SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img



IN THE HIGH COURT OF DELHI
Vibhu Bakhru, J.
Gail (India) Limited - Appellant
Versus
Bansal Infratech Synergies Limited - Respondent
O.M.P. (COMM.) 177 of 2021 and IA No. 7093 of 2021
Decided On : 06-07-2021




The No Claim Certificate was invalid due to coercion, allowing the party to assert claims under the contract notwithstanding the issuance of such certificate.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 11(6) - Validity of No Claim Certificate - Court finds that the No Claim Certificate and Material Reconciliation Statement were obtained through undue influence and coercion, thus invalid - The contract could not be considered discharged as payments under the Final Bill were not completed. (Paras 9, 18, 32)

(B) Claims - The Arbitral Tribunal awarded a refund of the water charges and the return of structural steel, determining that deductions made by the employer were improper - Delayed payments required interest at 10% per annum. (Paras 11, 17)

(C) Waiver of Claims - Respondent's claim for compensation for extended stay was denied as it was found to have waived this right without any coercion. (Para 15)

Facts of the case:
The dispute arose after GAIL failed to pay the respondent’s final bill completely, despite partial payments made over several years, leading to arbitration.

Findings of Court:
The Arbitral Tribunal found the unpaid amount insufficient to discharge the contract, and the documents claimed to discharge claims were invalid due to coercion.

Issues: The core issues were the validity of the No Claim Certificate, entitlement to water charge refund, retention of structural steel, and compensation for delay.

Ratio Decidendi: The Tribunal ruled that coercion vitiated the No Claim Certificate and the contractor was entitled to assert claims since full payment was not made for the contract.

Result: Petition dismissed.

Table of Content
1. introduction and factual background of the case. (Para 1 , 2 , 3 , 4)
2. claims made by the respondent. (Para 5 , 6)
3. gail's defense against the claims. (Para 7 , 8)
4. arbitral tribunal's finding on coercion and contract discharge. (Para 9 , 10)
5. evaluation of claims regarding water and structural steel. (Para 11 , 12 , 13 , 14)
6. arbitral tribunal's conclusion on compensation for delays. (Para 15 , 16)
7. finding on delayed payments and interest awarded. (Para 17 , 18)
8. interpretation of contract clauses related to water supply. (Para 19 , 20 , 21)
9. evidence regarding water supply from gail. (Para 22 , 23)
10. court's agreement with tribunal on structural steel claims. (Para 24 , 25)
11. arguments on coercion and undue influence in claim processing. (Para 26 , 27 , 28 , 29)
12. assessment of evidence supporting the coercion claim. (Para 30 , 31 , 32)
13. rejection of counterarguments regarding claim substantiation. (Para 33 , 34)
14. final dismissal of the petition. (Para 35)

JUDGMENT

Vibhu Bakhru, J. GAIL (India) Limited (hereinafter `GAIL') has filed the present petition impugning an arbitral award dated 10.12.2020 (hereinafter `the impugned award') rendered by an Arbitral Tribunal constituted by Justice (Retd.) Badar Durrez Ahmed as the Sole Arbitrator. The said award was rendered in respect of disputes that had arisen between the parties in connection with the contract for `Civil and Structural Works- II (OFFSITES)' at GAIL's Petrochemical Complex-II at Pata, Uttar Pradesh (hereinafter `the Project').

2. GAIL had appointed Engineers India Limited (EIL) as the consultant for implementation of the Project. EIL invited bids for the Project on behalf of GAIL and the respondent had submitted its bid pursuant to the said invitation. The respondent's bid for a contract value of Rs.67,09,29,050/- was accepted and the same was communicated to the respondent by a Fax of Acceptance (FAO) on 31.05.2011. Subsequently, on 14.06.2011, a detailed letter of acceptance (DLOA) was issued to the respondent. The works were required to be completed within a period of seventeen months with effect from the date of issuance of the FOA; that is, by 31.10.2012. The time for completing the works was extended and the respondent finally completed the same on 30.06.2014. Thereafter, on 15.06.2015, the respondent submitted its Final Bill to EIL. The Final Bill was forwarded by EIL to GAIL and payments against the same were made on the recommendations of EIL. The last payment was made to the respondent on 04.10.2017.

3. Shortly after receiving the last payment, the respondent invoked the Arbitration Clause and issued a notice dated 12.10.2017. GAIL did not take any steps for either resolving the disputes or constituting the Arbitral Tribunal pursuant to the aforesaid notice, as according to it, there were no disputes between the parties. According to GAIL, the contract stood discharged by accord and satisfaction in view of the No Claim Certificate (hereinafter `the NCC') issued by the respondent.

4. Since GAIL did not act on the aforementioned notice for arbitration, the respondent filed a petition under Section 11(6) of the A&C Act seeking appointment of an Arbitrator. This Court allowed the said petition and by an order dated 16.04.2018, appointed the Sole Arbitrator to adjudicate the disputes between the parties.

5. The respondent filed its Statement of Claims before the Arbitral Tribunal, inter alia, raising several claims. The same are briefly described below:

5.1. Claim No.1: a sum of Rs.31,23,139/- plus interest at the rate of 16% per annum. An amount equivalent to 0.5% of the Running Account (RA) bills submitted by the respondent had been deducted towards water charges. The respondent claimed the said amount on account of sums deducted by GAIL as deduction on account of water charges. The respondent claimed that in fact at the material time, the water networks were either non-existent or were not fully charged and therefore

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top