SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2022 Supreme(P&H) 2243

IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH
Anil Kshetarpal, J.
Apex Buildwell Private Limited – Appellant
Versus
Sachin Kumar & Anr. – Respondents
Rera-Appl-58,59,60,61,62,63,64,65,66,67,68,39 of 2021 (O&M)
Decided On : 26-04-2022

Advocates appeared:
Mr. Akshay Bhan, Sr. Advocate with Mr. Alok Mittal, Advocate, Mr. Rohan Gupta, Advocate, Mr. Arun Gupta, Advocate, for the Appellant; Mr. Gaurav Bhardwaj, Advocate Ms. Ayushi Sharma, Advocate, Mr. Mayank Gupta, Advocate, for the Respondent.

The Real Estate Regulation and Development Act applies to ongoing projects and governs existing agreements. Prescribed interest rates do not override the Act's provisions.

Headnote:

Real Estate Regulation and Development Act - Delay in Project Completion - Sections 58, 100 of the 2016 Act - The court disposed of appeals challenging orders passed by HRERA and Tribunal. The issues included delay in project completion, applicability of the Act to existing agreements, and authority to grant interest. The court found the promoter negligent and in willful default, and held that the Act applies to ongoing projects and governs existing agreements. The court also ruled that prescribed interest rates do not override the Act's provisions.

Fact of the Case:

The appeals involved challenges to orders passed by HRERA and Tribunal. The issues included delay in project completion, applicability of the Act to existing agreements, and authority to grant interest. The court found the promoter negligent and in willful default, and held that the Act applies to ongoing projects and governs existing agreements. The court also ruled that prescribed interest rates do not override the Act's provisions.

Finding of the Court:

The court found the promoter negligent and in willful default, and held that the Act applies to ongoing projects and governs existing agreements. The court also ruled that prescribed interest rates do not override the Act's provisions.

Issues: The delay in project completion, applicability of the Act to existing agreements, and authority to grant interest were the key issues in the case.

Ratio Decidendi: The court held that the Act applies to ongoing projects and governs existing agreements. It also ruled that prescribed interest rates do not override the Act's provisions.

Final Decision: The appeals were dismissed, and all pending miscellaneous applications were disposed of.

JUDGMENT

Anil Kshetarpal, J. - Through this judgment, various appeals filed under Section 58 of the Real Estate (Regulation and Development) Act, 2016 (hereinafter referred to as 'the 2016 Act') shall stand disposed of, wherein the promoter/developer has challenged the various identical orders passed by Haryana Real Estate Regulatory Authority (hereinafter referred to 'HRERA'), which have been affirmed by the Haryana Real Estate Appellate Tribunal (hereinafter referred to as 'Tribunal'). In the background of the various judgments passed by the Supreme Court interpreting the provisions of the 2016 Act, the learned Senior counsel representing the appellant has restricted his arguments only on the following two issues:-

    i. The delay in completing the project cannot be imputed to the promoter particularly when there was a delay in renewal of licence for a period of more than three years.

    ii. The Authorities have wrongly ignored the contractual rate of interest on the delay in delivery of possession of the apartment beyond the contractual period.

    The learned Senior counsel has submitted that he intends to press question No.4, 6, 8 and 9, which are extracted as under:-

    '4. Whether the registration of the real estate project granted by the Ld. Authority thereby providing extended time to complete the project shall be applicable to the existing agreements which were executed between the promoter and the allottees prior to the coming into force of the Act 2016?

    6. Whether the project duly registered under the Act 2016 implies that the existing agreements and the sale transactions done prior to the coming into force of the Act 2016 shall be governed by the provisions of the Act 2016 and rules framed thereunder?

    8. Whether the Rules can over write the provisions of the Act thereby prescribing the fixed rate of interest to be granted to the allottees in all eventualities against the promoter, whether it being a case of refund or delay in delivery of possession?

    9. Whether the RERA Authorities have the requisite authority, power and competency to grant interest as per section 38 of the RERA Act, 2016 to the allottee for the delay in delivering the physical possession as permitted under the provision of Section 18 of the RERA Act, 2016?"

    2. It may be noted here that as per Section 48 of the 2016 Act, the appeal to the High Court is maintainable only on a substantial question of law as provided under Section 100 of Code of Civil Procedure, 1908. So for entertaining an appeal under Section 58 of the 2016 Act, the High Court is required to be satisfied that the case involves a substantial question of law which is a sine qua non.

      Section 58 of the 2016 Act is extracted as under:-

      '58. (1) Any person aggrieved by any decision or order of the Appellate Tribunal, may, file an appeal to the High Court, within a period of sixty days from the date of communication of the decision or order of the Appellate Tribunal, to him, on any one or more of the grounds specified in section 100 of the Code of Civil Procedure, 1908:

      Provided that the High Court may entertain the appeal after the expiry of the said period of sixty days, if it is satisfied that the appellant was prevented by sufficient cause from preferring the appeal in time.

      Explanation.-The expression "High Court" means the High Court of a State or Union territory where the real estate project is situated.

      (2) No appeal shall lie against any decision or order made by the Appellate Tribunal with the consent of the parties."

      3. Some facts are required to be noticed.

      4. The promoter/developer was granted the licence, to carry out the project under the name 'Affordable Housing Project', on 22.02.2012 which was valid upto 21.02.2016. The respondent in this appeal was allotted an apartment bearing No.343, 3rd Floor, Tower-Orchid in Group Housing namely 'Our Home', Sector 37, Gurugram, having a carpet area of 48 square mts. at a total sale price of Rs.16,00,000/-. The respondent (allottee) has already paid Rs.15,20,000/

                    Click Here to Read the rest of this document
                    1
                    2
                    3
                    4
                    5
                    6
                    7
                    8
                    9
                    10
                    11
                    SupremeToday Portrait Ad
                    supreme today icon
                    logo-black

                    An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

                    Please visit our Training & Support
                    Center or Contact Us for assistance

                    qr

                    Scan Me!

                    India’s Legal research and Law Firm App, Download now!

                    For Daily Legal Updates, Join us on :

                    whatsapp-icon Back to top