SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2022 Supreme(Del) 988

IN THE HIGH COURT OF DELHI AT NEW DELHI
C. Hari Shankar, J.
M/s Garg Builders Through Shri Mohinder Pal Garg - Appellant
Versus
Hindustan Prefab Ltd. & Anr. - Respondents
Original Miscellaneous Petition (I) (COMM.) No. 200, 201, 202 of 2021, I.As. No. 7653-7655, 7656-7658, 7659-7661 of 2021
Decided On : 02-05-2022

Advocates appeared:
Rajshekhar Rao, Advocate, Rahul Malhotra, Advocate, Ankit Jain, Advocate, Varun Nischal, Advocate, Vaibhav Mishra, Advocate, Mukesh Kumar, Advocate, Amol Sharma, Advocate

The Court held that the invocation of the bank guarantees by HPL was in accordance with the terms of the bank guarantees and that there was no case for interdicting invocation of the bank guarantees. The Court also held that the petitioner had not made out a case of egregious fraud, irretrievable injustice, or special equities that would justify interdicting invocation of the bank guarantees.

Headnote:

The Court held that the invocation of the bank guarantees by HPL was in accordance with the terms of the bank guarantees and that there was no case for interdicting invocation of the bank guarantees. The Court also held that the petitioner had not made out a case of egregious fraud, irretrievable injustice, or special equities that would justify interdicting invocation of the bank guarantees.

Fact of the Case:

The petitioner, Garg Builders, had entered into three contracts with HPL for the construction of various projects. As required by the agreements, the petitioner provided HPL with nine bank guarantees totaling Rs. 10,74,98,388/-. Disputes arose between the parties, and the petitioner invoked the arbitration clause in the agreements. While the arbitration proceedings were ongoing, HPL wrote to the bank on 14th June, 2021, seeking to invoke the bank guarantees. The petitioner approached the Court seeking a stay of the invocation of the bank guarantees. The Court had earlier stayed the operation of the letter of invocation dated 14th June, 2021, subject to the petitioner renewing the bank guarantees. On 1st July, 2021, HPL wrote to the bank again, seeking to invoke the bank guarantees. The petitioner filed the present petitions challenging the invocation of the bank guarantees.

Finding of the Court:

The Court held that the invocation of the bank guarantees by HPL was in accordance with the terms of the bank guarantees and that there was no case for interdicting invocation of the bank guarantees. The Court also held that the petitioner had not made out a case of egregious fraud, irretrievable injustice, or special equities that would justify interdicting invocation of the bank guarantees.

Issues: Whether the invocation of the bank guarantees by HPL was in accordance with the terms of the bank guarantees. Whether the petitioner had made out a case of egregious fraud, irretrievable injustice, or special equities that would justify interdicting invocation of the bank guarantees.

Ratio Decidendi: The Court held that the invocation of the bank guarantees by HPL was in accordance with the terms of the bank guarantees and that there was no case for interdicting invocation of the bank guarantees. The Court also held that the petitioner had not made out a case of egregious fraud, irretrievable injustice, or special equities that would justify interdicting invocation of the bank guarantees. The Court noted that the bank guarantees were unconditional and irrevocable and that the only condition for invocation was that HPL had to state that the amount claimed was required to meet the recoveries due or likely to be due from the petitioner. The Court held that HPL had complied with this condition and that the bank was therefore bound to honor the bank guarantees. The Court also held that the petitioner had not made out a case of egregious fraud, irretrievable injustice, or special equities that would justify interdicting invocation of the bank guarantees. The Court noted that the petitioner had not alleged that the bank guarantees were procured by fraud and that the petitioner had not shown that it would suffer irretrievable injustice if the bank guarantees were invoked. The Court also held that the petitioner had not shown that there were any special equities in its favor that would justify interdicting invocation of the bank guarantees.

Final Decision: The Court dismissed all three OMPs.

JUDGMENT

C. Hari Shankar, J. - Hindustan Prefab Limited (HPL) invited tenders from interested bidders for construction activities to be carried out at various locations in the country. With respect to three of the tenders thus floated, the petitioner Garg Builders was the successful bidder.

2. Tenders were awarded to the petitioner, by HPL, for carrying out of construction activities at Ghaziabad, Uttar Pradesh, Raipur, Chhattisgarh and asansol, West Bengal vide Letters of award dated 3rd March, 2016, 9th January, 2017 and 4th august, 2018, followed by agreements dated 21st March, 2016, 25th January, 2017 and 25th September, 2018 respectively.

3. Each of these agreements required the petitioner to provide Bank Guarantees towards security deposit as well as Performance Bank Guarantee (PBGs). Bank Guarantees, as so required, were undisputedly furnished by the petitioner to HPL. all the Bank Guarantees were issued by HDFC Bank Ltd. ('the Bank') which is, accordingly, Respondent 2 in these three petitions.

4. Disputes arose between the petitioner and HPL in respect of all these three contracts. The contracts provided for reference of the disputes to arbitration. accordingly, after following the pre-arbitral regimen stipulated in that regard in the individual agreements, the petitioner moved this Court by way of arb. P 518 of 2021, arb. P 473 of 2021 and arb. P P47 of 2020, respectively.

5. Prior to filing arb. P 518 of 2021, arb. P 473 of 2021 and arb. P 47 of 2020, however, the petitioner moved the captioned three OMPs, under Section 9 of the arbitration and Conciliation act, 1996 ('the 1996 act'), seeking pre-arbitral interim reliefs.

6. The relief sought in these three cases is identical. In each of these cases, the petitioner has averred that HPL had written to the Bank on 1st July, 2021, invoking the Bank Guarantees furnished by the petitioner, and calling upon the Bank to credit the amount secured by the Bank Guarantees into HPL's account. The petitioner has sought a restraint against such invocation, pending resolution of the disputes between the petitioner and HPL by arbitration.

7. The petitioner was represented, initially, by Mr. Jayant Mehta, learned Senior Counsel, and later, by Mr. Raj Shekhar Rao, learned Senior Counsel, in these matters, whereas Mr. ankit Jain appeared on behalf of the contesting respondent HPL. They were heard at length. The Bank was represented by Mr. amol Sharma, who did not choose to advance any argument, as the Bank has no stake in the matter.

8. I proceed to dispose of the captioned OMPs by the present judgment. The relevant facts, and prevailing considerations, being the same in all the three OMPs, they are dealt with together.

Facts

9. The details of the contracts in these three OMPs may be tabulated as under:

OMP No.

Date of Contract

Location of work

200 of 2021

25th January, 2017

Raipur

201 of 2021

25th September, 2018

asansol

202 of 2021

21st March, 2016

Ghaziabad

Other specifics of the contracts are of no particular relevance to the determination of the issue in controversy; ergo, reference thereto is eschewed.

10. Nine Bank Guarantees, provided by the petitioner as required by the aforenoted three contracts, form subject matter of these three petitions. The petitioner also provided four Bank Guarantees towards security deposit, the details of which may be tabulated thus:

BG No.

Dated

amount (Rs. )

Purpose

OMP (I) (Comm) 200/2021

003GT02163520012

17.12.2016

3243000/-

Security Deposit

003GT02192540009

11.09.2019

2974000/-

Security Deposit

003GT02182790007

06.10.2018

7500000/-

Security Deposit

003GT02173030030

30.10.2017

3243000/-

Security Deposit

OMP (I) (Comm) 201/2021

003GT02182190021

07.08.2018

28773504/-

Performance

OMP (I) (Comm) 202/2021

003GT02160760022

16.03.2016

15172278/

                                            Click Here to Read the rest of this document
                                            1
                                            2
                                            3
                                            4
                                            5
                                            6
                                            7
                                            8
                                            9
                                            10
                                            11
                                            SupremeToday Portrait Ad
                                            supreme today icon
                                            logo-black

                                            An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

                                            Please visit our Training & Support
                                            Center or Contact Us for assistance

                                            qr

                                            Scan Me!

                                            India’s Legal research and Law Firm App, Download now!

                                            For Daily Legal Updates, Join us on :

                                            whatsapp-icon Back to top