SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2024 Supreme(Cal) 394

IN THE HIGH COURT AT CALCUTTA
Sabyasachi Bhattacharyya, J.
Learning Spiral Private Limited – Petitioner
Versus
Jharkhand Combined Entrance Competitive Examination Board & Ors. – Respondents
WPA NO. 19280 of 2023
Decided On : 19-03-2024

Advocates:
Advocate Appeared:
For the petitioner: Mr. Prem Prakash, Mr. Sailendra Jain, Mr. Farhan Ghaffar
For the Respondent: Ms. Amrita Pandey, Mr. Surendra Kumar

The penalty of blacklisting must be proportionate to the offense and should not be imposed arbitrarily.

Headnote:

Blacklisting - Contractual Dispute - Clause 10, Clause 18, Arbitrariness, Natural Justice - [Clause 10, Clause 18, Article 14 of the Constitution of India, Uttar Pradesh Power Transmission Corporation Ltd., Unitech Limited, Blue Dreamz Advertising Pvt. Ltd., Birla Gtm-Enterpose Ltd., Hariom Project Private Limited, Lt. Governor, Delhi and others Vs. HC Narinder Singh, Mohinder Singh Gill & Anr. Vs. The Chief Election Commissioner, New Delhi & Ors., Sambasiva Milk Transport Vs. State of Andhra Pradesh] - The court discussed the applicability of Clause 10 and Clause 18 of the agreement, arbitrariness, and failure of natural justice principles in the decision to blacklist the petitioner. It also referred to various judgments to support the argument that alternative remedy is not an absolute bar, and the penalty of blacklisting must be proportionate to the offense.

Fact of the Case:

The petitioner challenged an order of blacklisting issued by the respondent-Authorities, arguing that the contract was never terminated, and the blacklisting was disproportionate to the alleged minor delay.

Finding of the Court:

The court found that the blacklisting decision was arbitrary, disproportionate, and lacked consideration of the petitioner's explanations for the delay. It also noted the absence of a blacklisting clause in the current agreement and the element of malice and arbitrariness in the respondent's actions.

Issues: Contractual dispute, arbitrariness, proportionality of penalty, failure of natural justice principles.

Ratio Decidendi: The court held that the blacklisting decision was arbitrary, disproportionate, and lacked consideration of the petitioner's explanations for the delay. It also noted the absence of a blacklisting clause in the current agreement and the element of malice and arbitrariness in the respondent's actions.

Final Decision: WPA No. 19280 of 2023 is allowed on contest, thereby setting aside the order of blacklisting the petitioner dated June 24, 2024. There will be no order as to costs.

JUDGMENT :

Sabyasachi Bhattacharyya, J.

1. The petitioner has challenged an order of blacklisting issued by the respondent-Authorities. Learned counsel for the petitioner argues that throughout the entire period during which the petitioner did the concerned work for the respondents, the contract of the petitioner was never terminated by the respondent-Authorities. During the pendency of the writ petition, a substantial portion of the dues of the petitioner has also been cleared. Hence, there was no occasion for the respondent-Authorities to issue the impugned order of blacklisting.

2. It is next argued that Clause 10 of the agreement between the parties contemplates larger penalty than damages to be imposed only in cases where the delay occasioned for performing the work is more than five weeks. The delay occasioned by the petitioner being much less, the larger penalty of blacklisting could not have been imposed.

3. Clause 18 of the agreement (Memorandum of Understanding) clearly stipulates that the present agreement sets forth the entire understanding and agreement of the parties as to the subject matter of the agreement and supersedes all oral and written agreement or understanding between the parties regarding the subject matter. The present contract does not contain any clause of blacklisting, as opposed to the other previous agreements. Thus, by specific exclusion, the provision of blacklisting has been removed. Accordingly, the order of blacklisting is also challenged on such ground.

4. Learned counsel next contends that the elaborate reply given by the petitioner to the Show-Cause Notice, citing reasons for the delay, which were not attributable to the petitioner, was overlooked by the respondents and not adverted to in the order of blacklisting. Thus, the said order is vitiated on such ground as well.

5. It is argued that the blacklisting decision was taken only when the petitioner asked for its dues, much after the petitioner completed the work under the contract. Hence, an element of arbitrariness and malice cannot be ruled out as well.

6. Lastly, it is contended that the penalty of blacklisting is grossly disproportionate with the allegation of minor delay on the part of the petitioner.

7. Learned counsel for the petitioner cites the judgment of the Supreme Court in Uttar Pradesh Power Transmission Corporation Ltd. and Anr. Vs. CG Power and Industrial Solutions Limited and Anr., reported at (2021) 6 SCC 15, where it was held that alternative remedy is not an absolute bar to the writ jurisdiction, which can be invoked for enforcement of a fundamental right or failure of principle of natural justice, etc.

8. Learned counsel appearing for the petitioner next cites another judgment of the Supreme Court in the matter of Unitech Limited & Ors. Vs. Telangana State Industrial Infrastructure Corporation (TSIIC) & Ors., reported at LL 2021 SC 92, where the Supreme Court observed that even if the dispute is contractual and there is an arbitration clause, it can be subject to the writ jurisdiction when there is arbitrary exercise of power or misuse of authority on the part of State instrumentalities.

9. Learned counsel also cites Mohinder Singh Gill & Anr. Vs. The Chief Election Commissioner, New Delhi & Ors., reported at AIR 1978 SC 851 and a judgment of a Learned Single Judge of the Andhra Pradesh High Court in Sambasiva Milk Transport Vs. State of Andhra Pradesh, reported at AIR 2022 AP 110 in support of the proposition that reasons for an order cannot be subsequently furnished by way of affidavit or otherwise to justify an order which did not contain such reasons.

10. Learned counsel next relies on Blue Dreamz Advertising Pvt. Ltd. & Anr. Vs. The Kolkata Municipal Corporation & Ors., in W.P. No. 6616 (W) of 2016, an unreported judgment of a Co-ordinate Bench of this Court, where it was held that blacklisting is a civil consequence and rules of natural justice have to be scrupulously followed, giving proper reasons which suggest that p

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top