IN THE HIGH COURT AT CALCUTTA
PRAKASH SHRIVASTAVA, RAJARSHI BHARADWAJ, JJ.
Sri Ramanand Jha and Others - Appellants
Versus
Union of India and Others - Respondents
MAT No. 960 of 2022 With CAN 1 of 2022, CAN 2 of 2022
Decided On : 28-09-2022
Partnership deed - Tender - Bid - Transportation of bulk petroleum products - Held, appellants had failed to submit requisite registration certificate with annexure mentioning names of all partners of partnership firm, in terms of aforesaid condition the appellants were given opportunity to submit same during technical evaluation and on his failure to submit same, bid has been rejected - Record further reflects that requisite certificate from Registrar of Firms was obtained by appellants only and undisputedly it was not submitted to respondents - Court find no error in the order of learned Single Judge in disposing of the petition and no case for interference is made out - Appeal is accordingly dismissed.
JUDGMENT :
Prakash Shrivastava, J.
1. This intra-court appeal is at the instance of the writ petitioner aggrieved with the order of the learned Single Judge dated 02.05.2022 disposing of WPA 19540 of 2021 on reaching to the conclusion that no relief could be granted to the petitioner in the petition.
2. The appellants had submitted bid in response to the e-tender floated by the respondents for transportation of bulk petroleum products from Jharsuguda Terminal. The bid of the appellants was rejected, hence a prayer was made in the petition to set aside the order of rejection.
3. Learned Single Judge while passing the order under challenge has noted that the appellants were informed about the deficiency in the bid particularly in the context of supply of amended partnership deed and Form A and thereafter the bid was rejected on 14th of September, 2021, after giving ample opportunity to submit documents. Hence, learned Single Judge found that there was sufficient compliance of the requirement of providing opportunity to the appellants to rectify the bid.
4. Submission of the learned Counsel for the appellants is that the appellants had submitted the memorandum Annexure-P1 page 30 of the paper book showing registration of partnership firm, therefore, there was sufficient compliance of the requisite clause and that in the bid they had disclosed the registration number and the names of the partners, therefore, rejection of the bid cannot be sustained.
5. As against this, learned Counsel for the respondents has submitted that the appellants had failed to submit the registration certificate as required by the terms of the NIT, therefore, after giving an opportunity to the appellants, the bid has been cancelled.
6. We have heard learned Counsel for the parties and perused the record.
7. The respondents had sent to the appellants technical-commercial query dated 14th of September, 2021 by giving an opportunity to the appellants to response to the same and thereafter on 2nd of November, 2021 at the stage of technical evaluation the appellants were informed that the bid was rejected by the duly constituted committee and the reasons for rejection were also conveyed to the appellants, a perusal of which discloses that the appellants had failed to produce Form-A (Annexure) mentioning names of the partners of the partnership firm and the appellants were technically disqualified.
8. Clause 9 of terms and conditions of NIT requires the tenderer to submit copy of the registration certificate from the Registrar of Firms enclosing all annexures wherein names of all the partners of the partnership firm are mentioned. Condition 9 of the NIT reads under :
9. The record reveals that the appellants had failed to submit the requisite registration certificate with annexure mentioning the names of all the partners of the partnership firm, therefore, in terms of the aforesaid condition the appellants were given opportunity to submit the same during technical evaluation and on his failure to submit the same, the bid has been rejected. The record further reflects that the requisite certificate from the Registrar of Firms was obtained by the appellants only on 02.12.2021 and undisputedly it was not submitted to the respondents. The memorandum
Silppi Constructions Contractors vs. Union of India and Another
Point of law : Under the scope of judicial review, the High Court could not ordinarily interfere with the judgment of the expert consultant on the issues of technical qualifications of a bidder when ....
The main legal point established in the judgment is that the rejection of tenders must be based on valid legal grounds and cannot be arbitrary or unfair. The court emphasized the importance of legal ....
Tender rejection valid if bidder unregistered at evaluation due to unverifiable certificates.
Point of law: Supreme Court held that any contract of public service should not be interfered with lightly and in any case, there should not be any interim order derailing entire process of services ....
Bidders must provide complete and accurate documentation as required by tender specifications, and courts should exercise restraint in reviewing decisions made by tender authorities unless there is c....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.