IN THE HIGH COURT OF DELHI AT NEW DELHI
YASHWANT VARMA, J.
M/S PACIFIC DEVELOPMENT CORPORATION LIMITED – Petitioner
Versus
DELHI METRO RAIL CORPORATION LTD. – Respondent
ARB. PET. No. 1303 of 2022, I.A. Nos. 19890, 19891, 19892 of 2022, O.M.P. (I) (COMM.) No. 295 of 2022
Decided On : 30-01-2023
Arbitration and Conciliation Act, 1996 – Section 9, 11, 12, 17 – Interim measures –Appointment of arbitrators – Grounds for challenge – Court by means of present order, and with consent of parties proposes to dispose of these two connected petitions been instituted subsequently and seeks constitution of an Arbitral Tribunal in accordance – Record would reflect that on petition preferred learned Judge of Court proceeded – Held, Court further observes that any such application that may be made shall be decided by Arbitral Tribunal uninfluenced by order continuance in interregnum in term of directions framed aforesaid order shall hold field only till such time as Arbitral Tribunal is duly constituted – Court directs petitioner to express and convey its choice with respect to its nominee arbitrator within a period of one week from today – It shall be open to DMRC to nominate its arbitrator from out of panel prepared and maintained by it within a week two appointed arbitrators shall be obliged to indicate Presiding Arbitrator within a period of ten days – Petitions shall stand disposed of.
JUDGMENT :
YASHWANT VARMA, J.
1. The Court by means of the present order, and with the consent of parties, proposes to dispose of these two connected petitions. While O.M.P. (I) (COMM.) No. 295/2022 has been preferred under Section 9 of the Arbitration and Conciliation Act, 1996 [The Act], ARB. PET. No. 1303/2022 came to be instituted subsequently and seeks the constitution of an Arbitral Tribunal in accordance with the provisions of Section 11(4) and (6) of the Act.
2. The record would reflect that on the petition preferred under Section 9, on 03 November 2022 a learned Judge of the Court proceeded to pass the following order:
2. In other words, respondent is not agreeable for appointment of an Arbitrator. She states, reply shall be filed by Tuesday, i.e. November 8, 2022.
3. Till the next date of hearing, status quo with regard to invocation of the bank guarantee, which is the subject matter of the present petition, shall be maintained.
4. List on November 14, 2022.”
It is that order which has continued till these two petitions were taken upon for final disposal today.
3. From the material which has been placed on the record by way of the petition under Section 11, it is manifest that the dispute between the parties emanates from a Lease Agreement dated 04 September 2017. The petitioner appears to have firstly initiated the conciliation process as envisaged under the agreement in terms of its letter of 14 March 2022. Consequent to conciliation proceedings having failed, a conciliation failure report came to be drawn and submitted whereafter the petitioner by its letter of 18 August 2022 called upon the Delhi Metro Rail Corporation [DMRC] for constitution of an Arbitral Tribunal. This was followed by a reminder letter dated 12 September 2022 addressed to the DMRC by the petitioner in reiteration of the said request. It becomes relevant to note that responding to the notice of 18 August 2022, the DMRC by its letter of 15 September 2022 had, while purporting to act in furtherance of clause 11.3 of the Lease Agreement, forwarded a panel of five arbitrators to the petitioner requesting it to nominate one arbitrator who may be then treated to be a constituent of the three-member Arbitral Tribunal which was to enter upon the reference. The petitioner had questioned the aforesaid action of the DMRC asserting that it was entitled to choose an arbitrator out of the entire panel that was maintained by it. It is thereafter that the petition under Section 11 came to be preferred before this Court.
4. The dispute insofar as the aforesaid question is concerned is no longer res integra and stands conclusively settled by the Supreme Court in Voestalpine Schienen GMBH vs. Delhi Metro Rail Corporation Limited, (2017) 4 SCC 665. It becomes pertinent to note that in the said decision while upholding the composition of the panel as drawn by the DMRC and finding that the choice of retired or erstwhile employees of Central Government and Public Sector Undertakings as offered would not be violative of Section 12 of the Act, the Supreme Court had observed as under:
Dhoom Chand Jain vs. Chamanlal Gupta
Voestalpine Schienen GMBH vs. Delhi Metro Rail Corporation Limited
Sub-section (3) of Section 9 provides for restriction of exercise of powers by the Court and it has to decide whether the remedy provided under section 17 is efficacious or not.
Once an Arbitral Tribunal is constituted, Section 9 of the Arbitration Act prohibits further applications for interim relief unless the party shows that the remedy under Section 17 is ineffective.
The court dismissed the petition, stating that the Tribunal had the authority to grant interim measures and that the petitioners had failed to demonstrate that the Section 17 remedy was inefficacious....
Section 9 of the Arbitration and Conciliation Act, 1996 permits interim relief after an arbitral award but before enforcement, irrespective of concurrent execution proceedings.
The court established that while Section 9 allows for court intervention in arbitration matters, it can only do so if the remedy under Section 17 is found to be ineffective, particularly when third p....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.