IN THE HIGH COURT OF GAUHATI, ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH
MICHAEL ZOTHANKHUMA, J.
M/s GSR Ventures Pvt. Ltd. – Petitioner
Versus
The State of Mizoram and Others – Respondents
Arbitration Appeal No. 3 of 2023
Decided On : 21-05-2024
Arbitration - Challenge to Partial Arbitral Award - Arbitration and Conciliation Act, 1996 - Section 34 - 32 and 34 of the 1996 Act - Severability of Arbitral Award
Fact of the Case:
The appellant, awarded a construction contract, had claims allowed and rejected by the Arbitrator. The appellant challenged the rejection under Section 34 of the Arbitration and Conciliation Act, 1996. The District Judge dismissed the challenge on the ground that the arbitral award had been executed.
Finding of the Court:
The Court found that the rejected claims were independent and severable from the allowed claims. It held that the District Judge erred in not considering whether the rejected claims were severable and independent. The Court remanded the case to the District Judge for a decision on the challenge to the rejected claims.
Issues: The issues revolved around the challenge to a part of the Arbitral Award, the severability of the claims, and the District Judge's failure to consider the independence of the rejected claims.
Ratio Decidendi: The Court held that under Section 34 of the 1996 Act, the Principal Civil Court can partially or wholly set aside an Arbitral Award, provided the claims are separable and independent. It emphasized the need for the District Judge to consider the severability of the rejected claims and make a decision on the challenge under Section 34.
Final Decision: The appeal was allowed, and the case was remanded back to the District Judge for a decision on the challenge to the rejected claims, considering their severability and independence.
JUDGMENT :
MICHAEL ZOTHANKHUMA, J.
1. Heard Ms. S. Bhattacharjee, learned counsel for the appellant. Also heard Mrs. Mary L. Khiangte, learned Government Advocate, appearing for all the respondents.
2. The appellant is aggrieved by the Order dated 27.09.2023 passed by the District Judge, Aizawl dismissing Arbitration Case No. 1/2023 as infructuous. The Arbitrator in Arbitration Proceeding No. 4/2020 had allowed several of the claims of the appellant while rejecting others vide Arbitral Award dated 30.05.2022. The appellant had prayed for execution of the claims that had been allowed by the Arbitrator vide Execution Case No. 15/2023. The same was allowed vide Order dated 11.08.2023. With regard to the claims that had been rejected by the Arbitrator, the appellant challenged the rejection under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as “the 1996 Act”) vide Arbitration Case No. 1/2023. However, the same was dismissed vide order dated 27.09.2023 passed in Arbitration Case No. 1/2023 on the ground that the arbitral award had been executed vide Execution Case No. 15/2023.
3. The genesis of this appeal under Section 37(1)(c) of the 1996 Act is that the appellant had been awarded the contract work for construction of Tawngkolong to Longmasu Road 0.00 kmp-27.50 kmp. The appellant’s contract was terminated by the State respondents. As a dispute arose between the parties in respect of the said contract, an application under Section 11 of the 1996 Act was filed in this Court, vide Case No. Arbitration Petition 4/2019. This Court disposed of Case No. Arbitration Petition 4/2019, vide judgment dated 12.03.2020, appointing a sole Arbitrator to decide the dispute between the parties.
4. The appellant made 10 claims against the respondents, vide the Statement of Claims and the respondents submitted their statement of defence.
5. The case was registered before the Arbitrator as Arbitration Proceeding No. 4/2020. The Arbitration Proceeding No. 4/2020 was disposed of, vide Award dated 30.05.2022, by allowing Claim Nos. 2, 3, 4, 9 and 10 in favour of the petitioner. Claim No. 6 was withdrawn by the petitioner, while the petitioner’s Claim Nos. 1, 5, 7 and 8 were rejected by the Arbitrator.
6. The appellant thereafter filed Execution Case No. 15/2023 in respect of the Award dated 30.05.2022 pertaining to the claims which had been allowed by the Arbitrator. Execution Case No. 15/2023 was disposed of by the District Judge, Aizawl, vide order dated 11.08.2023 in terms of the Arbitrator’s Award dated 30.05.2022.
7. The appellant had also filed an application under Section 34 of the 1996 Act, in respect of Claim Nos. 1, 5, 7 and 8 which had been rejected by the Arbitrator, vide Arbitration Case No. 4/2022 before the District Judge, Aizawl. The District Judge, Aizawl dismissed Arbitration Case No. 4/2022, vide the impugned order dated 27.09.2023, on the ground that the Arbitral Award dated 30.05.2022 arising out of Arbitration Proceeding No. 4/2020 had been executed, vide order dated 11.08.2023 passed in Execution Case No. 15/2023 and as such, the application under Section 34 was found to be infructuous.
8. The appellant’s counsel submits that there was no challenge made to the Arbitral Award dated 30.05.2022 by the State respondents and as such, the appellant was claiming execution of a part of the Arbitral Award passed in arbitration proceeding, pertaining to release of performance guarantee, release of security deposit and cost of arbitration, as had been allowed by the Arbitrator. However, as Claim Nos. 1, 5, 7 and 8 had been rejected by the Arbitrator, the same had been put to challenge by the appellant, vide Arbitration Proceeding No. 4/2020. However, the dismissal of the same by the learned District Judge, Aizawl only on the ground that the execution case had been executed in terms of Award dated 30.05.2022 could not be a ground for dismissing the petitioner’s application made under Section 34. She submits that th
Dyna Technologies Ltd. vs. Crompton Greaves Ltd. (2019) 20 SCC 1
Hindustan Construction Co. Ltd. vs. Governor of Orissa and Others
J.G. Engineers vs. Union of India
J.C. Budhraja vs. Chairman, Orissa Mining Corporation Ltd. and Another
Maharashtra State Electricity Distribution Co. Ltd. vs. Datar Switchgear Ltd. (2018) 3 SCC 133
MMTC Limited vs. Vedanta Limited
McDermott International Inc. vs. Burn Standard Co. Ltd. (2006) 11 SCC 181
MMTC Ltd. Ssangyoung Engg. and Construction Ltd. vs. NHAI
Narayan Niwas and Others vs. Ircon International Ltd. and Others
Saptarishi Hotels Pvt. Ltd. and Others vs. National Institute of Tourism and Hospitality Management
The main legal point established is that under Section 34 of the Arbitration and Conciliation Act, 1996, the Court can partially or wholly set aside an Arbitral Award if the claims are separable and ....
The Court can partially set aside an arbitral Award and has limited scope of interference under Section 34 of the Arbitration and Conciliation Act, 1996. The Court cannot modify an Award but can set ....
The court clarified that its jurisdiction under Section 34 of the Arbitration and Conciliation Act is limited to setting aside the arbitral award based on specific grounds and does not extend to modi....
The court affirmed that judicial intervention in arbitral awards is limited to grounds of public policy or patent illegality, emphasizing respect for the Arbitrator's findings.
The appeal was allowed, reinstating the arbitrator's award which concluded that the termination of the contract was illegal due to failure in fulfilling mutual obligations concerning site availabilit....
The judgment emphasizes the limited grounds for interference with arbitral awards under Section 34 of the Arbitration and Conciliation Act, highlighting the need for restraint by courts while examini....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.