SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2022 Supreme(Del) 994

IN THE HIGH COURT OF DELHI AT NEW DELHI
Vibhu Bakhru, J.
Shailendra Paul - Appellant
Versus
Mukesh Aggarwal - Respondent
O.M.P. 3/2020
Decided On : 18-05-2022

Advocates appeared:
Mr. P.S. Bindra, Sr. Adv. with Mr. Dhruv Madan, Advocates, for the Petitioner; Mr. Sushant Kumar & Ms. Shikha Singh, Advocates, for the Respondent

The court held that the Arbitral Tribunal erred in its finding that the version of the ATS (Agreement to Sell dated 14.11.2011) as relied upon by the petitioner was fabricated, and also erred in its conclusion that the petitioner was in possession of the Property prior to July 2012.

Headnote:

ARBITRATION - AWARD - CHALLENGE - GROUNDS - FABRICATION OF DOCUMENT - CONSIDERATION FOR SALE OF PROPERTY - VERSION OF ATS RELIED UPON BY RESPONDENT - ADMISSION BY RESPONDENT IN REPLY TO PETITION FILED BY PETITIONER - NO EXPLANATION OFFERED - INFERENCE DRAWN BY ARBITRAL TRIBUNAL THAT ATS RELIED UPON BY PETITIONER WAS FABRICATED - MANIFESTLY ERRONEOUS - NO GROUNDS TO CONCLUDE THAT AGREED CONSIDERATION OF RS. 2.85 CRORES, AS MENTIONED IN THE ATS RELIED UPON BY RESPONDENT, WAS GENUINE - POSSESSION OF PROPERTY - CONTROVERSY - ARBITRAL TRIBUNAL'S CONCLUSION THAT PETITIONER MUST HAVE BEEN IN POSSESSION OF PROPERTY PRIOR TO JULY 2012 - BASED ON PREMISES THAT PETITIONER, BEING A LAWYER, WOULD NOT HAVE PERMITTED OR TOLERATED RESPONDENT HANDING OVER POSSESSION OF SECOND FLOOR TO THIRD PARTY WITHOUT RECEIVING POSSESSION OF REMAINING PROPERTY - RESPONDENT'S CASE IN PROCEEDINGS BEFORE COURT THAT PETITIONER WAS NEVER IN POSSESSION AND RESPONDENT HAD CONTINUED TO BE IN POSSESSION FROM 31.03.2012 TILL 16.12.2015 - CONCLUSION OF ARBITRAL TRIBUNAL MANIFESTLY ERRONEOUS - CLAIM FOR BALANCE CONSIDERATION OF RS. 1,90,00,000/- AND INTEREST THEREON - REJECTED BY ARBITRAL TRIBUNAL ON GROUND THAT CLAIMS WERE BARRED BY LIMITATION - CONCLUSION MANIFESTLY ERRONEOUS - TRANSACTION FOR SALE OF SECOND FLOOR IN FAVOUR OF SHARAD BHANSLI NOT CLOSED - PETITIONER'S RIGHT TO CLAIM ENTIRE CONSIDERATION IN TERMS OF COLLABORATION AGREEMENT - CANNOT BE STATED TO BE BARRED BY LIMITATION - DAMAGES FOR INCOMPLETE WORK - REJECTED BY ARBITRAL TRIBUNAL ON GROUND THAT POSSESSION OF PROPERTY WAS HANDED OVER TO PETITIONER PRIOR TO 25.07.2012 - CONCLUSION MANIFESTLY ERRONEOUS - LIQUIDATED DAMAGES - QUANTIFIED BY ARBITRAL TRIBUNAL AT RS. 6,00,000 - CONCLUSION PATENTLY ERRONEOUS AS IT RESTS ON ASSUMPTION THAT PETITIONER WAS HANDED POSSESSION OF PROPERTY PRIOR TO 25.07.2012 - CLAIM FOR ELECTRICITY BILLS AND OTHER CHARGES SUCH AS HOUSE TAX, WATER CHARGES, GROUND RENT ETC. - REJECTED BY ARBITRAL TRIBUNAL ON GROUND THAT PETITIONER WAS HANDED OVER POSSESSION OF PROPERTY ON 25.07.2012 - CONCLUSION REQUIRED TO BE SET ASIDE - ARBITRAL TRIBUNAL'S DECISION REGARDING PETITIONER'S CLAIM FOR ELECTRICITY (CLAIM NO.5A), IS ALSO LIABLE TO BE SET ASIDE - CLAIM FOR HOUSE TAX AND OTHER LIABILITIES - ARBITRAL TRIBUNAL FOUND THAT INSUFFICIENT DETAILS WERE PROVIDED AND HELD THAT A BLANKET ORDER, AS SOUGHT BY THE PETITIONER, COULD NOT BE GRANTED - NO INFIRMITY WITH THE SAID CONCLUSION - COST OF LITIGATION - REJECTED BY ARBITRAL TRIBUNAL AND FOUND THAT BOTH THE PARTIES HAD TAKEN INCONSISTENT STANDS AND MADE INCORRECT STATEMENTS BEFORE THE ARBITRAL TRIBUNAL AND THEREFORE, WERE NOT ENTITLED TO ANY COSTS - NO INFIRMITY WITH THE SAID CONCLUSION AS WELL - IMPUGNED AWARD SET ASIDE TO THE EXTENT IT REJECTS THE PETITIONER'S CLAIM FOR BALANCE CONSIDERATION AND INTEREST (CLAIM NOS. 1 AND 2) AS WELL CLAIM FOR INCOMPLETE WORK (CLAIM NO.3), AND IN RESPECT OF THE PETITIONER'S CLAIM FOR LIQUIDATED DAMAGES (CLAIM NO.4) AND ELECTRICITY CHARGES (CLAIM NO. 5-A), IS SET ASIDE IN ENTIRETY.

Fact of the Case:

Petitioner filed a petition under Section 34 of the Arbitration and Conciliation Act, 1996 (A&C Act) impugning an arbitral award dated 31.12.2019 (impugned award) rendered by an Arbitral Tribunal comprising of a Sole Arbitrator. The impugned award was rendered in the context of disputes that have arisen between the parties in relation with the Collaboration Agreement dated 24.10.2010 (Collaboration Agreement).

Finding of the Court:

The impugned award to the extent it rejects the petitioner's claim for balance consideration and interest (Claim Nos. 1 and 2) as well claim for incomplete work (Claim no.3), is set aside. The impugned award in respect of the petitioner's claim for liquidated damages (Claim no.4) and electricity charges (Claim no. 5-A), is set aside in entirety.

Issues: Whether the Arbitral Tribunal erred in its finding that the version of the ATS (Agreement to Sell dated 14.11.2011) as relied upon by the petitioner was fabricated, and whether the Arbitral Tribunal erred in its conclusion that the petitioner was in possession of the Property prior to July 2012.

Ratio Decidendi: The Arbitral Tribunal's conclusion that the ATS relied upon by the petitioner was fabricated and the other version relied upon by the respondent that reflected the lower consideration was genuine, is clearly not a plausible view. The respondent had admitted in its reply that the consideration for the sale of Second Floor was in excess of Rs. 4.5 - Rs. 4.6 crores. In this view, the conclusion that the ATS relied upon by the petitioner was fabricated and the other version relied upon by the respondent that reflected the lower consideration was genuine, is clearly not a plausible view.

Final Decision: The impugned award is set aside to the aforesaid extent. The petition is, accordingly, disposed of in the aforesaid terms.

JUDGMENT

Vibhu Bakhru, J. - The petitioner has filed the present petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter 'the A&C Act') impugning an arbitral award dated 31.12.2019 (hereinafter 'the impugned award') rendered by an Arbitral Tribunal comprising of a Sole Arbitrator (hereinafter 'the Arbitral Tribunal').

2. The impugned award was rendered in the context of disputes that have arisen between the parties in relation with the Collaboration Agreement dated 24.10.2010 (hereinafter 'the Collaboration Agreement').

Factual Context

On 13.01.2006, the petitioner purchased the property bearing number F-20, Geetanjali Enclave, New Delhi - 110017. Thereafter, on 24.10.2010, the petitioner and the respondent entered into the Collaboration Agreement, wherein the parties had agreed to demolish the existing structure and reconstruct the building with a basement, ground floor, first floor, second floor, third floor and terrace (hereafter 'the Entire Property') in terms of the quality standards as detailed out in Annexure A of the Collaboration Agreement. Further, the respondent agreed to pay the petitioner a sum of Rs.  1,90,00,000 against the rights of the second floor of the Entire Property (hereinafter 'the Second Floor'). The relevant Clauses of the Collaboration Agreement are set out below:

'That in addition to the Builder incurring the entire costs and expenses, etc. the Builder has agreed to pay a sum of Rs. 1,90,00,000 (Rupees one crore ninety lacs only) to the Owner as the consideration, in the manner detailed in this Agreement, against the rights, in the portion of the property to be transferred in favour of the Builder or its nominee/s on the completion or during the course of construction of the building.

This consideration shall be payable to the Owner at the time the Builder enters into any Agreement to sell the Builder's Allocation to any person(s). Out of the payments so received at this time, the Owner shall receive a sum equivalent to the percentage this consideration bears to the sale consideration of the Builder's Allocation. The balance consideration shall also be received and shared between the Owner and Builder in the same manner.

xxxx xxxx xxxx

That the Builder shall handover the vacant and physical possession of the Owners' allocation at first and only thereafter the builder shall deliver the vacant and physical possession of the Portion falling on its share to the prospective buyer(s) of the Builder's portion.

xxxx xxxx xxxx

That the Builder undertake to complete the proposed building to the satisfaction of the Owner by 31st March 2012 extendable by a grace period of one month, subject to FORCE MAJEURE and further if delay is occasioned for any reason of any act or legislation or restriction, prohibition or restrained imposed by any Statutory Body and or Governmental Authority, no liability shall attach to the Builder.

That in case the Builder fails to complete the construction of the proposed building within the above stipulated period and the completed, vacant, physical possession of the Owner's Allocation is not handed over to the Owner, then the Builder shall be liable to pay liquidated damages to the tune of Rs. 10,000/- (Rupees ten thousand only) per day to the owner.

That In case the building is not completed by the stipulated date or extended period as stated above, then the Owner shall be free to re-enter the Said Property and complete the then remaining work at the cost and expense of the Builder besides recovering liquidated damages as agreed earlier.'

3. Thereafter, on 14.11.2011, the petitioner issued a 'No Objection Certificate' to the respondent. The said certificate was for the purpose of the respondent to enter into an agreement to sell the Second Floor. The petitioner avers that on the same day, the respondent entered into an Agreement to Sell in respect of the Second Floor (hereinafter 'the ATS'), with one Mr Sharad Bhansali, whereby he agreed to sell the Second Floor for

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

AI

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top