IN THE HIGH COURT OF DELHI AT NEW DELHI
V. KAMESWAR RAO, J.
VPS Healthcare Private Limited and Another - Decree Holders
Versus
Prabhat Kumar Srivastava and Another - Judgment Debtors
OMP (ENF.) (Comm.) 184 of 2022
Decided On : 01-05-2023
Arbitration - Enforcement of Consent Award - Arbitration and Conciliation Act, 1996 - Section 36 - The consent award dated March 1, 2019 sought enforcement by the decree holders. The award was in relation to the disputes between the parties and the liability imposed by the award dated August 17, 2021. The respondents agreed to defend/contest at their cost all proceedings detailed in Annexure-I of the Deed of Compromise. The respondents were to take all remedies available in law, including but not limited to settling the proceedings on behalf of the petitioner No. 2 by filing appeal/review till the highest Court of appeal. The liability, if any, shall be discharged by the respondents only when the same is confirmed by the highest Court of appeal. The petitioners shall be entitled to recover from the respondents, any amount it is compelled to pay pursuant to the award dated August 17, 2021.
Fact of the Case:
The petitioners sought enforcement of a consent award dated March 1, 2019, in relation to disputes between the parties and the liability imposed by the award dated August 17, 2021. The respondents agreed to defend/contest at their cost all proceedings detailed in Annexure-I of the Deed of Compromise. The liability, if any, shall be discharged by the respondents only when the same is confirmed by the highest Court of appeal.
Finding of the Court:
The Court interpreted the consent award and concluded that the respondents are liable to discharge the liability imposed by the award dated August 17, 2021, only after it is confirmed by the highest Court of appeal. The petition was closed at this stage, and the petitioners were granted the liberty to seek enforcement of the award at a future date if the cause accrues.
Issues: The main issue was the interpretation of paragraph 32(a) of the consent award, which stipulated the obligations of the respondents in relation to the liability imposed by the award dated August 17, 2021.
Ratio Decidendi: The respondents are liable to discharge the liability imposed by the award dated August 17, 2021, only after it is confirmed by the highest Court of appeal. The petitioners shall be entitled to recover from the respondents, any amount it is compelled to pay pursuant to the award dated August 17, 2021.
Final Decision: The petition was closed at this stage, and the petitioners were granted the liberty to seek enforcement of the award at a future date if the cause accrues.
JUDGMENT :
V. Kameswar Rao, J.
This petition has been filed by the decree holders under Section 36 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the ‘Act of 1996’) seeking enforcement of a consent award dated March 01, 2019 by the Arbitral Tribunal, in arbitration bearing Singapore International Arbitration Centre (‘SIAC’, for short) Arbitration No. 093/2017.
2. At the outset, I may narrate a brief factual background of the instant case, as borne out from the petition. Petitioner No. 1 is VPS Healthcare Pvt. Ltd., a part of VPS Healthcare Group and petitioner No. 2 is Medeor Hospitals Pvt. Ltd. (formerly Rockland Hospitals Ltd.), a company wholly owned by petitioner No. 1. The judgment debtors/respondent Nos. 1 and 2 are Mr. Prabhat Kumar Srivastava and Mr. Rishi Kumar Srivastava respectively, who are the erstwhile promoters and shareholders of petitioner No. 2.
3. On August 11, 2015, an agreement was entered into between the erstwhile Rockland Hospitals Limited (‘RHL’, for short) and Ernst and Young India LLP (‘EY’, for short), through a Letter of Engagement (‘LOE’, for short), since RHL had chosen EY to provide professional services with regard to the proposed induction of strategic partners/buyers through sale of significant majority stake in two of its hospitals at Qutub Institutional Area and Dwarka. Thereafter certain disputes arose between the petitioner No. 2 (Medeor/RHL) and EY, resulting in arbitral proceedings before a three-member Arbitral Tribunal constituted as per the rules of the Indian Council of Arbitration (‘ICA’, for short). Subsequently, arbitration bearing No. AC-2085 commenced before the said Tribunal.
4. On June 29, 2016, petitioner No. 1 and the erstwhile promoters of petitioner No. 2 executed a Share Purchase Agreement by virtue of which, petitioner No. 1 purchased/acquired 100% shares in the petitioner No. 2 for a consideration of Rs. 650 crore. The respondents were appointed as the sellers’ representative in their individual capacity and on behalf of other shareholders. On execution of the Share Purchase Agreement, petitioner No. 1 stepped into the shoes of the respondents'/promoters/shareholders/management and became responsible for the management of the day-to-day affairs of the petitioner No. 2 Company. Pursuant to the takeover by petitioner No. 1, certain disputes arose between the parties, which resulted in filing of various complaints/arbitrations/litigations.
5. On August 12, 2017, a notice invoking arbitration was issued, pursuant to which, an Arbitral Tribunal was constituted on October 16, 2017 as per the SIAC Rules. During the pendency of arbitral proceedings, the parties decided to amicably and mutually settle all their disputes and thereby executed a compromise deed dated February 02, 2019. As per the terms of the compromise deed, both the parties are under obligation to withdraw all the complaints/cases filed before various forums/courts/government departments. The respondents are also under the obligation to contest/defend all the legal matters as recorded in Annexure - I of the compromise deed at its own cost, thereby protecting the interest of the petitioners herein. The Arbitral Tribunal accordingly passed the final consent award dated March 01, 2019 in terms of the said compromise deed dated February 02, 2019. Paragraph 32 (a) of the consent award states as under:—
Bihar SEB v. Green Rubber Industries
Transmission Corporation of Andhra Pradesh Limited v. GMR Vemagiri Power Generation Limited
Bangalore Electricity Supply Company Limited v. ES Solar Power Private Limited
Eureka Forbes Limited v. Allahabad Bank
Comed Chemicals Limited v. C.N. Ramchand
Citibank, N.A. v. TLC Marketing Plc
Khardah Co. Limited v. Raymon and Co. India (P) Ltd.
Virjee Daya & Co. v. Ramakrishna Rice & Oil Mills
Central Bank of India Ltd. v. Hartford Fire Insurance Co. Ltd.
The respondents are liable to discharge the liability imposed by the award dated August 17, 2021, only after it is confirmed by the highest Court of appeal.
The enforcement of indemnity obligations under a consent award occurs immediately upon crystallization of liability, not pending appellate confirmation.
The court upheld the arbitral award, confirming that the petitioner breached the contract and consent orders, making them liable for damages.
Consent awards are enforceable under the New York Convention and are not contrary to the public policy of India.
No arbitration clause relating to dispute between the parties in not appointing appellant as stockist and claim of compensation towards loss of goodwill and reputation. High Court erred in proceeding....
An appeal against a consent decree is barred under Section 96(3) of the CPC; aggrieved parties must contest the decree's validity in the same court that issued it.
A bald plea of fraud, coercion, duress, or undue influence is not enough to undo settlement agreements.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.