IN THE HIGH COURT OF DELHI AT NEW DELHI
C. Hari Shankar, J.
M/s Garg Builders & Ors. - Appellants
Versus
Hindustan Prefab Limited & Ors. - Respondents
O.M.P.(I) (Comm.) 200 of 2021 and I.As. 7653-55 of 2021
Decided On : 02-05-2022
The Court held that the invocation of the bank guarantees by HPL was in accordance with the terms of the bank guarantees and that there was no egregious fraud, irretrievable injustice, or special equities that would justify interdicting the invocation. The Court also held that the petitioner's contention that HPL owed it amounts in excess of the amount covered by the bank guarantees was irrelevant to the issue at hand and that any amounts owed by HPL to the petitioner would have to form the subject matter of resolution by arbitral proceedings.
Fact of the Case:
The petitioner, Garg Builders, had entered into three contracts with HPL for the construction of various projects. As required by the agreements, the petitioner provided HPL with nine bank guarantees totaling ? 20 crores. Disputes arose between the parties, and the petitioner initiated arbitration proceedings. Prior to the arbitration, the petitioner filed three petitions under Section 9 of the Arbitration and Conciliation Act, 1996, seeking a stay on the invocation of the bank guarantees by HPL.
Finding of the Court:
The Court found that the invocation of the bank guarantees by HPL was in accordance with the terms of the bank guarantees. The Court also found that there was no egregious fraud, irretrievable injustice, or special equities that would justify interdicting the invocation. The Court further held that the petitioner's contention that HPL owed it amounts in excess of the amount covered by the bank guarantees was irrelevant to the issue at hand and that any amounts owed by HPL to the petitioner would have to form the subject matter of resolution by arbitral proceedings.
Issues: 1. Whether the invocation of the bank guarantees by HPL was in accordance with the terms of the bank guarantees? 2. Whether there was egregious fraud, irretrievable injustice, or special equities that would justify interdicting the invocation? 3. Whether the petitioner's contention that HPL owed it amounts in excess of the amount covered by the bank guarantees was relevant to the issue at hand?
Ratio Decidendi: 1. The Court held that the invocation of the bank guarantees by HPL was in accordance with the terms of the bank guarantees because the bank guarantees required HPL to merely state that the amount claimed was required to meet the recoveries due or likely to be due from the petitioner, and HPL had made such a statement in its letter of invocation. 2. The Court held that there was no egregious fraud, irretrievable injustice, or special equities that would justify interdicting the invocation because the petitioner had not pleaded egregious fraud, the petitioner's contention of irretrievable injustice was based on the precarious financial condition of HPL which was not supported by the evidence, and the petitioner had not established any special equities. 3. The Court held that the petitioner's contention that HPL owed it amounts in excess of the amount covered by the bank guarantees was irrelevant to the issue at hand because the issue was whether the invocation of the bank guarantees was justified, not whether HPL owed the petitioner any money.
Final Decision: The Court dismissed all three petitions filed by the petitioner.
JUDGMENT
1. Hindustan Prefab Limited (HPL) invited tenders from interested bidders for construction activities to be carried out at various locations in the country. With respect to three of the tenders thus floated, the petitioner Garg Builders was the successful bidder.
2. Tenders were awarded to the petitioner, by HPL, for carrying out of construction activities at Ghaziabad, Uttar Pradesh, Raipur, Chhattisgarh and Asansol, West Bengal vide Letters of Award dated 3rd March, 2016, 9th January, 2017 and 4th August, 2018, followed by agreements dated 21st March, 2016, 25th January, 2017 and 25th September, 2018 respectively.
3. Each of these Agreements required the petitioner to provide Bank Guarantees towards security deposit as well as Performance Bank Guarantee (PBGs). Bank Guarantees, as so required, were undisputedly furnished by the petitioner to HPL. All the Bank Guarantees were issued by HDFC Bank Ltd. ('the Bank') which is, accordingly, Respondent 2 in these three petitions.
4. Disputes arose between the petitioner and HPL in respect of all these three contracts. The contracts provided for reference of the disputes to arbitration. Accordingly, after following the pre-arbitral regimen stipulated in that regard in the individual agreements, the petitioner moved this Court by way of Arb. P 518 of 2021, Arb. P 473 of 2021 and Arb. P P47 of 2020, respectively.
5. Prior to filing Arb. P 518 of 2021, Arb. P 473 of 2021 and Arb. P 47 of 2020, however, the petitioner moved the captioned three OMPs, under Section 9 of the Arbitration and Conciliation Act, 1996 ('the 1996 Act'), seeking pre-arbitral interim reliefs.
6. The relief sought in these three cases is identical. In each of these cases, the petitioner has averred that HPL had written to the Bank on 1st July, 2021, invoking the Bank Guarantees furnished by the petitioner, and calling upon the Bank to credit the amount secured by the Bank Guarantees into HPL's account. The petitioner has sought a restraint against such invocation, pending resolution of the disputes between the petitioner and HPL by arbitration.
7. The petitioner was represented, initially, by Mr. Jayant Mehta, learned Senior Counsel, and later, by Mr. Raj Shekhar Rao, learned Senior Counsel, in these matters, whereas Mr. Ankit Jain appeared on behalf of the contesting respondent HPL. They were heard at length. The Bank was represented by Mr. Amol Sharma, who did not choose to advance any argument, as the Bank has no stake in the matter.
8. I proceed to dispose of the captioned OMPs by the present judgment. The relevant facts, and prevailing considerations, being the same in all the three OMPs, they are dealt with together.
Facts
9. The details of the contracts in these three OMPs may be tabulated as under:
| OMP No. | Date of Contract | Location of work |
| 200 of 2021 | 25th January, 2017 | Raipur |
| 201 of 2021 | 25th September, 2018 | Asansol |
| 202 of 2021 | 21st March, 2016 | Ghaziabad |
Other specifics of the contracts are of no particular relevance to the determination of the issue in controversy; ergo, reference thereto is eschewed.
10. Nine Bank Guarantees, provided by the petitioner as required by the aforenoted three contracts, form subject matter of these three petitions. The petitioner also provided four Bank Guarantees towards security deposit, the details of which may be tabulated thus:
| BG No. | Dated | Amount (Rs.) | Purpose |
| OMP (I) (Comm) 200/2021 | |||
| 003GT0216 3520012 | 17.12.16 | 3243000/- | Security Deposit |
| 003GT0219 2540009 | 11.09.19 | 2974000/- | Security Deposit |
| 003GT0218 2790007 | 06.10.18 | 7500000/- | Security Deposit |
| 003GT0217 3030030 | 30.10.17 | 3243000/- | Security Deposit |
| OMP (I) (Comm) 201/2021 | |||
| 003GT0218 2190021 | 07.08.18 | 28773504/- | Performance |
| OMP (I) (Comm) 202/2021 | |||
| 003GT0216 0760022 | 16.03.16 | 15172278/- | - |
| 003GT0217 16700 | |||
BSES Ltd. v. Fenner India Ltd.
Hindustan Steelworks Construction Ltd. v. Tarapore & Co
Svenska Handelsbanken v. Indian Charge Chrome
United Commercial Bank v. Bank of India
AI
The invocation of an unconditional bank guarantee can only be interdicted in exceptional circumstances, such as egregious fraud, irretrievable injustice, or special equities.
The Court held that the invocation of the bank guarantees by HPL was in accordance with the terms of the bank guarantees and that there was no case for interdicting invocation of the bank guarantees.....
A confirmed Bank Guarantee/irrevocable Letter of Credit cannot be interfered with unless there is established fraud or irretrievable injustice involved in case.
Bank guarantees are independent and unconditional contracts, and courts should refrain from interfering with their invocation unless exceptional circumstances such as fraud or irretrievable injury ar....
The court emphasized the independence and unconditional nature of bank guarantees, while recognizing exceptions such as fraud, irretrievable injustice, or special equities.
Unconditional bank guarantees may only be reviewed for egregious fraud or irretrievable injustice; disputes over contract performance must be resolved through arbitration.
Bank guarantees can be invoked regardless of disputes, unless fraud or irretrievable harm is clearly established.
The court clarified that injunction against unconditional bank guarantees requires proof of egregious fraud, irretrievable injustice, or special equities, none of which were sufficiently substantiate....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.