IN THE HIGH COURT OF DELHI AT NEW DELHI
Chandra Dhari Singh, J.
Tehri Hydro Development Corporation India Limited - Petitioner
Versus
C.E.C. Limited - Respondent
O.M.P. (COMM) 577 of 2020 & I.A. 11747 of 2020
Decided On : 26-04-2023
The Court set aside the Arbitral Award only with regard to the rate of interest, where perversity, and thus patent illegality was observed. The Court held that the learned Arbitrator had erred in decreeing the award with respect to the rate of interest, and hence, the Award qua issue no. 20 with regards to the rate of interest is liable to be set aside.
Fact of the Case:
The instant petition under section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter “the Act, 1996”) has been filed on behalf of the petitioner seeking the following reliefs: (a) Set aside the impugned Arbitral Award dated 04.08.2020 passed by the Learned Arbitral Tribunal; Pass such further or other orders as this Hon'ble Court may deem fit in the facts and circumstances of the case in favour of the Petitioner and against the Respondent herein.
Finding of the Court:
The Court found that there was a patent illegality in the impugned Award only in the learned Arbitral Tribunal's decision in issue no. 20, pertaining to the rate of Interest. The Court held that the learned Arbitrator had erred in decreeing the award with respect to the rate of interest, and hence, the Award qua issue no. 20 with regards to the rate of interest is liable to be set aside.
Issues: 1. Whether the learned Arbitrator adjudicated the dispute disregarding the facts and evidences pertaining to the matter? 2. Whether the interest rate specified in issue no. 20 is patently illegal and contrary to the contract? 3. Whether the learned Arbitrator has the power to give out issue wise findings without any issues being addressed by the parties during the course of Arbitration proceedings?
Ratio Decidendi: The Court held that the learned Arbitrator had erred in decreeing the award with respect to the rate of interest, and hence, the Award qua issue no. 20 with regards to the rate of interest is liable to be set aside. The Court found that the learned Arbitrator had passed the impugned Award without considering relevant clauses of the Agreement, and in complete contravention of Section 31(a) of the Act, 1996, while adjudicating on the rate of interest to be granted. Therefore, the impugned Award till the extent of the rate of interest granted, is contrary to provisions of the Agreement, suffers from infirmity and patent illegality.
Final Decision: The Court set aside the impugned Arbitral Award only with regard to the rate of interest, where perversity, and thus patent illegality was observed. The Court held that the learned Arbitrator had erred in decreeing the award with respect to the rate of interest, and hence, the Award qua issue no. 20 with regards to the rate of interest is liable to be set aside.
JUDGMENT :
CHANDRA DHARI SINGH, J.
The instant petition under section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter “the Act, 199”) has been filed on behalf of the petitioner seeking the following reliefs:
(a) Set aside the impugned Arbitral Award dated 04.08.2020 passed by the Learned Arbitral Tribunal;
Pass such further or other orders as this Hon'ble Court may deem fit in the facts and circumstances of the case in favour of the Petitioner and against the Respondent herein.”
FACTUAL MATRIX
2. The facts necessary for the disposal of this instant petition are that the petitioner is Tehri Hydro Development Corporation India Limited, the employer/respondent in the Arbitration and the respondent is M/S C. E. C. Limited, the contractor/claimant in the Arbitration. The petitioner and the respondent entered into a Contract Agreement No. 1/TDC-1/1981-82 for the construction of four circular head race tunnels having a diameter of 8.5m and approximate lengths 1100, 1200, 1450, and 1500 meters leading to bottoms of four underground surge tanks for the underground powerhouse of Tehri Dam Project, on 23rd November 1981. The respondent was sent a notice of commencement of work on 28th November 1981 as per clause 1.4.05 of the Agreement.
3. The respondent vide letter dated 19th September 1987 submitted a Claim of INR 568.4 Lakhs which was rejected by the Engineer-in-charge vide his letter dated 2nd January 1988 after which the claimant invoked the Arbitration Clause. The dispute thus, existed between the parties only for Rs. 568.4 lakhs and which was made the subject matter of reference by the Claimant.
4. A Statement of Claim was filed by the respondent herein before the learned Arbitral Tribunal comprising of Mr. Justices B. Pandey (Retd.), R.N. Misra (Retd.), and Shri R.K. Agarwal on 11th November 1988 followed by Statement of Defence by the petitioner (respondent in the Arbitration) on 7th March 1989. The rejoinder was filed by the claimant/respondent on 15th April 1989.
5. On 7th July 1992 due to the demise of one of the learned Arbitrators, a new Arbitral Tribunal was constituted consisting of new Arbitrators, followed by the demise of another learned Arbitrator on 14th December 1992, and re-constitution of the Arbitral Tribunal.
6. The composition of the learned Arbitral Tribunal has changed on multiple occasions since the foreclosure of the contract on 15th December 1990. On 4th February 2019, Mr. Ram Dayal Gupta was appointed as the learned Sole Arbitrator in the Arbitration proceedings and the first hearing took place on 8th March 2019 before the current learned Sole Arbitrator.
7. The impugned Award was passed on 4th August 2020 and received by the petitioner on 7th August 2020, aggrieved by which the petitioner has approached this Court with the instant petition seeking the aforesaid reliefs.
SUBMISSIONS
(On behalf of the Petitioner)
8. Learned counsel for the petitioner submitted that the impugned Arbitral Award dated 4th August 2020 is in conflict with the fundamental policy of Indian Law and basic notions of justice, and is completely perverse, both factually and legally. It is further submitted that the Impugned Award suffers from sheer non-applicability of mind and is exfacie fraudulent.
9. It is further submitted by Learned counsel for the petitioner that the impugned Award is arbitrary, and passed in utter disregard to facts, documents, evidence, and material on record.
10. It is submitted by learned counsel for the petitioner that evidence has been disregarded in each issue decided by the Arbitrator and that any extra expenditure on account of any idling and/or underutilization of resources, rise in wages, infructuous overheads, was incurred on account of any breach or otherwise by the claimant/respondent.
11. Learned Counsel for the Petitioner submitted that the Learned Sole Arbitrator violated the procedu
Champsey Bhara and Co. v. Jivraj Balloo Spinning and Weaving Co. Ltd. AIR 1923 PC 66
Army Welfare Housing Organisation v. Sumangal Services (P) Ltd.
Bungo Steel Furniture (P) Ltd. v. Union at India AIR 1967 SC 378
Firm Madan Lal Roshan Lal Mahajan v. Hukamchand Mills Ltd. Indore AIR 1967 SC 1030
Hindustan Zinc Ltd. v. Friends Coal Carbonisation
Hyder Consulting (UK) Ltd. v. State of Orissa
Jivarajbhai v. Chintamanrao Balaji AIR 1965 SC 214
Kali Charan Sharma v. Municipal Corporation of Delhi
Krishna Bhagya Jala Nigam Ltd. v. Harischandra Reddy
McDermott International Inc. v. Burn Standard Co. Ltd.
MSK Projects Ltd. v. State of Rajasthan
Satyanarayana Construction Co. v. Union of India
Smt. Santa Sila Devi v. Dhirendra Nath Sen AIR 1963 SC 1677
Ssangyong Engg. & Construction Co. Ltd. v. NHAI
State of Haryana v. S.L. Arora & Co.
State of Madhya Pradesh v. Satyapal Wasson AIR 1979 MP 119
Union of India v. Firm J.P. Sharma and Sons AIR 1968 Raj 99
Vedanta Ltd. v. Shenzhen Shandong Nuclear Power Construction Co. Ltd.
The Court held that the learned Arbitrator had erred in decreeing the award with respect to the rate of interest, and hence, the Award qua issue no. 20 with regards to the rate of interest is liable ....
The Court held that the impugned award with respect to Claim 7 was not well-reasoned as required by the Act under Section 31(3), and the impugned award with respect to the award in Claim 11 is contra....
The limited scope of intervention by Courts in arbitral awards under Section 34 of the Arbitration and Conciliation Act, emphasizing the need to satisfy specific grounds for setting aside an arbitral....
Limited intervention of the Courts in arbitral proceedings is intended by the legislature. An Arbitral Award may only be set aside if it is patently illegal, against the public policy of India, based....
The scope of interference with an Arbitral Award under Section 34 of the Arbitration and Conciliation Act, 1996 is fairly limited and narrow. The Courts shall not sit in an appeal while adjudicating ....
An arbitral award can only be set aside under Section 34 of the Arbitration and Conciliation Act, 1996 if the appellant establishes that the award is in conflict with the public policy of India, is p....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.