IN THE HIGH COURT OF DELHI AT NEW DELHI
RAJIV SAHAI ENDLAW, SANJEEV NARULA, JJ.
AMR-BBB Consortium Thro, Lead Partner, AMR India Ltd. - Appellant
Versus
Bharat Coking Coal Ltd. & Anr. - Respondents
FAO(OS) (COMM) 20 of 2021, CMs No. 4009 of 2021 (for stay), 4010 of 2021 (for permission to file lengthy synopsis and list of dates)
Decided On : 26-03-2021
Arbitration and Conciliation Act 1996 - Section 37 - Section 9 - Encashing bank guarantees - Seeking interim measures for protection - Work Tender - Contract Breach of.
Finding of the Court:
Court do find merit in contention that as bank guarantees had not been encashed at point when matter was heard learned Single Judge should not have granted alternate prayer and fact Impugned Order does not record any reason for declining main relief of injunction and thus to this extent learned Single Judge fell in error - mount of bank guarantees in question has been ordered to be deposited before this Court and same is subject to outcome of arbitration proceedings - BCCL has not assailed Impugned Order - Thus although Appellant is prejudiced by encashment but amount is still secured - In event Appellant succeeds in arbitration proceedings necessary orders pertaining to amount of bank guarantees will necessarily follow –
Result: Appeal disposed of
JUDGMENT
Sanjeev Narula, J.
[Via Video Conferencing]
1. The present appeal under Section 37(1)(b) of the Arbitration and Conciliation Act, 1996 [hereinafter referred to as the ‘Act’] is directed against the final judgment/order dated 27th January, 2021 [hereinafter referred to as 'Impugned Order’] passed by the learned Single Judge in OMP (I) (COMM) 31/2021, wherein the petition filed by the Appellant herein under Section 9 of the Act, seeking orders restraining the Respondent from encashing bank guarantees, has been decided by directing the Respondents No. 2 to 5 [hereinafter referred to as the 'Banks'] to encash the four bank guarantees and transfer the encashed amount into the account of the learned Registrar General of this Court, to be put in a fixed deposit subject to the outcome of the arbitration proceedings.
Facts
2. The bare essential facts leading to the establishment of the bank guarantees in question are that a Notice Inviting Tender [hereinafter referred to as 'NIT] along with Geological Reports furnished therein [hereinafter referred to as 'GRs'], was issued by Respondent No. 1 [Bharat Coking Coal Ltd., hereinafter referred to as 'BCCL'] for, inter alia, ''Development of Kapuria Block and extraction of coal by mass production technology package for a minimum guaranteed production of 2.0 million ton per year on turnkey basis" [hereinafter referred to as the 'Project']. Pursuant thereto, on 10th September, 2011, a letter of acceptance was issued by BCCL to the Appellant/Consortium contractor. This was followed by the execution of a Contract Agreement between the Appellant and BCCL on 18th April, 2012 [hereinafter referred to as the 'Contract’]. On 8th November, 2012, the Appellant after undertaking exploration works, submitted a comprehensive Detailed Project Report to BCCL, for approval [hereinafter referred to as ‘.DPR’]. On 11th July, 2013, BCCL communicated its approval to the Appellant and gave directions to start work as per the approved DPR, after obtaining the required environmental clearance and statutory approvals. Based on the approval of the aforesaid DPR, on 29th July, 2013, the Appellant in line with Clause 4.1.4 of the Contract, furnished a performance bank guarantee in favour of BCCL for an amount of Rs.12,78,49,970/-. The Appellant also prepared a mining plan for extraction of coal reserves and submitted the same to BCCL, which was approved on 30th December, 2014. In line with the same, the Appellant conducted Environmental Impact Assessment and Environmental Management Plan, and submitted these reports to BCCL, based whereupon, environmental clearance for the Project was accorded on 19th December, 2014 by the Ministry of Environment and Forest, Government of India.
3. Based on the approved DPR, the Appellant tied up the supply of indigenous and imported plant and machinery/equipment for the Project and in terms of Clause 4.1.49.3 of the Contract furnished three bank guarantees for release of 5% part payment of deliverable plant and machinery to BCCL, for Rs.6,40,75,203/-, 20,00,00,000/- and 14,79,00,000/- respectively.
4. On 15th January, 2018, BCCL informed the Appellant that the Internal Rate of Return (IRR) of the total investment in the Project was unfavourable, as, upon a re-examination of the layout of the proposed panels, it was found that the amount of coal extraction is likely to be greatly reduced. Resultantly, subsidence studies were done afresh through the Central Institute of Mining and Fuel Research and its report was submitted in June, 2018. On 26th November, 2018, BCCL informed the Appellant that the reports furnished by the Appellant have been provided to the Design Consultant (Central Mine Planning and Design Institute Limited) to re-work the integrated economics of this Project. Thereafter, on 20th May, 2019, BCCL furnished a fresh GR to prepare revised DPR.
5. According to the Appellant, the fresh GRs were at great variance to the earlier GRs and called for entire fresh planning of wo
U.P. Cooperative Federation Ltd. v. Singh Consultants and Engineers (P) Ltd.
U.P State Sugar Corporation v. M/s Sumac International Ltd.
Atul Gupta and Ors. v. S. Chand and Company Limited and Ors.
Tender/Contract – Breach of – Invocation of bank guarantees - Existence of disputes between the parties to the Contract is not a ground for issuing an order of injunction to restrain enforcement of b....
The invocation of bank guarantees must adhere strictly to the contractual terms; courts may intervene to prevent encashment if it risks undermining arbitration.
A confirmed Bank Guarantee/irrevocable Letter of Credit cannot be interfered with unless there is established fraud or irretrievable injustice involved in case.
Courts should not interfere with the invocation or payment under an unconditional bank guarantee unless there is egregious fraud or special equity.
The obligation of a bank guarantee is independent of underlying contractual disputes, and interference is justified only in cases of fraud or irretrievable injustice.
Invocation of an unconditional bank guarantee cannot be restrained unless fraud or irretrievable injustice is established; the nature of bank guarantees is independent and absolute.
Bank guarantees can be invoked regardless of disputes, unless fraud or irretrievable harm is clearly established.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.