IN THE HIGH COURT OF DELHI AT NEW DELHI
Yashwant Varma, Dharmesh Sharma, JJ.
National Projects Constructions Corporation Ltd. (NPCC) - Appellant
Versus
M/s Aac India Pvt. Ltd . - Respondent
FAO (COMM) 140 of 2021
Decided On : 02-11-2023
Arbitration and Conciliation Act - Setting aside impugned judgment - Section 37 of A&C Act, Section 13(1A) of CC Act - [35.0, 35.1 of GC-14; 48.3, 48.4 and 49 of the GC-22] - The court upheld the arbitral award dated 29 August 2016 in its entirety, setting aside the impugned judgment that partially set aside the award on the aspect of payment of liquidated damages.
Fact of the Case:
The appellant, a Government Enterprise, entered into an agreement with the respondent for a project. The appellant claimed that the respondent breached the contract and delayed its performance, leading to the imposition of liquidated damages. The respondent invoked arbitration, and the Arbitrator partly granted the reliefs claimed by the respondent. The award was challenged by the respondent under Section 34 of the A&C Act, and the learned ADJ partially set aside the award.
Finding of the Court:
The court found that the learned ADJ went beyond the scope of Section 34 of the A&C Act and the decision to modify the award was flawed and unsustainable in law. The court upheld the arbitral award in its entirety, setting aside the impugned judgment that partially set aside the award on the aspect of payment of liquidated damages.
Issues: The issues revolved around the imposition of liquidated damages, the interpretation of contract clauses, and the scope of challenge and interference with an arbitral award under Section 34 of the A&C Act.
Ratio Decidendi: The court held that the learned ADJ misconstrued the contents and import of a letter/correspondence, and the reasoning for modifying the award was flawed. The court emphasized that the jurisdiction of the Court under Section 34 is neither in the nature of an appellate nor a revisional remedy, and an award can be set aside on limited grounds.
Final Decision: The impugned order was set aside, and the award dated 29 August 2016 passed by the Arbitrator was upheld in its entirety. The parties were left to bear their own costs.
JUDGMENT
Dharmesh Sharma, J. - This Judgment shall decide the present appeal preferred by the appellant under Section 37 of the Arbitration and Conciliation Act, 1996[A&C Act] read with Section 13(1A) of the Commercial Courts Act, 2015[CC Act] for setting aside the impugned judgment dated 12 March 2021 passed by learned Additional District Judge-03, South District, Saket Courts, New Delhi[ADJ] in ARBTN No.20824/2016, whereby the learned ADJ chose to partially set aside the award dated 29 August 2016 on the aspect of liquidated damages[LD] to be paid by the appellant to the respondent.
FACTUAL BACKGROUND:
2. The appellant, which is a Government Enterprise under the Ministry of Water Resources and also a company registered under the Companies Act, 1956 consequent to letter of intent[LOI] dated 03 March 2017 entered into an agreement dated 13 March 2007 as Project Management Consultant of the Central Reserve Police Force[CRPF] with the respondent, which was a micro enterprise stated to be having a turnover of less than Rs. 10 Lacs, for installation of Fire Protection System for the Auditorium Block, CRPF Campus, Vasant Kunj, New Delhi. The project was stipulated to be completed within a period of 7 months from the date of issuance of LOI for total contract value of Rs. 90,79,200/-. However, performance got delayed.
3. To cut a long story short, the appellant claimed that the respondent was in breach of its obligations under the contract and delayed its performance by taking about 33 months for completion of work, and therefore, in terms of clause 35.5 of the contract, LD was levied and adjusted against the payment payable to the respondent not only for the abnormal delay but also for causing damage to the reputation of the appellant for the delay caused; and accordingly payment for a sum of Rs. 1,13,97,341/- i.e., 10% of the work cost of the CRPF camp project was withheld. The respondent in terms of clause 52 of the 'General Conditions' of the contract invoked arbitration and accordingly Sh. Suresh Chandra Garg, Ex. General Manager of the appellant was appointed as the Sole Arbitrator to adjudicate upon the disputes between the parties vide appointment/nomination letter dated 17 April 2014. The Arbitrator entered upon the reference, conducted the proceedings, and eventually passed the award dated 29 August 2016.
4. After considering the dispute between the parties in light of various clauses of the contract, the Arbitrator partly granted the reliefs claimed by the claimant/respondent as follows:-
'Claim No.1:
The claim for refund of Rs. 9,68,470/- was disallowed after adjusting LD of Rs. 9,17,000/- giving balance of Rs. 51,470/- to the claimant;
Claim No.2:
Claim No.2 for an amount of Rs. 4,47,578- towards the balance of security deposit was allowed;
Claim No.3:
Claim for unfair profit earned by the respondent by utilizing payments received from CRPF against RA bills of claimant amounting to Rs. 1,78,486/- with interest was declined;
Claim No.4:
Direct expenses induced by the respondent towards Pump Operator plus interest besides insurance charges was rejected;
Claim No.5:
Claim for escalation charges and interest upon escalation charges was rejected;
Claim No.6:
Claim for damages of loss of profits and loss as well as goodwill amounting to Rs. 25,00,000/- was rejected;
Claim No.7:
Fair compensation on account of harassment, mental agony and physical harm to the tune of Rs. 5,00,000/- was rejected; and INTEREST:
Interest was allowed on the claim No.1 @ 6% per annum from the date of appointment of the Arbitrator i.e., 17 April 2014 till the date of Award and it was directed that in case interest is not paid within 60 days, it shall carry interest @ 9% per annum from the date of the Award till payment.'
5. Simultaneously, the Arbitrator also dealt with the counter claims of the appellant herein and arrived at the following decision:
(i) Claim for loss of reputation to the respondent/organization to Rs. 1,00,00,000/- was rejected.
(ii) Claim for damages i
Associate Builders v. Delhi Development Authority
Bharat Coking Coal Ltd. v. Annapurna Construction
Dakshin Haryana Bijli Vitran Nigam Ltd. v. Navigant Technologies (P) Ltd.
Delhi Airport Metro Express Private Limited v. Delhi Metro Rail Corporation
Kinnari Mullick v. Ghanshyam Das Damani
M/s. Kailash Nath Associates v. Delhi Development Authority
Mcdermott International Inc. v. Burn Standard Company Ltd.
P.R. Shah, Shares and Stock Brokers (P) Ltd. v. B.H.H. Securities (P) Ltd.
The appeal was allowed, reinstating the arbitrator's award which concluded that the termination of the contract was illegal due to failure in fulfilling mutual obligations concerning site availabilit....
The Court's decision highlights the limited scope of judicial review of arbitral awards under Section 34 of the Arbitration and Conciliation Act, 1996. The Court held that it lacked the authority to ....
(1) Appeal against modified arbitral award – Merits of award are only to be gone into, if award is demonstrated to be contrary to public policy of India.(2) Arbitral proceedings are per se not compar....
Clauses in contracts that prohibit claims for damages are against public policy and void under Section 23 of the Indian Contract Act, 1872, as they undermine the sanctity of contracts.
The court clarified that its jurisdiction under Section 34 of the Arbitration and Conciliation Act is limited to setting aside the arbitral award based on specific grounds and does not extend to modi....
Arbitration Award - An Award however can be interfered with if it is found to be vulnerable under any of the grounds in Section 34 including being in contravention with the fundamental policy of Indi....
The court clarified the limited grounds for interference with arbitral awards under Section 34 and emphasized the importance of timely goods delivery in contractual obligations.
The appellate jurisdiction under section 37 is limited to the grounds prescribed under section 34. Courts cannot re-appreciate evidence or substitute their views for that of the arbitrator, provided ....
The court can set aside an arbitral award under Section 34 if it violates substantive law, contract terms, or public policy, especially when procedural requirements aren't met or if the award is pate....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.