IN THE HIGH COURT OF ALLAHABAD
ALOK MATHUR, J.
Lucknow Development Authority Thru. Vice Chairman Lucknow – Appellant
Versus
Smt.Upasana Duggal – Respondents
Rera Appeal No.266 of 2019
Decided on : 30-11-2023
Delay in Possession - Real Estate Regulation & Development Act, 2016 - Section 18, Clause 2.4, Clause 11.1 - MCLR +1% per year, 15% per annum - Interest payable by promoter or allottee, retrospective operation of the Act
Fact of the Case:
The case involves a dispute over the delay in handing over possession of a flat in a real estate project. The petitioner had promised possession within 24 months, but due to construction delays, the possession was not provided. The respondent sought interest on the delay and filed a complaint before the Real Estate Regulatory Authority, Uttar Pradesh.
Finding of the Court:
The court found that the petitioner had delayed in handing over possession despite the agreement, and the allottee was entitled to interest for the delay as per Section 18 of the Real Estate Regulation & Development Act, 2016. The Appellate Tribunal modified the interest rate to 15% per annum, aligning with the rate charged by the petitioner for default in payment.
Issues: The key issues revolved around the delay in possession, entitlement to interest, and the retrospective operation of the Act of 2016. The court also considered the applicability of the interest rate prescribed in the brochure published by the petitioner.
Ratio Decidendi: The court held that the Act of 2016 operates retrospectively and the levy of interest for delay is compensatory in nature. The court also emphasized that the contractual terms do not override the retrospective applicability of the authority under the provisions of the Act.
Final Decision: The court dismissed the appeal, citing that the issues raised had already been determined and answered by the Supreme Court in a similar case, and no substantial question arose in the present appeal.
JUDGMENT :
Alok Mathur, J.
1. Heard Shri Ratnesh Chandra, learned counsel for the appellant as well as Shri Ashish Chaturvedi, learned counsel appearing on behalf of respondents.
2. The controversy in brief is with regard to the delay in handing over the possession of the flat which was sought to be constructed by the petitioner while developing apartments known as Smriti Apartments, Sector J Extension, Sitapur Raod Scheme, Jankipuram, Lucknow.
3. In the brochure published by the petitioner it was stated that the flats would be handed over within a period of 24 months as per clause 2.4 of the said brochure and as per clause 11.1 it was provided that in case possession is not given then the allottee shall be at liberty to seek refund of the entire money along with interest at the rate of 4% per annum.
4. It is stated that for certain reasons beyond the control of the petitioner construction activities could not commence and, hence, there was delay in completion of the said project. In the meanwhile the Real Estate Regulation & Development Act, 2016 came into operation and the said project was registered by the petitioner with the concerned authorities and further the date of delivery of possession was extended till 31.12.2019.
5. In light of the fact that the petitioner did not complete the project within the stipulated time, the respondent filed a complaint before the Real Estate Regulatory Authority, Uttar Pradesh seeking interest on the delay in completion of the said project as provided under Section 18 and also sought a direction to the petitioner for expediting the possession of the said flat.
6. In the application it was stated that in pursuance to the application made by the respondent he was allotted a flat no. D/1407/C which was valued at Rs.13,00000/-and by 13.12.2013 he had paid an amount of Rs.14,18,886/-. It was further stated by him that as per the registration booklet the possession was to be given within 24 months and, accordingly, he should have got possession by 01.10.2013 and till filing of the said application before authority, i.e., some time in 2018 the possession had not been given to the respondent/allottee and hence prayed for quahing the order dated 26.2.2019 passed by Chairman, Real Estate Appellate Tribubnal, U.P., Lucknow in Appeal No.87 of 2018 (Smt. Upasand Duggal Vs. Lucknow Development Authority).
7. The petitioner had put in appearance before the Authority and objected to the claim made by the respondent/allottee. The petitioner had admitted that the possession was to be handed over by 01.10.2013 but due to certain dispute and delay by the construction agency who was given the contract of constructing the said flats there was delay in completion of the said project. It was further stated that there was difficulty and delay in obtaining the possession of the said land due to farmers’ agitation and it is only when settlement was arrived at, the possession was given to the petitioners and, accordingly, submitted that the delay was beyond the control of the petitioners and, consequently, prayed that the interest as claimed by the petitioner does not deserve to be granted in peculiar facts of the present case.
8. Another objection made with regard to the claim of the allottee was that as per the brochure he was entitled only for refund of the entire amount with interest @ 4% and as per the settled terms and conditions there was no provision for grant of interest on the delay in completion of the said project and, consequently, stated that the prayer made by the allottee before the Authority could not be admitted/allowed.
9. Considering the arguments the Real Estate Regulatory Authority was of the considered view that the petitioner had delayed in handing over the possession of the said flat despite there being agreement in this regard and once there is a breach of the said agreement the allottee was entitled for interest for the delay in completion of the said project, and, accordingly, awarded interest @ MC
Abati Bezbaruah v. Director General
Alok Shanker Pandey v.UOI-(2007) 3 SCC 545(para 9)
Shanti Conductors (P) Ltd. v. Assam SEB
The main legal point established is that the Real Estate Regulation & Development Act, 2016 operates retrospectively, and the levy of interest for delay is compensatory in nature, aligning with the r....
The Real Estate Regulation and Development Act applies to ongoing projects and governs existing agreements. Prescribed interest rates do not override the Act's provisions.
Private settlements cannot override statutory obligations established by the Real Estate (Regulation and Development) Act, 2016; agreements executed under duress or unfair terms are void.
The main legal point established in the judgment is the liability of the promoter to pay interest to the flat purchasers under the Real Estate (Regulation and Development) Act, 2016 (RERA) and the ef....
The judgment established the unconditional right of the allottee to seek refund and the application of promissory estoppel in enforcing promises made by the promoter.
The RERA Act applies to ongoing real estate projects, and the Act's provisions protect the rights of stakeholders, including home buyers and promoters.
The 'as is where is' clause in the brochure was deemed unconscionable and void under Section 23 of the Indian Contract Act, 1872. The allottee is entitled to interest for every month of delay in poss....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.