IN THE HIGH COURT OF DELHI
Vibhu Bakhru, J.
Gail (India) Ltd. - Appellant
Versus
Triveni Engineering & Industries Ltd. - Respondent
O.M.P.(COMM.) 390 of 2020
Decided On : 12-05-2022
| Table of Content |
|---|
| 1. procedural context of arbitration (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 28) |
| 2. delays and extensions of time (Para 8 , 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16 , 17) |
| 3. finalization and verification of works (Para 18 , 19 , 20 , 21 , 22 , 23 , 24) |
| 4. contentions raised by gail (Para 30 , 31 , 32 , 33 , 34) |
| 5. assessment of bank charges and prs (Para 35 , 36 , 37 , 40 , 56 , 57) |
| 6. justification of the arbitral tribunal's award (Para 39 , 44 , 58) |
JUDGMENT
Vibhu Bakhru, J. The petitioner (hereinafter `GAIL') has filed the present petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter `the A&C Act') impugning an arbitral award dated 20.11.2019 (hereinafter `the impugned award') rendered by an Arbitral Tribunal comprising of a former Chief Justice of the High Court of Jammu and Kashmir as the Sole Arbitrator (hereinafter `the Arbitral Tribunal')
2. The impugned award was rendered in the context of disputes that have arisen between the parties in connection with an agreement dated 28.05.2012 (hereinafter the `Agreement').
3. The controversy in the present case arises in the following context:
4. Tenders were invited by GAIL (being Tender no. A096/T-069/11-12/MS/38) for the works regarding setting up of a "Dematrialised (DM) Water Plant and Condensate Polishing Unit (CPU) for GAIL Petrochemical Complex-II at Pata, Uttar Pradesh" (hereinafter the `Project'), on the terms and conditions stipulated therein.
5. Pursuant to the said invitation to tender, the respondent submitted its bid for executing the Project, on 27.02.2012. The respondent's bid was accepted and thereafter, GAIL issued a Fax of Acceptance dated 03.05.2012 (hereinafter the `FoA'), accepting the respondent's bid to execute the Project for a consideration of Rs.55 crores inclusive of all taxes and duties except service tax at the rate of 4.944%. The `Extended Stay Compensation' was stipulated as Rs.10,00,000/- per month. In terms of the FoA, the respondent was required to furnish a Performance Bank Guarantee and enter into a formal agreement within a period of fifteen days from the date of the said FoA, as per the provisions of the tender documents.
6. Subsequently, on 22.05.2012, GAIL issued the Letter of Acceptance (hereafter the `LoA'). M/s Engineers India Limited (hereafter `EIL') was appointed as the `Engineer in-Charge' under the Agreement. The effective date of commencement of the Project was stipulated as 03.05.2012 and the works were to be completed within a period of eighteen months, that is, on or before 02.11.2013. Thereafter, on 28.05.2012, the parties signed the Agreement.
7. The execution of the Project was delayed. GAIL withheld amounts as reduction of price as stipulated under Clause 27 of the GCC. It also withheld an amount of Rs.1,20,00,000/- as the value of Cathodic Protection System, on the ground that the same was within the scope of work but was not installed. Disputes arose between the parties regarding the Price Reduction Schedule (hereinafter `PRS'), installation of Cathodic Protection System (hereinafter `CPS'), extra works performed under the Agreement and bank charges.
8. The context in which the aforesaid dispute arose are briefly stated hereafter.
9. The respondent, by a communication dated 25.10.2013, requested EIL for provisional extension of time for a period of four months without imposition of liquidated damages. The respondent stated that the delays in execution of Project works were caused, inter alia, due to local disputes, delay in supply items, force majeure events, delay due to rainy season, delay in supply item and sequential work front. Thereafter, by a letter dated 28.10.2013 addressed to GAIL, EIL recommended that provisional extension of time be granted to the respondent till 31.01.2014 without prejudice to GAIL's right to impose PRS as per the provisions of the Agreement, in the case the delays were attributable to the respondent.
10. On 31.10.2013, GAIL granted provisio
The Arbitral Tribunal's decision to award refunds related to price reductions and bank charges was upheld, demonstrating the limited grounds for court interference under the Arbitration and Conciliat....
The main legal point established in the judgment is that the decision of the arbitral Tribunal is entitled to substantial discretion in awarding interest, and the court does not sit as the first appe....
The court reaffirmed the need for parties to substantiate claims with primary evidence in arbitration proceedings while respecting the arbitrator's discretion unless a clear patent illegality is prov....
The termination of a contract can be deemed wrongful if it is primarily due to the actions of the party seeking termination and if the party fails to provide essential documentation or withholds paym....
The issuance of a No Claim Certificate under coercion does not negate a party's claims, and contractual requirements for communication in risk transfer are mandatory.
The No Claim Certificate was invalid due to coercion, allowing the party to assert claims under the contract notwithstanding the issuance of such certificate.
Arbitral tribunals have discretion over fact-finding, and courts should not re-evaluate evidence unless decisions violate public policy or involve patent illegality.
The Arbitral Tribunal has considerable discretion in evaluating evidence and interpreting contract clauses, and its decision cannot be interfered with unless found to be patently illegal or in confli....
The Arbitral Tribunal's decision falls within its jurisdiction and does not amount to patent illegality, as it was based on a plausible interpretation of the exclusionary clause in the contracts and ....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.