SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2023 Supreme(Del) 5666

IN THE HIGH COURT OF DELHI AT NEW DELHI
Yashwant Varma, Dharmesh Sharma, JJ.
National Projects Constructions Corporation Ltd. (NPCC) - Appellant
Versus
M/s Aac India Pvt. Ltd . - Respondent
FAO (COMM) 140 of 2021
Decided On : 02-11-2023

Advocates appeared:
Mr. Rajat Arora, Ms. Mariya Shahab & Mr. Nibin Louis, Advocates, for the Appellant.

IMPORTANT POINT
The court emphasized the limited grounds for setting aside an arbitral award under Section 34 of the A&C Act and the lack of power to modify, revise, or vary the terms of an award under this section.

Headnote:

Arbitration and Conciliation Act - Setting aside impugned judgment - Section 37 of A&C Act, Section 13(1A) of CC Act - [35.0, 35.1 of GC-14; 48.3, 48.4 and 49 of the GC-22] - The court upheld the arbitral award dated 29 August 2016 in its entirety, setting aside the impugned judgment that partially set aside the award on the aspect of payment of liquidated damages.

Fact of the Case:

The appellant, a Government Enterprise, entered into an agreement with the respondent for a project. The appellant claimed that the respondent breached the contract and delayed its performance, leading to the imposition of liquidated damages. The respondent invoked arbitration, and the Arbitrator partly granted the reliefs claimed by the respondent. The award was challenged by the respondent under Section 34 of the A&C Act, and the learned ADJ partially set aside the award.

Finding of the Court:

The court found that the learned ADJ went beyond the scope of Section 34 of the A&C Act and the decision to modify the award was flawed and unsustainable in law. The court upheld the arbitral award in its entirety, setting aside the impugned judgment that partially set aside the award on the aspect of payment of liquidated damages.

Issues: The issues revolved around the imposition of liquidated damages, the interpretation of contract clauses, and the scope of challenge and interference with an arbitral award under Section 34 of the A&C Act.

Ratio Decidendi: The court held that the learned ADJ misconstrued the contents and import of a letter/correspondence, and the reasoning for modifying the award was flawed. The court emphasized that the jurisdiction of the Court under Section 34 is neither in the nature of an appellate nor a revisional remedy, and an award can be set aside on limited grounds.

Final Decision: The impugned order was set aside, and the award dated 29 August 2016 passed by the Arbitrator was upheld in its entirety. The parties were left to bear their own costs.

JUDGMENT

Dharmesh Sharma, J. - This Judgment shall decide the present appeal preferred by the appellant under Section 37 of the Arbitration and Conciliation Act, 1996[A&C Act] read with Section 13(1A) of the Commercial Courts Act, 2015[CC Act] for setting aside the impugned judgment dated 12 March 2021 passed by learned Additional District Judge-03, South District, Saket Courts, New Delhi[ADJ] in ARBTN No.20824/2016, whereby the learned ADJ chose to partially set aside the award dated 29 August 2016 on the aspect of liquidated damages[LD] to be paid by the appellant to the respondent.

FACTUAL BACKGROUND:

2. The appellant, which is a Government Enterprise under the Ministry of Water Resources and also a company registered under the Companies Act, 1956 consequent to letter of intent[LOI] dated 03 March 2017 entered into an agreement dated 13 March 2007 as Project Management Consultant of the Central Reserve Police Force[CRPF] with the respondent, which was a micro enterprise stated to be having a turnover of less than Rs. 10 Lacs, for installation of Fire Protection System for the Auditorium Block, CRPF Campus, Vasant Kunj, New Delhi. The project was stipulated to be completed within a period of 7 months from the date of issuance of LOI for total contract value of Rs. 90,79,200/-. However, performance got delayed.

3. To cut a long story short, the appellant claimed that the respondent was in breach of its obligations under the contract and delayed its performance by taking about 33 months for completion of work, and therefore, in terms of clause 35.5 of the contract, LD was levied and adjusted against the payment payable to the respondent not only for the abnormal delay but also for causing damage to the reputation of the appellant for the delay caused; and accordingly payment for a sum of Rs. 1,13,97,341/- i.e., 10% of the work cost of the CRPF camp project was withheld. The respondent in terms of clause 52 of the 'General Conditions' of the contract invoked arbitration and accordingly Sh. Suresh Chandra Garg, Ex. General Manager of the appellant was appointed as the Sole Arbitrator to adjudicate upon the disputes between the parties vide appointment/nomination letter dated 17 April 2014. The Arbitrator entered upon the reference, conducted the proceedings, and eventually passed the award dated 29 August 2016.

4. After considering the dispute between the parties in light of various clauses of the contract, the Arbitrator partly granted the reliefs claimed by the claimant/respondent as follows:-

    'Claim No.1:

    The claim for refund of Rs. 9,68,470/- was disallowed after adjusting LD of Rs. 9,17,000/- giving balance of Rs. 51,470/- to the claimant;

    Claim No.2:

    Claim No.2 for an amount of Rs. 4,47,578- towards the balance of security deposit was allowed;

    Claim No.3:

    Claim for unfair profit earned by the respondent by utilizing payments received from CRPF against RA bills of claimant amounting to Rs. 1,78,486/- with interest was declined;

    Claim No.4:

    Direct expenses induced by the respondent towards Pump Operator plus interest besides insurance charges was rejected;

    Claim No.5:

    Claim for escalation charges and interest upon escalation charges was rejected;

    Claim No.6:

    Claim for damages of loss of profits and loss as well as goodwill amounting to Rs. 25,00,000/- was rejected;

    Claim No.7:

    Fair compensation on account of harassment, mental agony and physical harm to the tune of Rs. 5,00,000/- was rejected; and INTEREST:

    Interest was allowed on the claim No.1 @ 6% per annum from the date of appointment of the Arbitrator i.e., 17 April 2014 till the date of Award and it was directed that in case interest is not paid within 60 days, it shall carry interest @ 9% per annum from the date of the Award till payment.'

    5. Simultaneously, the Arbitrator also dealt with the counter claims of the appellant herein and arrived at the following decision:

      (i) Claim for loss of reputation to the respondent/organization to Rs. 1,00,00,000/- was rejected.

      (ii) Claim for damages i

                  Click Here to Read the rest of this document
                  1
                  2
                  3
                  4
                  5
                  6
                  7
                  8
                  9
                  10
                  11
                  SupremeToday Portrait Ad
                  supreme today icon
                  logo-black

                  An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

                  Please visit our Training & Support
                  Center or Contact Us for assistance

                  qr

                  Scan Me!

                  India’s Legal research and Law Firm App, Download now!

                  For Daily Legal Updates, Join us on :

                  whatsapp-icon Back to top