IN THE HIGH COURT OF DELHI AT NEW DELHI
Vibhu Bakhru, Amit Mahajan, JJ.
M/s Jop International Limited – Appellant
Versus
M/s Multifold Group Contractor And Engineers – Respondent
FAO (COMM) 52 of 2023 and CM Nos. 9523 of 2023 & 9524 of 2023
Decided On : 17-05-2023
Arbitration and Conciliation Act - Construction Dispute - Section 34
Fact of the Case:
The respondent filed an application under Section 34 of the Arbitration and Conciliation Act, 1996, seeking to set aside an arbitral award that rejected several claims related to a construction project. The Commercial Court allowed the respondent's claims, which the appellant challenged.
Finding of the Court:
The Commercial Court concluded that the arbitral award was patently illegal and allowed the respondent's claims. The appellant was aggrieved by the decision.
Issues: The main issue was whether the Commercial Court had the jurisdiction to modify the arbitral award and allow the respondent's claims under Section 34 of the Arbitration and Conciliation Act.
Ratio Decidendi: The court held that its jurisdiction under Section 34 of the Arbitration and Conciliation Act is limited to setting aside the arbitral award if specific grounds are established. It cannot modify the award or allow claims, as that would amount to rewriting the award, which is impermissible.
Final Decision: The court set aside the portion of the impugned order that allowed the respondent's claims.
JUDGMENT
Vibhu Bakhru, J.(Oral)
1. The appellant has filed the present appeal under Section 37(1)(c) of the Arbitration and Conciliation Act, 1996 (hereafter `the A&C Act') impugning a judgement dated 18.11.2022 (hereafter `the impugned judgement') passed by the learned Commercial Court in an application preferred by the respondent under Section 34 of the A&C Act.
2. The respondent had filed the said application seeking setting aside of the arbitral award dated 01.09.2018 (hereafter `the impugned award'). The impugned award was rendered in the context of the disputes that had arisen between the parties in connection with their agreement dated 22.03.2014 (hereafter `the Agreement'). In terms of the Agreement, the respondent had agreed to carry out construction and development of works in a project named `JOP Palms', located at Sector 28, Rohtak, Haryana (hereafter `the project').
3. The disputes were referred to an arbitral tribunal comprising of a sole arbitrator (hereafter `the Arbitral Tribunal'). The respondent had, inter alia, claimed a sum of Rs.17,04,755/- (Claim no.1). The said amount comprised of a sum of Rs.1,09,879/- due against the Running Account Bills and an amount of Rs.15,94,876/- on account of refundable security deposit. The Arbitral Tribunal awarded a sum of Rs.15,81,705/- being the security deposit that was retained by the appellant. Insofar as claim for payment due under the 39th Running Bill is concerned, the Arbitral Tribunal rejected the same on the ground that the respondent (claimant in the impugned award) had failed to prove the acknowledgement of the said bill. The balance claims (Claim nos.2 to 6), relating to miscellaneous civil work, were disallowed. Claim nos.7 and 8, relating to interest, were partly allowed to the extent of the amount awarded under Claim no.1.
4. Claim nos.2 to 6, as summarized in the impugned judgement, are set out below:
"Claim No.2
Payment for Miscellaneous civil work
3BHK: Covered Area 98400 Sq.ft. @ Rs. 8/- Rs.7,87,200/-
Balcony Area 15346 Sq.ft. @ 4/- Rs. 61,387/-
Total
Rs.8,48,587/-
Claim No.3
Loss due to delay in casting of slab at 2BHK Casted on 20.03.2016 Rs.2,00,000/-.
Claim No.4
Casting of columns at 2BHK & 3 BHK Manually/Hand mixing Rs.10,22,230/-.
Claim No.5
2BHK pending column quantity at basement Rs.2,38,122/-.
Claim No.6
Extra payment made to rigger for setting of pipeline from the concrete pump to the point of casting Rs. 1,38,000/-."
5. The Arbitral Tribunal had rejected the said claims, principally, on the ground that the claimant (respondent) had failed to establish the same. The Arbitral Tribunal held that the respondent had failed to show any specific order or any specific bill in respect of the amounts claimed under Claim nos.2 to 6. The Arbitral Tribunal also rejected the emails relied upon by the respondent on the ground that such electronic evidence could not be relied upon in the absence of a necessary affidavit under Section 65B of the Indian Evidence Act, 1872. The relevant extract of the impugned award is set out below:
"while claim no 2 to 6 which are concerned with the payment for misc civil work carried out at the site, Loss due to delay in casting of slab and column at 2 BHK, pending column quantity at basement and extra payment made to rigger by the claimant, the claimant has explained the same in a detailed manner in his claim and also explained the same during the course of argument and succeed in proving the calculation so made by him for the purpose of the claim that the said work has been carried out by him at the site however the conducting of the said work is duly admitted by the respondent, but on the pretext that the same was a part of the work order and without these work the project cannot be consider as completed, even otherwise the claimant has failed to show any specific work order or any specific bill so raised by him in respect to the said alleged misc works etc as mentioned in claim 2 to 6, however it is a settled principal of commercia
McDermott International Inc. v. Burn Standard Co. Ltd. & Ors.
The court clarified that its jurisdiction under Section 34 of the Arbitration and Conciliation Act is limited to setting aside the arbitral award based on specific grounds and does not extend to modi....
(1) Appeal against modified arbitral award – Merits of award are only to be gone into, if award is demonstrated to be contrary to public policy of India.(2) Arbitral proceedings are per se not compar....
The judgment emphasizes the limited grounds for interference with arbitral awards under Section 34 of the Arbitration and Conciliation Act, highlighting the need for restraint by courts while examini....
A Section 34 court cannot modify an arbitral award, as established by the Supreme Court in Hakeem, which overruled previous case law allowing such modifications.
The main legal point established is that under Section 34 of the Arbitration and Conciliation Act, 1996, the Court can partially or wholly set aside an Arbitral Award if the claims are separable and ....
The main legal point established in the judgment is that the court's power under Section 34 of the Arbitration and Conciliation Act, 1996 is limited to setting aside an award and does not extend to m....
(1) While exercising power under Section 34 of A & C Act, arbitral award can only be confirmed or set aside, but not modified.(2) Award passed by Arbitral Tribunal cannot be set aside on the ground t....
The court emphasized the limited grounds for setting aside an arbitral award under Section 34 of the A&C Act and the lack of power to modify, revise, or vary the terms of an award under this section.
An arbitral award must be supported by reasoning and evidence; a Minority Award is merely an opinion and cannot prevail over a Majority Award; the Court cannot modify an arbitral award.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.