IN THE HIGH COURT OF DELHI AT NEW DELHI
Chandra Dhari Singh, J.
Dedicated Freight Corridor Corporation of India Limited (dgccil) – Appellant
Versus
Tata Aldesa JV – Respondent
O.M.P. (COMM) 104 of 2021 & I.A. 10347 of 2021
Decided On : 24-08-2023
The Court dismissed the petition filed by the petitioner challenging the Arbitral Award passed by the Arbitral Tribunal. The Court held that the petitioner failed to establish that the impugned Award suffered from patent illegality or contravened the fundamental policy of Indian law or public policy of the country. The Court further held that the Arbitral Tribunal had the jurisdiction and power to grant and bestow an interest while passing the Award, given the absence of any preceding agreement between the parties concerning said interest.
Fact of the Case:
The petitioner, a special purpose vehicle established for the purpose of planning and development of dedicated freight corridors, entered into a contract with the respondent for the construction of a railway line. Disputes arose between the parties, which were referred to arbitration. The Arbitral Tribunal passed an Award in favor of the respondent, directing the petitioner to pay the respondent a sum of Rs. 36,24,85,884/-. The petitioner filed a petition under Section 34 of the Arbitration and Conciliation Act, 1996, seeking to set aside the Award.
Finding of the Court:
The Court held that the petitioner failed to establish that the impugned Award suffered from patent illegality or contravened the fundamental policy of Indian law or public policy of the country. The Court further held that the Arbitral Tribunal had the jurisdiction and power to grant and bestow an interest while passing the Award, given the absence of any preceding agreement between the parties concerning said interest.
Issues: Whether the impugned Award suffered from patent illegality or contravened the fundamental policy of Indian law or public policy of the country.
Ratio Decidendi: The Court held that the petitioner failed to establish that the impugned Award suffered from patent illegality or contravened the fundamental policy of Indian law or public policy of the country. The Court further held that the Arbitral Tribunal had the jurisdiction and power to grant and bestow an interest while passing the Award, given the absence of any preceding agreement between the parties concerning said interest.
Final Decision: The Court dismissed the petition filed by the petitioner challenging the Arbitral Award passed by the Arbitral Tribunal.
JUDGMENT
Chandra Dhari Singh, J.
1. The instant petition under Section 34 of the Arbitration and Conciliation Act, 1996 (`the Act' hereinafter) has been filed against the final Award dated 11th September, 2020 whereby the Arbitral Tribunal allowed the claims filed by the respondent/claimant.
FACTUAL MATRIX
2. The petitioner is a special purpose vehicle established in 2006 under the erstwhile Companies Act, 1956, for the purpose of planning and development, mobilizing financial resources, building, maintaining, and operating dedicated freight corridors and is under the administrative control of the Ministry of Railways.
3. The respondent/claimant is an unincorporated joint venture referred to as Tata-Aldesa Joint Venture (`Tata-Aldesa JV' hereinafter) comprising of Tata Projects Limited having office at Secunderabad, India and Aldesa Constructions, a private company incorporated in accordance with the Spanish Laws, having its registered office in Spain.
4. The petitioner undertook a project pertaining to "Design and Construction of Civil, Structures and Track Works for Double Line Railway involving formation in Embankments/Cuttings, Ballast on formation, Track Works, Bridges, Structures, Buildings including Testing and Commissioning on Design-Build Lump Sum Basis for Bhaupur- Khurja Section of Eastern Dedicated Freight Corridor" which was split into three contract packages divided into three lots namely Lot No. 101 for 135 kms, No. 102 for 102 kms and No. 103 for 106 kms.
5. The petitioner invited bids for the aforesaid three contract packages and 14 pre-qualified bidders visited the work site for inspection. The respondent/claimant submitted its bid for Lot No. 103 and was duly awarded the contract vide notification dated 24th January, 2013. Consequently, an agreement dated 08th March, 2013 was entered into between the parties and the deadline for the completion of work was decided to be 21st April, 2017.
6. Thereafter, the respondent/claimant wrote a letter dated 17th July, 2013 seeking clarification from the petitioner regarding the applicability of the size of boxes to be used for crossing roads below railway tracks for the preparation of design, drawing, and execution in accordance with the Contract Agreement. In the said letter, the respondent/claimant also stated that the requirements sought by the petitioner were `variations' which might result in additional time and costs. The petitioner responded to the said letter stating that the respondent/claimant had been handed over the clearances obtained from the State Public Works Department (`PWD' hereinafter) and can approach their office for any explanations or modifications relating to clearances. In the said response letter, the petitioner clarified that the submission of the plan, profile, and drawing should not be delayed owing to the issuance of approvals from the PWD. The response letter further noted that the Contract Agreement was a design and build contract and the respondent was required to build and design the alignment profiles and Roads under Bridges (`RUBs' hereinafter) in accordance with the terms of the Contract Agreement.
7. On 21st November, 2013, a final list of RUBs was executed by the parties and the same was incorporated in the alignment plan and the profile of the respondent/claimant. Thereafter, the respondent/claimant sent the alignment plan and profile to the petitioner for approval with the note that variations in cost and time relating thereto would be sent later.
8. The Engineer appointed by the petitioner rejected the claim with respect to increase in number and change in sizes of RUBs by the PWD vide letter dated 30th May, 2014. It also stated that the General Arrangement Drawings ("GADs") provided as part of the bidding document were indicative and were to be finalized after validation of the survey in compliance with the provisions of applicable Codes which cannot be considered a reason for any significant increase in the quantities.
The scope of interference with an Arbitral Award under Section 34 of the Arbitration and Conciliation Act, 1996 is fairly limited and narrow. The Courts shall not sit in an appeal while adjudicating ....
The limited grounds for interference with an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996, emphasize the concept of patent illegality and the criteria for setting asi....
The Court held that the learned Arbitrator had erred in decreeing the award with respect to the rate of interest, and hence, the Award qua issue no. 20 with regards to the rate of interest is liable ....
The main legal point established in the judgment is the limited scope of interference with an Arbitral Award under Section 34 of the Arbitration and Conciliation Act, 1996, and the requirement for th....
The court affirmed that arbitral awards challenging under Sections 34 and 37 are limited in scope, requiring clear evidence of illegality or perversion; otherwise, the Arbitrator's decision stands.
Limited grounds for interference with an Arbitral Award under Section 34 of the Arbitration Act
The limited scope of intervention by Courts in arbitral awards under Section 34 of the Arbitration and Conciliation Act, emphasizing the need to satisfy specific grounds for setting aside an arbitral....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.