2017 Supreme(Del) 1073
IN THE HIGH COURT OF DELHI AT NEW DELHI
S. MURALIDHAR, J.
NATIONAL BUILDINGS CONSTRUCTION CORP. (NBCC) LTD. - Petitioner
Versus
M/S NATAVARLAL M. PATEL - Respondent
O.M.P. 552/2008 WITH O.M.P. 553/2008
Decided On : 31-03-2017
Important Points
Act Referred
ARBITRATION AND CONCILIATION ACT : S.34, S.28, S.11, S.21
CONSTITUTION OF INDIA : Art.142
CONTRACT ACT : S.55, S.28, S.73, S.55, S.52
Headnote
Arbitration & Conciliation Act - Construction Contract, Road Contract - 34, 28 - The judgment pertains to two petitions under section 34 read with section 28 of the Arbitration & Conciliation Act, 1996 by the Petitioner M/s National Building Construction Corporation (‘NBCC’) Ltd challenging the common Award dated 10th July, 2008 passed by the Sole Arbitrator in disputes arising out of the Construction Contract and the Road Contract. The Court discussed the legal provisions, their interpretations, and their influence on the court's decision.
Fact of the Case:
The petitions under section 34 read with section 28 of the Arbitration & Conciliation Act, 1996 were filed by the Petitioner M/s National Building Construction Corporation (‘NBCC’) Ltd challenging the common Award dated 10th July, 2008 passed by the Sole Arbitrator in disputes arising out of the Construction Contract and the Road Contract. The disputes arose from the Construction of MP Pool Building and Allied Works at Civil Airport, Vadodara and the Construction of Road Work of MP Pool Building and Allied Works at Civil Airport, Vadodara. The Arbitrator allowed various claims of the Respondent along with interest and costs.
Finding of the Court:
The Court found that the claims of the Respondent were not time-barred, and the Arbitrator's decision was based on the evidence before him. The Court also found that NBCC failed to produce sufficient material to support its case and that the Respondent had not waived its claims. The Court upheld the Arbitrator's decision on interest and found no grounds for interference with the impugned Award.
Issues: The issues included the limitation of claims, the reasons for delay, the waiver of claims, and the award of interest.
Ratio Decidendi: The Court held that the claims were not time-barred, NBCC failed to produce sufficient material to support its case, the Respondent had not waived its claims, and the Arbitrator's decision on interest was upheld.
Final Decision: Both the petitions were dismissed with no orders as to costs.
For the Petitioner:Mr. Manoj Kumar Dass, Advocate
For the Respondent:Ms Meenakshi Arora, Senior Advocate and Mr Vasav Anantharaman, Advocates
Introduction
1. These are two petitions under section 34 read with section 28 of the Arbitration & Conciliation Act, 1996 by the Petitioner M/s National Building Construction Corporation (‘NBCC’) Ltd.
2. The challenge in OMP No. 552 of 2008 is to the common Award dated 10th July, 2008 passed by the Sole Arbitrator in the disputes between NBCC and the Respondent, M/s Natavarlal M. Patel, arising out of an Agreement dated 1st January, 2001 whereby the work of “Construction of Road Work of MP Pool Building and Allied Works at Civil Airport, Vadodara” (hereafter ‘Road Contract’) was awarded by NBCC to the Respondent.
3. The challenge in OMP No. 553 of 2008 is to the same common Award in so far as it relates to the disputes between the parties arising out of the Agreement dated 27th October, 1999 whereby the work of “Construction of MP Pool Building and Allied Works at Civil Airport, Vadodara” (hereafter the ‘Construction Contract’) was awarded by NBCC to the Respondent.
4. There were two separate references before the same Arbitrator. In the impugned Award dated 10th July, 2008 pertaining to the disputes arising out of the Construction Contract, the learned Arbitrator allowed the Claim Nos. 1, 2, 3 (a) to (d), 4, 5, 6 of the Respondent together with simple interest at 12% per annum from the date of filing the petition under Section 11 of the Act till the date of payment apart from costs of Rs. 2 lakhs.
5. As regards the Award dated 10th July, 2008 in respect of the disputes arising out of the Road Contract, the learned Arbitrator allowed the Claim Nos. 1, 2 (a) to (c) and 3 to 6 of the Respondent together with simple interest at 12% per annum from the date of filing the petition under Section 11 of the Act till the date of payment apart from costs of Rs. 2 lakhs.
The Construction Contract
6. The background facts are that Petitioner invited tenders for the Construction of MP Pool Building and Allied Works at Civil Airport, Vadodara. The Respondent submitted its tender for the said work on 6th September, 1999. NBCC then issued a Letter of Intent (‘LOI’) / Work Order (‘WO’) in favour of the Respondent awarding it the said work for a total value of Rs. 38.97 lacs. An Agreement i.e., the Construction Contract was entered into on 27th October, 1999. In terms thereof, the date of start of work was 21st October, 1999. The completion period was 9 months expiring in July, 2000. NBCC claims that time was of essence to the Contract.
7. It is stated that the Respondent commenced the work on the stipulated date but could not complete it by 31st July, 2000. NBCC then granted an extension of time (‘EOT’) for the completion of the work till 15th January, 2001. This EOT was "without imposition of the penalty and without escalation". It is stated that the Respondent completed the work on 15th January, 2001.
8. On 8th February, 2001, NBCC by letter dated 8th February, 2001 had asked the Respondent to submit proper documents/evidence in compliance of Clause 17 (Insurance), Clause 19 (Third Party Insurance) & Clause 23.2 (EPF Contribution) etc. It is stated that in April 2001, the Respondent submitted its final bill which was finally prepared/passed by NBCC and was signed by the Respondent by way of acceptance on 31st August, 2001.
9. In terms of the said final bill, a sum of Rs. 7,40,793 was payable to the Respondent. According to NBCC, the said amount was, however, not released to the Respondent on account of the failure of the Respondent to fulfil its part of the contractual / statutory obligation as per Clause 13 (non-payment of levies, taxes, duties) etc., Clause 19 (third party insurance for damages/loss/injury), Clause 23 (observance of labour laws, EPF contribution), Clause 29 (bill of materials in respect of extra items). By letter dated 6th September, 2001, NBCC again asked the Respondent to submit proper documents. A reminder was sent on 13th O