IN THE HIGH COURT OF DELHI
Vibhu Bakhru, J.
Armtech (India) Limited - Appellant
Versus
Gail (India) Limited - Respondent
O.M.P. (COMM) 20 of 2020 and O.M.P. (COMM) 33 of 2020 and IA No. 779 of 2020
Decided On : 04-07-2022
| Table of Content |
|---|
| 1. overview of disputes and contract execution (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8 , 9 , 10 , 11) |
| 2. invocation of arbitration by armtech (Para 12 , 13) |
| 3. claims and counterclaims summary (Para 14 , 15 , 16) |
| 4. tribunal's observations on claims (Para 17 , 18 , 19) |
| 5. discussion on claim no.3 (Para 20 , 21 , 22 , 23 , 24) |
| 6. contested issues on delay and prs (Para 25 , 26 , 27) |
| 7. analysis of tribunal's conclusions on delays (Para 28 , 29 , 30 , 31 , 32) |
| 8. judicial review limits under a&c act (Para 33) |
| 9. findings on gail's counterclaims (Para 35 , 39 , 40) |
| 10. counterclaims related to execution of works (Para 41 , 42 , 43) |
| 11. claims rejected on lack of evidence (Para 44 , 50 , 51 , 52 , 53) |
| 12. interest claims and tribunal's discretion (Para 54 , 55 , 56 , 57 , 58 , 59 , 60 , 61) |
| 13. final order on claim adjustment (Para 63) |
| 14. conclusion of the judgments (Para 64) |
JUDGMENT
Vibhu Bakhru, J.
1. The aforesaid petitions are cross petitions under Section 34 of the Arbitration & Conciliation Act, 1996 (hereafter the `A&C Act') impugning the Arbitral Award dated 24.09.2019 (hereafter the `impugned award') rendered by an Arbitral Tribunal constituted of Justice (Retd.) V.K. Gupta as the Sole Arbitrator (hereafter the `Arbitral Tribunal').
2. The impugned award was rendered in the context of the disputes that have arisen between the parties in connection with an Agreement dated 01.05.2012, whereby Armtech (India) Limited [petitioner in OMP(COMM) No.20/2020 - hereafter referred to as `Armtech'] had agreed to execute the works relating to the "External Development and External Services for 100 Type B and 20 Type D Houses at Gain Gaon, Dibiyapur, Auraiya, Uttar Pradesh".
3. GAIL (India) Limited [petitioner in OMP(COMM) No.33/2020 - hereafter referred to as `GAIL'], is a Government of India undertaking, inter alia, engaged in the business of distribution of natural gas, liquid hydrocarbons, LPG, manufacturing of petrochemicals etc. One of GAIL's manufacturing unit is located at Gail Gaon, Dibiyapur, District Auraiya, Uttar Pradesh.
4. GAIL issued a tender [bearing Tender No. GAIL/PA11/35611/3300043656/SKG (E-bid No.8000003712] inviting bids for executing the works of external development and external services for 100 Type B and 20 Type D houses at Gail Gaon.
5. Pursuant to the aforesaid tender, Armtech submitted its bid. Armtech was declared as the successful bidder and accordingly GAIL issued a Fax of Acceptance (FOA) dated 01.02.2012. In terms of the FOA, the estimated value of the Contract was fixed at Rs.17,47,91,942.51/-. The works in question were to be executed within a period of fifteen months commencing from the seventh day of the issuance of the FOA dated 01.02.2012.
6. On 03.02.2012, GAIL handed over the site in question to Armtech. Thereafter, on 28.03.2012, GAIL issued a Letter of Acceptance (LOA) awarding the Contract for executing the works in question to Armtech. The LOA issued by GAIL also included the Schedule of Rates and the description of the works to be performed by Armtech. Thereafter, on 01.05.2012, the parties entered into a formal agreement (hereafter `the Contract').
7. In terms of the Contract entered into between the parties, Armtech furnished a Bank Guarantee dated 28.04.2012 for a sum of Rs.1,74,79,200/-. The stipulated date for completion of the works was 07.05.2013. However, execution of the works was delayed.
8. Armtech sent a letter dated 25.04.2013 to GAIL seeking extension of nine months' time for completion of the works in question. This request of Armtech was acceded to and by a letter dated 06.05.2013, GAIL provisionally extended the time for completion of the Contract till 06.06.2013. Similarly, further extensions were sought by Armtech and the same were granted by GAIL from time to time. GAIL granted the last extension by its letter dated 19.12.2015 extending the terms of the Contract upto 20.02.2016.
9. Since the work was not completed by Armtech within the extended perio
The court reaffirmed the need for parties to substantiate claims with primary evidence in arbitration proceedings while respecting the arbitrator's discretion unless a clear patent illegality is prov....
The Arbitral Tribunal's decision to award refunds related to price reductions and bank charges was upheld, demonstrating the limited grounds for court interference under the Arbitration and Conciliat....
The termination of a contract can be deemed wrongful if it is primarily due to the actions of the party seeking termination and if the party fails to provide essential documentation or withholds paym....
The main legal point established in the judgment is that the decision of the arbitral Tribunal is entitled to substantial discretion in awarding interest, and the court does not sit as the first appe....
The issuance of a No Claim Certificate under coercion does not negate a party's claims, and contractual requirements for communication in risk transfer are mandatory.
The No Claim Certificate was invalid due to coercion, allowing the party to assert claims under the contract notwithstanding the issuance of such certificate.
The court upheld the validity of the arbitration agreement while emphasizing the necessity of clear evidence for quantifying damages, ruling that claims for compound interest were not accounted for i....
In terms of Section 21 of the A&C Act, the arbitral proceedings commence on the date of receipt of notice invoking the arbitration agreement.
Point of law: In terms of Section 21 of the A&C Act, the arbitral proceedings commence on the date of receipt of notice invoking the arbitration agreement.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.