SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img



IN THE HIGH COURT OF DELHI
Vibhu Bakhru, Amit Mahajan, JJ.
Wapcos Limited - Appellant
Versus
C & C Energy Private Limited - Respondent
FAO (COMM) 53 of 2021
Decided On : 20-10-2022




An arbitral award is not subject to re-evaluation of the merits as long as it does not contravene public policy; parties are entitled to payments as per contractual obligations fulfilled, irrespective of external project delays.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - Appeal against the rejection of applications under Section 34 - Application dismissed as none of the grounds fell within the limited scope of Section 34 - Court upheld the Arbitral Tribunal's award to C&C for services rendered, stating C&C had performed its obligations under the Agreement. (Paras 16-32)

(B) Legal principles relating to the interpretation of contract terms in arbitration - C&C entitled to full remuneration despite incomplete work; payments contingent on the provision of manpower rather than project milestones. (Paras 20-28)

(C) Findings of the Commercial Court - The Arbitral Tribunal's decision was not patently illegal; C&C entitled to consideration as per the Agreement, and interest awarded was within discretion of the Tribunal. (Paras 29-30)

Table of Content
1. contractual relationship and obligations (Para 2 , 3 , 4 , 5 , 6 , 7)
2. claims and counterclaims submitted in arbitration (Para 8 , 9 , 11)
3. grounds for application under section 34 of the a&c act (Para 10 , 12 , 13 , 14 , 15 , 16)
4. analysis of the scope of services and payment terms (Para 19 , 20 , 21 , 22 , 23 , 24 , 26 , 27 , 28)
5. conclusion of the appeal process (Para 29 , 30 , 31 , 32)

JUDGMENT

Vibhu Bakhru, J.

1. M/s Wapcos Limited (hereinafter `Wapcos') has filed the present appeal under Section 37(1)(c) of the Arbitration and Conciliation Act (hereinafter `the A&C Act') impugning a common judgement dated 31.07.2020 (hereinafter `the impugned judgement') passed by the learned Commercial Court, whereby it had rejected the applications filed by Wapcos and M/s C & C Energy Private Limited (hereinafter `C&C') under Section 34 of the A&C Act. The parties had preferred their respective applications, impugning the award dated 13.06.2019 (hereinafter `the impugned award') to the extent that they were aggrieved. Wapcos assails the impugned judgement to the limited extent that it rejects its application under Section 34 of the A&C Act [being OMP(Comm) No. 167/2009 captioned M/s WAPCOS Limited vs C & C Energy Private Limited].

Factual Background

2. On 18.09.2012, the Energy Water and Sanitation Authority of Rwanda (EWSA, Rwanda) awarded a contract to Wapcos for "supervision of engineering-procurement-construction of 15 MW peat- to-power plant in Rwanda" (hereinafter `the Project').

3. Thereafter, on 21.01.2013, Wapcos and C&C entered into an agreement (hereinafter `the Agreement'), whereby C&C agreed to assist in the supervision of the Project. The Agreement was for a term of fifteen months from the date of execution of the Agreement, that is, until 20.04.2014. In terms of Article 9 of the Agreement, the remuneration and payment for the services was fixed at Rs.1,64,43,000/-, excluding all taxes against the provision of manpower for carrying out the tasks.

4. The scope of work to be performed by Wapcos and C&C was contingent upon the work executed by the Engineering Procurement Construction (EPC) Contractor engaged by EWSA, Rwanda. The EPC Contractor delayed in completing its work, rendering Wapcos and C&C unable to complete their work within the stipulated period of time. The parties were only able to complete 50% of the work within the stipulated period of fifteen months.

5. C&C contends that on account of failure of the EPC Contractor to complete its work in time, it sent a letter dated 17.03.2014, requesting for an extension of time for a period of six months or until the completion of the erection of plant by the EPC Contractor. C&C also stated that the financial remuneration for this would be agreed mutually. C&C states that it continued to work and provided seventy-six (76) additional man-days for the work. Thereafter, it withdrew its manpower.

6. C&C raised invoices amounting to Rs.1,86,44,882/-. Against the said invoices, Wapcos only paid an amount of Rs.1,16,57,067/-. The remuneration for the additional man-days provided by C&C amounted to Rs.13,68,684/-, against which Wapcos did not make any payment.

7. Thereafter, disputes arose between Wapcos and C&C regarding the payment of the balance amount. After no result came from trying to resolve the disputes amicably, C&C invoked the agreement to refer the disputes to arbitration, in terms of Article 11.5 of the Agreement. However, the parties failed to agree on the appointment of an arbitrator. Thereafter, C&C, by way of a petition under Section 11 of the A&C Act, approached this Court for appointment of an arbitrator. By an order dated 30.05.2017, this Court referred the parties to the Delhi International Arbitration Centre (DIAC). The Arbitral Tribunal was constituted under the Rules of the DIAC.

Arbitration

8. Before the Arbitral Tribunal, C&C filed its Statement of Claims. The claims made by C&C in the Statement of Claims are tabulate




Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top