SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img



IN THE HIGH COURT OF DELHI
Vibhu Bakhru, J.
Gail (India) Ltd. - Appellant
Versus
Triveni Engineering & Industries Ltd. - Respondent
O.M.P.(COMM.) 390 of 2020
Decided On : 12-05-2022




The Arbitral Tribunal's decision to award refunds related to price reductions and bank charges was upheld, demonstrating the limited grounds for court interference under the Arbitration and Conciliation Act.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - Arbitration award impugned for alleged errors in awarding damages, including liquidated damages and interest - Arbitrator upheld majority of claims by the respondent. (Paras 1, 28, 58)

(B) Scope of arbitral review - The court's role is limited to ascertaining that the award does not suffer from patent illegality, public policy contravention, or evident errors. (Paras 61, 62)

Facts of the case:
Disputes arose between the parties concerning the performance of a contract for a construction project due to delays and the execution of certain works, including Cathodic Protection System. The award primarily focused on claims related to price reduction and unjustified withholding of funds by GAIL. (Paras 5, 7, 28)

Findings of Court:
The Arbitral Tribunal's award of Rs.2,75,00,000/- for withheld amounts and establishment of bank charges was affirmed. Additional costs were awarded for the respondent’s claims. (Paras 28, 57)

Issues: The appeal questioned the validity of the Tribunal's decisions on liquidated damages, scope of work, and applicability of price reduction measures. (Paras 30, 32)

Ratio Decidendi: The court found that the Arbitral Tribunal had acted well within its jurisdiction, and claims were supported by sufficient evidence. GAIL’s arguments against the award did not satisfy the high threshold for interference. (Paras 36, 40)

Result: Petition dismissed with costs.

Table of Content
1. procedural context of arbitration (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 28)
2. delays and extensions of time (Para 8 , 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16 , 17)
3. finalization and verification of works (Para 18 , 19 , 20 , 21 , 22 , 23 , 24)
4. contentions raised by gail (Para 30 , 31 , 32 , 33 , 34)
5. assessment of bank charges and prs (Para 35 , 36 , 37 , 40 , 56 , 57)
6. justification of the arbitral tribunal's award (Para 39 , 44 , 58)

JUDGMENT

Vibhu Bakhru, J. The petitioner (hereinafter `GAIL') has filed the present petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter `the A&C Act') impugning an arbitral award dated 20.11.2019 (hereinafter `the impugned award') rendered by an Arbitral Tribunal comprising of a former Chief Justice of the High Court of Jammu and Kashmir as the Sole Arbitrator (hereinafter `the Arbitral Tribunal')

2. The impugned award was rendered in the context of disputes that have arisen between the parties in connection with an agreement dated 28.05.2012 (hereinafter the `Agreement').

3. The controversy in the present case arises in the following context:

4. Tenders were invited by GAIL (being Tender no. A096/T-069/11-12/MS/38) for the works regarding setting up of a "Dematrialised (DM) Water Plant and Condensate Polishing Unit (CPU) for GAIL Petrochemical Complex-II at Pata, Uttar Pradesh" (hereinafter the `Project'), on the terms and conditions stipulated therein.

5. Pursuant to the said invitation to tender, the respondent submitted its bid for executing the Project, on 27.02.2012. The respondent's bid was accepted and thereafter, GAIL issued a Fax of Acceptance dated 03.05.2012 (hereinafter the `FoA'), accepting the respondent's bid to execute the Project for a consideration of Rs.55 crores inclusive of all taxes and duties except service tax at the rate of 4.944%. The `Extended Stay Compensation' was stipulated as Rs.10,00,000/- per month. In terms of the FoA, the respondent was required to furnish a Performance Bank Guarantee and enter into a formal agreement within a period of fifteen days from the date of the said FoA, as per the provisions of the tender documents.

6. Subsequently, on 22.05.2012, GAIL issued the Letter of Acceptance (hereafter the `LoA'). M/s Engineers India Limited (hereafter `EIL') was appointed as the `Engineer in-Charge' under the Agreement. The effective date of commencement of the Project was stipulated as 03.05.2012 and the works were to be completed within a period of eighteen months, that is, on or before 02.11.2013. Thereafter, on 28.05.2012, the parties signed the Agreement.

7. The execution of the Project was delayed. GAIL withheld amounts as reduction of price as stipulated under Clause 27 of the GCC. It also withheld an amount of Rs.1,20,00,000/- as the value of Cathodic Protection System, on the ground that the same was within the scope of work but was not installed. Disputes arose between the parties regarding the Price Reduction Schedule (hereinafter `PRS'), installation of Cathodic Protection System (hereinafter `CPS'), extra works performed under the Agreement and bank charges.

8. The context in which the aforesaid dispute arose are briefly stated hereafter.

9. The respondent, by a communication dated 25.10.2013, requested EIL for provisional extension of time for a period of four months without imposition of liquidated damages. The respondent stated that the delays in execution of Project works were caused, inter alia, due to local disputes, delay in supply items, force majeure events, delay due to rainy season, delay in supply item and sequential work front. Thereafter, by a letter dated 28.10.2013 addressed to GAIL, EIL recommended that provisional extension of time be granted to the respondent till 31.01.2014 without prejudice to GAIL's right to impose PRS as per the provisions of the Agreement, in the case the delays were attributable to the respondent.

10. On 31.10.2013, GAIL granted provisio







Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top