IN THE HIGH COURT OF DELHI AT NEW DELHI
Vibhu Bakhru, J.
Gail (india) Ltd. - Appellant
Versus
M/s. Gupta Bros (india) - Respondent
O. M. P. (Comm. ) No. 474/2018
Decided On : 11-01-2022
Arbitration - GAIL (India) Ltd. - Arbitration and Conciliation Act, 1996 - 34
Fact of the Case:
GAIL terminated a construction contract with M/s Gupta Bros (India) for delay in completion. GAIL claimed reimbursement for additional costs incurred. The Arbitral Tribunal found GAIL's termination wrongful and awarded in favor of M/s Gupta Bros (India) for work done, PBG refund, and bank charges.
Finding of the Court:
The Arbitral Tribunal found GAIL's termination wrongful, accepted M/s Gupta Bros (India)'s claims for work done, PBG refund, and bank charges, and rejected GAIL's claims.
Issues: Termination of contract, delay in completion, reimbursement of additional costs, PBG refund, bank charges
Ratio Decidendi: The termination of the contract was found to be wrongful due to delay primarily attributable to GAIL, and GAIL's failure to provide joint measurements of work done and withholding of payments.
Final Decision: The petition is unmerited and dismissed.
JUDGMENT
Vibhu Bakhru, J. - Introduction
1. GAIL (India) Ltd. (hereinafter 'GAIL') has filed the present petition under section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter the 'A&C Act') impugning an arbitral award dated 31.07.2018 (hereinafter the 'impugned award') delivered by an Arbitral Tribunal constituted of Justice (Retd.) Aftab Alam, former Judge of the Supreme Court as the Sole Arbitrator (hereinafter the 'Arbitral Tribunal').
2. The impugned award was rendered in the context of disputes that have arisen between the parties in connection with a contract for construction of a residential colony for the employees of GAIL who are employed at LPG Recovery Plant at Ghandhar, District Bharuch, Gujarat (hereafter 'the Contract'). GAIL had terminated the Contract alleging that the respondent, M/s Gupta Bros (India), had failed to perform its obligations and complete the work within the stipulated period.
3. GAIL had, thereafter, engaged another contractor for completion of the balance work at the risk and costs of the respondent. GAIL claimed that in terms of the Contract, it was entitled to be reimbursed the additional amount paid for completion of the works (the amount spent in excess of the agreed consideration) along with administrative charges at the rate of 10% of the additional amount. Accordingly GAIL claimed a sum of Rs. 7,38,10,000/- on account of balance works executed at the respondent's risk and cost. GAIL recovered part of the amount by encashing the Contract Performance Bank Guarantee (hereafter 'the PBG') of Rs. 1,65,00,000/- and selling certain construction equipment belonging to the respondent for a sum of Rs. 5,00,000/-. GAIL claimed the remaining amount along with interest at the rate of 18% per annum.
4. The respondent disputed the claims made by GAIL. It contended that GAIL was responsible for the delay in execution of the project and therefore, the termination of the Contract by GAIL was illegal. It also claimed that GAIL's termination of the Contract was motivated to punish the respondent for taking recourse to Courts to challenge GAIL's of blacklisting the respondent in respect of another contract. The respondent also raised several counter-claims premised on the aforesaid assertions.
5. The Arbitral Tribunal accepted the respondent's case that GAIL did not have any grounds to terminate the Contract and the termination of the Contract were wrongful and unsustainable. The Arbitral Tribunal rejected the claims raised by GAIL. Insofar as the counter claims are concerned, the Arbitral Tribunal allowed the respondent's claim for payment of work done but not paid; refund of the amount recovered by encashment of PBG; and refund of bank charges along with interest at the rate of 12% per annum from 10.10.2014 till the date of payment. The remaining counterclaims were rejected.
6. The respondent has accepted the impugned award and has not challenged the impugned award to the extent it has rejected the counter-claims. GAIL, being aggrieved by the impugned award, has filed the present petition.
Factual Context
7. GAIL issued a Notice dated 16.03.2010 inviting offers for construction of residential accommodation / quarters / bachelors accommodation for its employees / officials at Bharuch in Gujarat, Rajamundry in Andhra Pradesh and Khera in Madhya Pradesh. The bidders were permitted to submit separate bids for the projects at the aforesaid three locations. The bids submitted by the respondent for the project at Bharuch in Gujarat and Rajamundry in Andhra Pradesh were accepted. On 27.07.2010, GAIL issued a Fax of Acceptance (FOA) on 27.07.2010 communicating its acceptance of the bids submitted by the respondent for the projects at the said two locations (Bharuch and Rajamundry).
8. The controversy in the present case relates to the Contract for executing the works at Bharuch (hereinafter 'the Project')
The termination of a contract can be deemed wrongful if it is primarily due to the actions of the party seeking termination and if the party fails to provide essential documentation or withholds paym....
The court reaffirmed the need for parties to substantiate claims with primary evidence in arbitration proceedings while respecting the arbitrator's discretion unless a clear patent illegality is prov....
The Arbitral Tribunal's decision to award refunds related to price reductions and bank charges was upheld, demonstrating the limited grounds for court interference under the Arbitration and Conciliat....
The issuance of a No Claim Certificate under coercion does not negate a party's claims, and contractual requirements for communication in risk transfer are mandatory.
The main legal point established in the judgment is that the decision of the arbitral Tribunal is entitled to substantial discretion in awarding interest, and the court does not sit as the first appe....
The No Claim Certificate was invalid due to coercion, allowing the party to assert claims under the contract notwithstanding the issuance of such certificate.
The main legal point established is that disputes can be arbitrable despite fraud allegations, and the court has the authority to appoint a Sole Arbitrator to adjudicate disputes arising from a const....
An arbitral award can only be annulled on limited grounds of patent illegality or violation of public policy; mere errors in evidence appreciation do not suffice.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.