, 2009, the award holder sent a letter to the award debtor raising several claims. By another letter dated October 15, 2009, the award holder invoked the arbitration clause. In terms of the arbitration clause incorporated in the tender conditions, arbitration was first referred to Shri Santanu Basu Rai Choudhury, Chief Engineer, Public Works (Roads) Department. Being unable to undertake the reference himself, Shri Santanu Basu Rai Choudhury appointed Shri Bibek Raha as the Sole Arbitrator. The said arbitrator entered reference on November 19, 2009.
(c) An award was passed on June 30, 2022 directing the award debtor to pay a sum of INR 2,11,67,054.00 (Two Crores Eleven Lakhs Sixty Seven Thousand Fifty Four Rupees Only) including INR 5 Lakhs costs along with interest at 15% per annum after expiry of 90 days from the date of award till the date of payment. The copy of the arbitral award was received by the parties on June 30, 2022 itself.
(d) On October 31, 2022, the award debtor filed the instant application praying for setting aside of the said arbitral award.
Contentions
4. Mr. S.N. Mookherjee, learned Advocate General, appearing on behalf of the award debtor has made following submissions on the point of maintainability:
(b) He argued that as the last day of filing the instant application fell on October 01, 2022 that is the day the Court was closed, the benefit of Section 4 of the Limitation Act, 1963, read with Section 12 of the Limitation Act, 1963, must be extended to the award debtor. Consequently, the three months period expired on October 31, 2022 that is the day this Court reopened after the Puja Vacations. The learned Advocate General contended that as the instant application was filed on October 31, 2022, the same falls within the prescribed period that is three months as provided under Section 34(3) of the Act.
(c) Not forgoing the above, the learned Advocate General proceeded to further argue that proviso to Section 34(3) of the Act shall become completely otiose if the Court holds that the prescribed period for filing the instant Section 34 challenge expir
The limitation period for challenging an arbitral award under Section 34(3) of the Arbitration and Conciliation Act, 1996 is strict and non-extendable, emphasizing the need for timely recourse to mai....
The court emphasized the peremptory language of section 34 of the Arbitration and Conciliation Act, 1996, and the requirement for sufficient cause to condone any delay in filing the application.
The period for challenging an arbitral award under Section 34 of the Arbitration and Conciliation Act cannot be extended beyond the prescribed period, as the Act is a self-contained special law and t....
The interpretation of 'three months' in Section 34(3) of the Arbitration and Conciliation Act, 1996, is clarified to mean three calendar months, not strictly 90 days.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.