SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img



IN THE HIGH COURT OF DELHI
Vibhu Bakhru, J.
Armtech (India) Limited - Appellant
Versus
Gail (India) Limited - Respondent
O.M.P. (COMM) 20 of 2020 and O.M.P. (COMM) 33 of 2020 and IA No. 779 of 2020
Decided On : 04-07-2022




The court reaffirmed the need for parties to substantiate claims with primary evidence in arbitration proceedings while respecting the arbitrator's discretion unless a clear patent illegality is proven.

Headnote:(A) Arbitration & Conciliation Act, 1996 - Section 34 - Impugned award dated 24.09.2019 contesting claims over a construction contract between parties - The tribunal found both parties partly responsible for delays but attributed final delay to one party and allowed certain monetary claims while dismissing counter-claims - Court declined to overturn tribunal’s findings without evidence of patent illegality. (Paras 16, 24, 28, 29)

(B) Claims and counterclaims adjudication - Parties must substantiate claims based on primary evidence; the tribunal's discretion must align with factual findings to prevent legal inconsistencies. (Paras 20, 30, 39)

Facts of the case:
The disputes arose over a construction project contract which faced delays, resulting in claims by one party for unpaid bills and penalties, while the counterparty justified delays citing the other’s inaction.

Findings of Court:
The court determined that the impugned award upheld the tribunal's discretion in findings despite some inconsistencies; it rejected claims that lacked substantiation.

Issues: The court examined the extent of delay attributed to each party and questioned the relevance of evidence provided for claims and counterclaims.

Ratio Decidendi: The tribunal's evaluations were deemed rational and not perverse, emphasizing onus of proof for claims; court affirmed that they would not interfere lightly in arbitration decisions unless a clear error emerges.

Result: Armtech's claims accepted to a limited extent; GAIL's claims dismissed.

Table of Content
1. overview of disputes and contract execution (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8 , 9 , 10 , 11)
2. invocation of arbitration by armtech (Para 12 , 13)
3. claims and counterclaims summary (Para 14 , 15 , 16)
4. tribunal's observations on claims (Para 17 , 18 , 19)
5. discussion on claim no.3 (Para 20 , 21 , 22 , 23 , 24)
6. contested issues on delay and prs (Para 25 , 26 , 27)
7. analysis of tribunal's conclusions on delays (Para 28 , 29 , 30 , 31 , 32)
8. judicial review limits under a&c act (Para 33)
9. findings on gail's counterclaims (Para 35 , 39 , 40)
10. counterclaims related to execution of works (Para 41 , 42 , 43)
11. claims rejected on lack of evidence (Para 44 , 50 , 51 , 52 , 53)
12. interest claims and tribunal's discretion (Para 54 , 55 , 56 , 57 , 58 , 59 , 60 , 61)
13. final order on claim adjustment (Para 63)
14. conclusion of the judgments (Para 64)

JUDGMENT

Vibhu Bakhru, J.

1. The aforesaid petitions are cross petitions under Section 34 of the Arbitration & Conciliation Act, 1996 (hereafter the `A&C Act') impugning the Arbitral Award dated 24.09.2019 (hereafter the `impugned award') rendered by an Arbitral Tribunal constituted of Justice (Retd.) V.K. Gupta as the Sole Arbitrator (hereafter the `Arbitral Tribunal').

2. The impugned award was rendered in the context of the disputes that have arisen between the parties in connection with an Agreement dated 01.05.2012, whereby Armtech (India) Limited [petitioner in OMP(COMM) No.20/2020 - hereafter referred to as `Armtech'] had agreed to execute the works relating to the "External Development and External Services for 100 Type B and 20 Type D Houses at Gain Gaon, Dibiyapur, Auraiya, Uttar Pradesh".

3. GAIL (India) Limited [petitioner in OMP(COMM) No.33/2020 - hereafter referred to as `GAIL'], is a Government of India undertaking, inter alia, engaged in the business of distribution of natural gas, liquid hydrocarbons, LPG, manufacturing of petrochemicals etc. One of GAIL's manufacturing unit is located at Gail Gaon, Dibiyapur, District Auraiya, Uttar Pradesh.

4. GAIL issued a tender [bearing Tender No. GAIL/PA11/35611/3300043656/SKG (E-bid No.8000003712] inviting bids for executing the works of external development and external services for 100 Type B and 20 Type D houses at Gail Gaon.

5. Pursuant to the aforesaid tender, Armtech submitted its bid. Armtech was declared as the successful bidder and accordingly GAIL issued a Fax of Acceptance (FOA) dated 01.02.2012. In terms of the FOA, the estimated value of the Contract was fixed at Rs.17,47,91,942.51/-. The works in question were to be executed within a period of fifteen months commencing from the seventh day of the issuance of the FOA dated 01.02.2012.

6. On 03.02.2012, GAIL handed over the site in question to Armtech. Thereafter, on 28.03.2012, GAIL issued a Letter of Acceptance (LOA) awarding the Contract for executing the works in question to Armtech. The LOA issued by GAIL also included the Schedule of Rates and the description of the works to be performed by Armtech. Thereafter, on 01.05.2012, the parties entered into a formal agreement (hereafter `the Contract').

7. In terms of the Contract entered into between the parties, Armtech furnished a Bank Guarantee dated 28.04.2012 for a sum of Rs.1,74,79,200/-. The stipulated date for completion of the works was 07.05.2013. However, execution of the works was delayed.

8. Armtech sent a letter dated 25.04.2013 to GAIL seeking extension of nine months' time for completion of the works in question. This request of Armtech was acceded to and by a letter dated 06.05.2013, GAIL provisionally extended the time for completion of the Contract till 06.06.2013. Similarly, further extensions were sought by Armtech and the same were granted by GAIL from time to time. GAIL granted the last extension by its letter dated 19.12.2015 extending the terms of the Contract upto 20.02.2016.

9. Since the work was not completed by Armtech within the extended perio

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top