IN THE HIGH COURT AT CALCUTTA
Debangsu Basak, Partha Sarathi Sen, JJ.
West Bengal State Fishermen’s Co-Operative Federation Limited (Benfish) - Appellant
Vs.
Lords Bluetech Co. Pvt. Ltd & Ors. - Respondent
FMA 999 of 2021 With IA No: CAN 1 of 2021, CAN 2 of 2021
Decided On : 12-07-2024
Contract - Termination - Clauses 20, 22, 23 - The court interpreted the contractual obligations and the right to terminate the agreement based on non-compliance, emphasizing the necessity of prior notice and the essence of time in contracts.
Fact of the Case:
The appellant terminated an agreement with the respondent for failing to comply with payment terms and other obligations. The respondent challenged this termination in a writ petition, which was initially upheld by a Single Bench.
Finding of the Court:
The court found that the appellant had provided adequate notice for rectification of breaches and that the respondent's failure to comply justified the termination of the agreement without further notice.
Issues: Whether the termination of the agreement was justified based on the respondent's failure to meet contractual obligations and whether the appellant acted arbitrarily.
Ratio Decidendi: The court held that the appellant's actions were not arbitrary as they followed the contractual provisions allowing termination for non-compliance, particularly under Clause 22.
Result: The appeal was allowed, and the Single Bench's order was set aside.
JUDGMENT :
Partha Sarathi Sen, J.
1. Challenge in this appeal is the judgement dated 22.12.2020 as passed by the learned Single Bench in WPA 9535 of 2020. By the impugned judgement learned Single Bench allowed the writ petition and thus quashed the decision of the respondent no.2/authority therein to terminate the agreement dated 17.12.2017 between the writ petitioner and the respondent no.2 therein and the notice dated 05.1.2020. The respondent no.2/authority of the said writ petition felt aggrieved and thus preferred the instant appeal.
2. For effective disposal of the instant appeal, the facts leading to initiation of the writ petition is required to be dealt with in a nutshell and those are as follows:-
ii. The agreement was for sale of ‘21se Annapurna’ lunch scheme at the rate of Rs.21/- per plate by using the brand name of ‘Benfish’ of the appellant/authority. The said agreement contains several terms and conditions.
iii. The execution of the deed of agreement between the parties is however not disputed.
iv. According to the appellant/authority the respondent no.1/writ petitioner violated certain terms and conditions of the said agreement and thus a letter dated 26.03.2019 was issued by the appellant/authority.
v. The said letter was duly replied by the respondent no.1/writ petitioner under cover of its reply letter dated 01.04.2019.
vi. Since according to the appellant/authority the grievance as raised under the cover of letter dated 26.03.2019 was not met with by the respondent no.1/writ petitioner, the appellant/authority by its letter dated 30.07.2019 requested the writ petitioner to comply with the terms and conditions of the said agreement in letter and spirit.
vii. According to the appellant/authority the respondent no.1/writ petitioner failed to discharge its obligation in terms of Clauses 6,7,8,22 and 23 of the said agreement and accordingly by issuing a letter dated 05.11.2020 the appellant/authority cancelled and terminated the aforesaid agreement which gave rise to the aforesaid writ petition.
3. In course of his submission learned advocate for the appellant/authority at the very outset draws out attention to the agreement dated 17.02.2017 between the appellant /authority and the respondent no.1/writ petitioner. Attention of ours is also drawn to the various clauses of the terms and conditions of the said agreement more specifically Clauses 6,7,8,13,20 and 22. Drawing attention to the notice dated 26.03.2019, the reply of the respondent no.1/writ petitioner dated 01.04.2019 and the second notice dated 30.07.2019 as issued by the appellant /authority it is submitted on behalf of the appellant that on conjoint perusal of the aforesaid two notices and the reply it would reveal that the respondent no.1/writ petitioner had failed and neglected to deposit monthly fixed and floating amount of sale of product on a quarterly basis within a fortnight on completion of each quarter to the appellant/authority and that apart the respondent/writ petitioner was found to be defaulted in paying the security deposit and further they were found to be using an excess area of the premises of the appellant/authority which was not allotted to them.
4. It is submitted further on behalf of the appellant/authority that from the letter dated 10.04.2019 it would reveal further that the respondent no.1/writ petitioner had not denied any of the allegations of the writ petitioner and on the contrary the respondent no.1/writ petitioner insisted the appellant/authority to extend the time to deposit the contractual amount.
5. Drawing our attention to the letter dated 30.07.2019 it is submitted further that from the said letter it would reveal that despite several request made by the appellant/authority the respondent no.1/writ petitioner paid no heed to the request of the appellant/authority though their outstanding dues reached to th
The court established that a party can terminate a contract without notice if the other party fails to comply with payment obligations over consecutive periods as stipulated in the agreement.
The court emphasized the importance of adhering to contractual procedures and the validity of penalties for non-performance, reinforcing the authority's right to terminate contracts under specified c....
Writ petitions in contractual disputes are generally not maintainable if they involve disputed questions of fact.
The court affirmed that principles of natural justice do not apply to non-statutory, purely contractual disputes where parties must adhere to the terms of their contract.
A writ petition can be dismissed for lack of maintainability if an arbitration clause exists; however, constitutional violations may warrant judicial review.
The main legal point established in the judgment is the interpretation and application of lease and sub-lease agreements, particularly Clause 10 and Clause 23, and the court's assertion of jurisdicti....
The main legal point established in the judgment is the importance of abiding by the dispute resolution mechanism provided in the Agreement for resolving disputes arising from the contract. The Court....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.