SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2024 Supreme(Del) 798

IN THE HIGH COURT OF DELHI AT NEW DELHI
VIBHU BAKHRU, SACHIN DATTA, JJ.
Indian Oil Corporation Ltd. - Appellant
Versus
M/s Fiberfill Engineers - Respondent
FAO (OS)(COMM) 114 of 2019 and CM No.24305 of 2019
Decided on : 20-11-2024

Advocate Appeared:
For the Appellant :Mr Huzefa Ahmedi, Sr Advocate with Ms Mala Narayan, Mr Shashwat Goel, Mr Rohan Sharma and Ms Isha Ray, Advocates.
For the Respondent:Mr Amit Gupta, Mr Kshitij Vaibhav, Ms Muskan Nagpal and Mr H. S. Mahapatra, Advocates.

IMPORTANT POINT
The court emphasized that for liquidated damages to be enforceable, the claimant must prove actual loss and the clause must represent a genuine pre-estimate of damages.

Headnote:

(A) Arbitration and Conciliation Act, 1996 - Section 34 - Intra court appeal against arbitral award - The learned Single Judge set aside the arbitral award rejecting Fiberfill's claim for Rs.22,08,528/- withheld by IOCL, holding it vitiated by patent illegality for lack of findings on damages suffered by IOCL due to delay. (Paras 28, 52)

(B) Contract Law - Liquidated Damages - The court reiterated that for a claim of liquidated damages, the party must establish that it suffered loss, and the clause must be a genuine pre-estimate of damages. (Paras 43.1, 52)

Facts of the case:

The dispute arose from an agreement for installation of high mast signage systems, where IOCL withheld payment citing delays in execution. Fiberfill challenged the arbitral award that rejected its claims.

Findings of Court:

The court found the arbitral tribunal's award flawed for not establishing that IOCL suffered any loss due to delays.

Issues: Whether IOCL was entitled to withhold payment as liquidated damages without proving actual loss.

Ratio Decidendi: The court held that the arbitral tribunal erred in awarding damages without evidence of loss, emphasizing the need for a genuine pre-estimate of damages in liquidated damages claims.

Result: The impugned award was set aside.

JUDGMENT :

VIBHU BAKHRU, J

1. Indian Oil Corporation Ltd. (hereafter IOCL) has filed the present intra court appeal under Section 37 of the Arbitration and Conciliation Act, 1996 (hereafter the A&C Act) impugning an order dated 29.03.2019 (hereafter the impugned order) passed by the learned Single Judge in OMP(COMM) No.303/2017 captioned Fiberfill Engineers v. Indian Oil Corporation Limited. The respondent (hereafter referred to as Fiberfill) had filed the aforementioned petition under Section 34 of the A&C Act for setting aside an arbitral award dated 12.04.2017 (hereafter the impugned award) rendered by the Arbitral Tribunal (hereafter the Arbitral Tribunal) comprising of a Sole Arbitrator.

2. The impugned award was rendered in the context of disputes that had arisen between the parties in connection with an agreement dated 11.01.2007 for designing, supplying, installation, testing and commissioning of high mast signage systems of various heights and types at various IOCL retail outlets in the State of Tamil Nadu and Union Territory of Pondicherry (hereafter referred to as the Work Order).

3. Fiberfill had made five claims, which were the subject matter of arbitration before the Arbitral Tribunal. The same included a claim of Rs.22,08,528/- being an amount that was deducted by IOCL towards price adjustment from the bills raised by Fiberfill for the work done; interest at the rate of 18% on the sum of Rs.22,08,528/- from the date the amounts were withheld by IOCL till the actual date of release; Rs.75,50,000/- towards Escalation; Rs.1,50,00,000/- towards Loss of Business Opportunity; and Rs.80,00,640/- towards Manpower Retention. The Arbitral Tribunal rejected all the aforesaid claims and found that Fiberfill is not entitled to any relief.

4. During the course of proceedings relating to Fiberfill’s petition for setting aside the impugned award under Section 34 of the A&C Act, Fiberfill had confined its challenge to the impugned award to the extent of denial of its claim for the amount of Rs.22,08,528/- withheld by IOCL and the interest payable thereon. The learned Single Judge sustained the said challenge and set aside the impugned award to the extent that it rejected Fiberfill’s claim for the amount of Rs.22,08,528/- and interest thereon. The learned Single Judge held that Fiberfill is entitled to the sum of Rs.22,08,528/- along with interest at the rate of 8% per annum from the date the amounts were withheld till the date of release.

5. The amount of Rs.22,08,528/- was withheld by IOCL in terms of Clause 9 of the Special Instructions to Tenderers (hereafter SIT) as compensation for delay in performance of the work. The learned Single Judge faulted the Arbitral Tribunal for accepting IOCL’s claim for compensation on account of delay in execution of the works without returning any finding that IOCL had suffered damages on account of delay or that the amount withheld was a reasonable compensation for the delay in execution of the work on the part of Fiberfill. The learned Single Judge held that to the aforesaid extent, the impugned award was vitiated by patent illegality. The Arbitral Tribunal ignored the relevant material and also awarded liquidated damages by way of price adjustment without recording a finding as to whether IOCL had suffered any loss or injury.

6. The controversy in the present appeal is, thus, confined to the question whether the Arbitral Tribunal had erred in rejecting Fiberfill’s claim for the amount of Rs.22,08,528/- withheld by IOCL as compensation by way of reduction in price payable for the work done.

FACTUAL CONTEXT

7. IOCL is a Public Sector Undertaking, inter alia, engaged in the business of distribution of Oil and Petroleum Products. IOCL had invited tenders for designing, supplying, installing, testing and commissioning of the high mast signage systems of various heights and types at its various retail outlets in the State of Tamil Nadu and the Union Territory of Pondicherry. The invitation was, essential

      Click Here to Read the rest of this document
      1
      2
      3
      4
      5
      6
      7
      8
      9
      10
      11
      SupremeToday Portrait Ad
      supreme today icon
      logo-black

      An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

      Please visit our Training & Support
      Center or Contact Us for assistance

      qr

      Scan Me!

      India’s Legal research and Law Firm App, Download now!

      For Daily Legal Updates, Join us on :

      whatsapp-icon telegram-icon
      whatsapp-icon Back to top