High Court Of Delhi
PUNJ LLOYD INSULATIONS LTD - Appellant
Versus
STATE BANK OF INDIA - Respondent
Decided On : 04/27/2006
Bank Guarantee - Contract Dispute - Companies Act, 1956 - [Section 1, Section 2, Section 3, Section 4, Section 5] - The court discussed the terms of the bank guarantee and its unconditional nature, the invocation of the bank guarantee, and the exceptions for seeking an order of injunction for encashment of bank guarantee. The court referred to various judgments and established that the bank guarantee is an independent contract enforceable on its own terms, and the obligation of the bank to pay would be subject to limited exceptional circumstances such as fraud, irretrievable injustice, or special equities.
Fact of the Case:
PUNJ Lloyd Insulations Limited filed a suit for injunction praying for grant of a decree for permanent injunction in favor of the plaintiff and against defendant no. 2, restraining him from encashing the bank guarantee dated 8. 11. 99. The plaintiff claimed to have performed the contract to the satisfaction of the concerned defendant and completed the entire work. The defendant invoked the bank guarantee alleging that the plaintiff had failed to fulfill the terms of the purchase order.
Finding of the Court:
The trial court dismissed the suit of the plaintiff, relying upon the terms of the bank guarantee and various judgments, and found that the case of the plaintiff was not covered under any of the exceptions provided for seeking an order of injunction for encashment of bank guarantee.
Issues: The main issue was whether the plaintiff's suit for injunction against the encashment of the bank guarantee was justified, and whether the plaintiff had performed the contract to the satisfaction of the concerned defendant.
Ratio Decidendi: The court established that the bank guarantee is an independent contract enforceable on its own terms, and the obligation of the bank to pay would be subject to limited exceptional circumstances such as fraud, irretrievable injustice, or special equities.
Final Decision: The appeal was dismissed, and the judgment and decree of the trial court were upheld.
( 1 ) PUNJ Lloyd Insulations Limited is a company duly registered under the companies Act, 1956 filed a suit for injunction praying for grant of a decree for permanent injunction in favour of the plaintiff and against defendant no. 2, restraining him from encashing the bank guarantee dated 8. 11. 99 which was valid upto 30th September, 2001. Separate injunction is prayed for against the bank/defendant no. 1 for making any payment under the said bank guarantee to defendant no. 2. In the plaint it was stated by the plaintiff that they had entered into an agreement for supply and application job of thermal insulation to the equipment and pipe work for the Paradeep Phasphatic Fertilizer of the defendant no. 2. On 6. 11. 99 the work was awarded to the plaintiff. The plaintiff was required to furnish bank guarantee towards mobilisation advance and performance of the contract to the extent of 10% and 5% respectively of the agreed value of contract which was Rs. 2. 50 crores. The plaintiff furnish two bank guarantees issued by defendant no. 1 towards the mobilisation advance and the performance bank guarantees valid upto 17th May, 2000 with invocation period upto 17. 11. 02. It is the case of the plaintiff that during the execution of the work defendant no. 2 changed the scope of the work and the work material requirement was revised by the plaintiff from time to time to suit the need of defendant no. 2 in the suit. The work done by the plaintiff beyond the scope of the contract was duly informed to the concerned defendant and financial implication in the performance of extra item was agreed between the parties. The plaintiff s claim to have performed the contract to the satisfaction of the concerned defendant and the entire work was completed by the plaintiff on 30th march, 2000. Due to the amendments to the scope of the work total value of the work was increased to Rs. 2,73,28,681. 47 which was also certified by the defendants. In fact, on 12th April, 2000 the defendant issued a certificate of completion of work and it was certified that the work and the project was carried out in a very professional manner with intricate planning. Complete amount of mobilisation advance was duly recovered by defendant no. 2 and the plaintiff requested defendant no. 2 to return the bank guarantee towards mobilisation advance duly discharged by defendant no. 2. The plaintiff had also requested for release of the balance payment. The mobilisation bank guarantee was returned to the plaintiff on 17th May, 2000. Vide letter dated 13th June, 2000 the value of the contract was increased and the plaintiff requested defendant no. 2 for release of its balance payment of Rs. 84,75,437. 75. After various meetings a sum of Rs. 25 lacs was released on 1st December, 2000 but the balance amount of Rs. 8,12,421. 87 was not paid. The plaintiff had been writing to the defendants for release of the payments and had so stated vide their letter dated 23rd July, 2001. It was also requested that the bank guarantee which had been submitted toward 12 months performance period, which had expired on 31st March, 2001 be also returned duly discharged to the plaintiff. But defendant no. 1 on 30th July, 2001 found that the defendant no. 2 had made a claim dated 26th July, 2001 for encashment of the bank guarantee alleging that the plaintiff had failed to fulfill the terms of the purchase order in question. According to the plaintiff, the defendants had no right whatsoever keeping in view the certificate, release of mobilisation advance, settlement of other accounts and keeping in view that still some amount was due from the defendants there was no justification whatsoever with the defendants to encash the bank guarantee and in any case there could be no breach of terms and conditions of the contract as the letter of invocation was beyond the terms of the bank guarantee. On these facts the suit for injunction was filed. The suit was contested by the defendants p
Hindustan Steelworks Construction Ltd. vs. Tarapore and Co. and Anr.
Ansal Engineering Projects Ltd. v. Tehri Hydro Development Corporation Ltd. and Anr.
Bolivinter Oil SA v. Chase Manhattan Bank
Svenska Handelsbanken v. Indian Charge Chrome
Larsen and Toubro Ltd.v. Maharashtra SEB
Hindustan Steel Workers Construction Ltd. v. G.S. Atwal and Co. (Engineers) (P) Ltd.
as also to National Thermal Power Corpn. Ltd. v. Flowmore (P) Ltd.
The latest decision is in the case of State of Maharashtra v. National Construction Co.
Hindustan Steel Works Construction Ltd. v. Tarapore and Co. and another
National Highway Authority of India v. M/s. Ganga Enterprises and anr
Hindustan Construction Co. Ltd. v. State of Bihar and others
Gujarat Optical Communication Ltd. v. Department of Telecommunication and another
Daewoo Motors India Ltd. vs. Union of India
Federal Bank Ltd. vs. V.M. Jog Engineering Ltd. and Ors
Dwarikesh Sugar Industries Ltd. vs. Prem Heavy Engineering Works (I) Ltd. and Anr
AI
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.