IN THE HIGH COURT OF DELHI AT NEW DELHI
JYOTI SINGH, J.
Larsen & Toubro Limited - Petitioner
Versus
Experion Developers Pvt. Ltd & Ors. - Respondents
O.M.P.(I) (Comm.) 234 Of 2019
Decided On : 03-12-2019
| Table of Content |
|---|
| 1. details of contractual obligations and guarantees. (Para 1 , 2 , 3 , 4 , 5) |
| 2. petitioner's argument on contract validity and performance. (Para 6 , 16 , 17 , 18 , 19) |
| 3. court's observations on prior injunctions. (Para 8 , 9 , 14) |
| 4. petitioner's continued arguments on contractual compliance. (Para 20 , 21 , 22) |
| 5. respondent's arguments on invocation of guarantees. (Para 23 , 24 , 25 , 29 , 30 , 31) |
| 6. discussion of previous judgments and their relevance. (Para 32 , 33 , 34 , 40 , 41) |
| 7. legal principles governing bank guarantees. (Para 59 , 60 , 61 , 62 , 63 , 64) |
| 8. court's detailed analysis on bank guarantees. (Para 65 , 66 , 67 , 68 , 69) |
| 9. final determinations on guarantee validity. (Para 70 , 71 , 72) |
| 10. conclusion of the court's judgment. (Para 88 , 94 , 96 , 97) |
JUDGMENT :
JYOTI SINGH, J.
1. This is a petition under Section 9 of the Arbitration & Conciliation Act, 1996 (‘Act’) seeking interim injunction restraining the respondents from invoking Retention Money Bank Guarantees (‘RMBG’) for Rs.13,84,35,000/- each dated 18.04.2014 and 08.09.2014 respectively as well as Performance Bank Guarantee (‘PBG’) for Rs.31,68,44,008/- dated 15.03.2013.
2. The brief facts required to be captured for deciding the present petition are that on 29.09.2012, respondent No. 1 issued a letter of intent in favour of the petitioner intending to award the work of Design and Build of a Group Housing Project at a cost of Rs. 682 Crores. A letter of acceptance was issued on 05.02.2013 by respondent No. 1 and a contract was executed between the parties on 07.02.2013. The date of commencement of the work was 09.01.2013 and date of completion was 09.01.2016.
3. On 15.03.2013, respondent No. 4 issued PBG in favour of respondent No. 1 on behalf of the petitioner for an amount of Rs. 34,10,00,000/- valid upto 10.04.2016. As per the terms of the PBG, it was to remain valid till the petitioner’s obligations were fulfilled under the Contract or until its first expiry whichever was earlier. The PBG was however, extended from time to time and finally reduced to a sum of Rs. 31,68,44,008/-.
4. Likewise, on 18.04.2013, RMBG was issued by respondent No. 2 in favour of respondent No. 1 for an amount of Rs. 6,92,17,500/-, subsequently revised to Rs.13,84,35,000/-. The second RMBG was issued by respondent No. 2 in favour of respondent No. 1 on 08.09.2014 for an amount of Rs. 6,92,17,500/-, subsequently revised to Rs.13,84,35,000/-. The completion date of the project was later extended to 31.08.2016 by an addendum to the Contract executed on 20.01.2015. A partial extension of time for completion of the Project was made by respondent No. 1 on 20.01.2017 for a period of 11 days. Request of the petitioner for extension of time till 30.06.2019 elicited no response from respondent No. 1. Subsequent requests for extension were again not responded to. The PBG was however extended to 30.06.2019 and the second RMBG was also extended to 30.06.2019.
5. It is the case of the petitioner that pursuant to a meeting held on 02.05.2019 between the parties, a request was made by the petitioner to extend the time for completion of the Project till 30.10.2019, in accordance with clause 8.4 of the Contract.
6. On 11.06.2019, respondent No. 1 informed the petitioner by a letter that it was not in a position to accept the timelines proposed by the petitioner and requested the petitioner to complete the occupational certificate inspection by 15.06.2019 and to renew the PBG for full value. Attempts to resolve the disputes amicably between the parties were unsuccessful.
7. It is the case of the petitioner that in these circumstances, respondent No. 1 invoked four Bank Guarantees (hereinafter referred to as ‘BGs’) against the petitioner viz. the three aforementioned and one Advance Bank Guarantee. Constrained by this invocation, petitioner filed a petition in this Court under Se
Adri Dharan Das v. State of W.B.
Ansal Engineering Projects Ltd. Vs. Tehri Hydro Development Corporation Ltd. and Anr.
Canara Bank (supra), Makhija Construction & Engg Pvt Ltd v. Indore Development Authority
Doosan Babcock Ltd. v. Comercializdora de Equipos y Materiales Mabe Lda (formerly Mabe Chile Lda)
Dwarikesh Sugar Industries Ltd. Vs. Prem Heavy Engineering Works (P) Ltd. and Anr.
Erach Soman Khavar vs. Tukaram Shridhar Bhatta
Fuerst Day Lawson v. Jindal Exports
Gangotri Enterprises Limited vs. Union of India & Ors.
Gujarat Maritime Board v. Larsen and Toubro Infrastructure Development Projects Limited
Himadari Chemicals Industries Ltd. v. Coal Tar Refining Company
Hindustan Construction Company v. State of Bihar
Hindustan Steel Workers Construction Ltd. v. G.S. Atwal & Co. (Engineers) (P) Ltd. (1995) 6 SCC 76
Hindustan Steel Works Construction Ltd. vs. Tarapore & Co. & Anr.
Larsen & Toubro Ltd. v. Maharashtra SEB
Mahadeolal Kanodia vs. Administrator-General of West Bengal
Mahatma Gandhi Sahakra Sakkare Karkhane Vs. National Heavy Engg. Coop. Ltd. and Anr.
Mamleshwar Prasad and Ors. v. Kanhaiya Lal (dead) through L. Rs.
NCC Limited Vs. Sembcorp Gayatri Power Limited and Ors.
S. Nagraj (Dead) By LRS v. BR Vasudeva
Salauddin Abdulsamad Shaikh v. State of Maharashtra
Siddharam Satlingappa Mhetre vs. State of Maharashtra & Ors.
State of Karnataka vs. Shree Rameshwara Rice Mills, Thirthahalli
Sub-Inspector Rooplal & Anr. v. Lt Governor through Chief Secretary, Delhi & Ors.
Svenska Handelsbanken v. Indian Charge Chrome
Tarini Charan Bhattacharjee v. Kedar Nath Haldar
U.P. Cooperative Federation Ltd. vs. Singh Consultants & Engineers (P) Ltd.
U.P. State Sugar Corpn. v. Sumac International Ltd.
Union of India (UOI) vs. Raman Iron Foundry
Vinitec Electronics Private Limited Vs. HCL Infosystems Ltd.
AI
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.